*right click and link button* - are we joke fore you? 😅
@pradeepadyapady340810 ай бұрын
Yes easiest option😊
@arcticpika Жыл бұрын
Thank you!
@PlanAcademy Жыл бұрын
You're very welcome. Glad we could help!
@reginaldibenne687525 күн бұрын
Very helpful. Pls, Michael..How is Productivity rate calculated? Is is per one labour or per labour crew in that particular activity..For example, In Painting Activity that has quatity of 1000 square meter and the productivity is 100 meter square/day. is this 10 meter square/day for one labour(painter)? Again, must we need to add the labour helper is our resource-loading?
@samratvchakraborty5157 Жыл бұрын
Great
@reginaldibenne68752 ай бұрын
Then, how do we add or adjust the lag?
@PlanAcademy2 ай бұрын
That can only be adjusted using relationship tab on the bottom.