Detailed explanation of validate scope and easy to understand.
@RajendraKumar-xt9yn3 жыл бұрын
Thank you sir for clarifying Validate scope... I was always confused because of IT terms of SIT and UAT that we use in our projects.
@shekharsawant43914 жыл бұрын
The business representative along with project team is in the process of verifying the project’s scope. Which of the following best describes what they will need? A. Project Charter, requirements documentation, requirement traceability matrix B. Project Management Plan, requirements documentation, validated deliverable, requirement traceability matrix C. Project Management Plan, work performance information, requirements documentation, requirement traceability matrix D. Project scope state