Thanks a lot! You are doing great job!!! really helpful
@PlanAcademy2 жыл бұрын
Our NEW Progressing Course just launched! Check out the best Advanced P6 Training available online: www.planacademy.com/
@jahangirhussain6297 Жыл бұрын
Thank you Michael. On your point about visibility of links between two projects ; if you run a relationships report, and then run an activity report and combine them in powerbi you can get a quick way of highlighting all the logic links between any number of projects. I tend to use a chord diagram for this. I also have a question, as when I have made a baseline of a project and then restore that baseline to make a monthly snapshot, my logic links between projects tend to get duplicated. Is there a way to avoid this?
@ekharinkhunrat49325 ай бұрын
Hi do you have any Project reference used P6
@larsm978 ай бұрын
How would you use Reflections for interlinked projects? Is this even possible, as normally you can only create a reflection one project at a time?
@wendygriffiths9829 ай бұрын
Hi Michael, if you link two projects. when you do an update for a following period does the project ID have to be the same or does it look at activity ID only
@gazrowan Жыл бұрын
Do all projects have to have the same schedule settings? Like retained logic? What happens if one project is retained logic and one is actual dates?
@PlanAcademy Жыл бұрын
Projects have their own Schedule settings - saved with the project. So unique settings for each project if you like.
@gazrowan Жыл бұрын
@@PlanAcademy sorry, I meant when creating an IMS. If I have say 4 projects that I need to combine to make an IMS, do they all need to have the same schedule settings? Same DD and same schedule setting (i.e retained logic)
@julioguzman805 Жыл бұрын
Hi Michael, nice video. Do you know how to deal with this P6 message: "There are multiple projects open which have conflicting scheduling options. Do you want to schedule all open projects using the scheduling options configured for ....?" ? I guess it is a bug.
@nohandlebarmtb2 жыл бұрын
Hello, How about importing relationships from two different projects with Excel
@armandpatry6744 Жыл бұрын
Hello, Just one question, what about the progress line in case of multi projects ? If the baselines are set at the same date, is it working ? Thank you ! Armand
@PlanAcademy Жыл бұрын
Progress is line is calculated per activity, so it should work when working with multiple projects. There is a setting for it. Right-click in Gantt -> Bar Chart Options -> Progress Line tab. Most popular is to set it to compare current / baseline "Finish Date".
@nazirahmad47122 жыл бұрын
How to create IMS?
@sajumon39473 жыл бұрын
When i import a MS Project XMl file in Primavera P6 18v MS-Project: 1FS +10 Days In other words a relationship which is FS + 5 days in MSP Imports as FS +3000d in P6. Primavera : Lag 4800 - not proper