You not only taught what it does, but you explained it's purpose and the differences to the other critical path method, which gave the ultimate clarity. Bravissimo!
@shkaushal8 жыл бұрын
I watched many presentations on CCPM however this is by far best in term of clarity and content.
@anthonyowolabi7 жыл бұрын
I agree Shweta!
@ProjectManager4 жыл бұрын
That's amazing to hear, Shweta! Thanks so much!
@xingchunmeng3 жыл бұрын
Thanks for a Clear and straightforward session!
@ProjectManager2 жыл бұрын
Thanks for watching!
@nps1153 жыл бұрын
After a couple of iterations team adjusted by providing a 2x longer scheduling estimates :)
@giantcat43543 жыл бұрын
That's a really useful explanation, thank you. You hit all the main points concisely and clearly.
@SigmaPMConsulting-i4w22 күн бұрын
Best explanation ever!
@BadarSyed4 жыл бұрын
Excellent, simple and to the point explanation
@davidaustin69628 жыл бұрын
Robotically cutting their expected completion time by 50% is a great way to loose your best employees. Instead you should explain to them the urgency, ask them for a best case and worst case, and then expect from them the best case, but your buffer is added by (worstcase - bestcase)/2 for each task. Everything else he says is good. Shareholders have a expected delivery date of bestcase plus percentage buffer or buffer left whichever is less (if you are halfway through and buffer is gone then you need to crash or fast-track to get back the lost buffer). Also, you should always refer to your used or remaining buffer status in terms of percent, not hours.
@harineemosur65306 жыл бұрын
David Austin Absolutely right.This is a common trend in Fixed bid projects where it can got 40-60, burn out the resource to achieve excess profit.
@sariuitto5 жыл бұрын
Yeah I was also wondering about that, how can you just cut 50% off. That will have the employees just add extra days in their estimates in the future to get the time they need, since the trust is gone. The problem is here that there is no urgency, it is a made up one. And that would happen in each of the projects that they do, not just one. That will backfire sooner or later. I do think that this (worstcase-bestcase)/2 is a good middle ground to solve this as I think there should be some sort of a buffer.
@AaronG3034 жыл бұрын
I totally agree with David A's comment "cutting 50% is a great way to lose your best employees". I can attest to this experience. Disclosure and communication is one of the greatest asset for an organization (Organizational Behaviors 101). Its disturbing that on one hand students are taught the best method to piece together WBS, amount of effort etc is by drawing on those who actually execute the work. In my view, dependent on the level of trust, honesty and professionalism, those asked to provide the estimates would take it as a great professional insult that PM would naturally assume their estimates are inaccurate (cutting their estimates by 50%)! This is why there exists a great divide between execution and project management! I have experienced this time and time again, builds discord, distrust of management and permeates through-out the organization, obliterates motivation, breeds contempt. No wonder thier are statistics supporting significant numbers relating disengagement!! This theory in reality (particularly) is highly questionable as I have witnessed first hand.
@AaronG3034 жыл бұрын
....also, for a PM to focus on the burn rate of the "buffer" only serves to favor the outcome for the Client and the PM's (his organizations) reputation. Those on the Project Team are surely "team players" however, clearly it is recognized some teams within the project teams can be clearly unproductive/inefficient (at time struggle to meet baseline) and take advantage of those teams and individuals who consistently perform! Once again this is poisonous to an organization if this is not recognized by the responsible PM or addressed by responsible Functional Managers. Recognizing performance and attending to under performance is just as important as fixation with the burn rate of the buffer.
@rachelfernandes25454 жыл бұрын
This is explained so well! Got a presentation regarding this topic and I'm so glad it has cleared my conepts.
@ProjectManager4 жыл бұрын
so glad to hear it was of use!
@iliakherrera74169 жыл бұрын
Excellent video, help me a lot on a assigment!!!
@tracya5194 Жыл бұрын
So helpful🙏
@EmmanuelHemmings4 жыл бұрын
I worked with a Senior PM who did CCPM, except he neglected to actually promote the buffer date and instead pushed for the 50% reduced date.... you guess how long his dev team stuck around.
@tootrue65297 жыл бұрын
Excellent presentation. I now have a good understanding of the CCPM concept and its use. Thank you so much!
@ProjectManager4 жыл бұрын
Thanks for watching!
@sarahmawell98767 жыл бұрын
Thank you for the overview on CCPM.. very good example... well done ..
@Paki14W3 жыл бұрын
Thank you so much
@saianookumar9 жыл бұрын
Excellent explanation. Thanks a lot!
@rizihsan9 жыл бұрын
Should the original timeline and buffer be kept a secret from the project team and only used for upwards communication?
@jaybakst1216 жыл бұрын
No! If anything, it is more important that it be thoroughly communicated with the project team. One of the difficulties in making introductory videos on Critical Chain (and this is a very good one) is that it is easier to explain that we cut task estimates than it is to explain why we cut task estimates. One big part of this is that estimates are just that, estimates! When I worked in 'traditional' PM, If I gave an estimate of 40 hours to complete a task, I expected that I would finish within the 40 hours. I knew that if I were late, then the next task would start and probably finish late. A quick cost benefit analysis told me that it was better to finish early than late. No one ever gave me kudos for finishing early and I received several 'what happened' when I was late. Experience has shown that people give an estimate that they can hit about 85% of the time.This is not being coy or unethical, it was my realistic estimate of when I was very confident that I could finish. Experience has also shown that the variability in these estimates effectively doubles the time to complete. Part of this is the CYA above and part is due to multi-tasking with my other project responsibilities. What never seems to come across in these videos is that after an organization has used CCPM for a while, and people understand that they are to provide 50% vs. 85% estimates, and they do not get yelled at when finish an individual task late, then they start to give aggressive dates to begin with and the buffer is added to their estimate (usually at a 50% add-on). This effectively is the same thing as described in the video with the 'cut 50%' part removed. Getting back to your question, for this to evolve successfully, the project team needs to understand the culture change required for CCPM.
@NoahTheKing79 жыл бұрын
is taking time from the schedule called crashing? as far as i know crashing is adding more resources and overtime to cut time
@ashleywolf55229 жыл бұрын
I believe he meant collapsing but crashing can be used interchangeably. He isn't referring to crashing as a form of schedule compression
@Simply_the_Best_One5 жыл бұрын
Crashing is using additional resources for additional money, you can't crash if you're overbudget. Simple is that. You can also fast-track (lead) activities, I.e. working in parallel several activities, but sometimes it might harm the quality of the project.
@shivanisorakhe45895 жыл бұрын
very helpful video it is!! Thanks
@ProjectManager4 жыл бұрын
So glad it could help!
@MrTchann443 жыл бұрын
well explained
@holyonfire8 жыл бұрын
Thank you for this! It was very helpful.
@ashleywolf55229 жыл бұрын
Nicely explained. Thank you
@Cold-er8 жыл бұрын
When I typed in "Chain Thinking" I wanted to see if there was anyone else that did it. What I mean by chain thinking is sometimes I start thinking about something then end up thinking about something totally different. For example, I think about Basketball then end up thinking about Chinese board games. I can't really explain it just happens.
@OutOfTheBoxThinker8 жыл бұрын
If you want to learn more about the phenonemon you're describing and how to utilize it in a creative process, you might want to look into the concept of "mind mapping" ( en.wikipedia.org/wiki/Mind_map )
@vdsingh2learn8 жыл бұрын
Thanks, nice explanation ..
@MrEngrfarhansiddiqui9 жыл бұрын
Thank you Brother
@jimhodgson58513 жыл бұрын
Thanks for the video - very helpful. Can I just query the way in which 'crash the schedule' was used here - as in PMP we are taught that this means adding more resources to compress the schedule, however in this example 'crashed schedule' meant something else?
@massaro2311909 жыл бұрын
Very helpful. thank you.
@RaghuKasturi10 жыл бұрын
nice video! thank you!
@JonKGKeys8 жыл бұрын
This was FANTASTIC!! You are a great communicator and I would think this method suits better than Critical path as that is more rigid and introduces possibilities for less or more effort from the project team. Love it!
@ProjectManager4 жыл бұрын
Thanks so much for watching! Glad you enjoyed!
@miedono9 жыл бұрын
Thanks. The white board is a very effective tool for explaining the CC concepts.
@xzotzvvs64929 жыл бұрын
Perfect
@batirk18996 жыл бұрын
It won’t work. Consider this, the Resource A (R.A) estimates time to complete Work Package 1 (WP.1) in T time. The PM compresses schedule for WP.1 to T/2 time (plus T/2 buffer). Now, R.A will finish late and use buffer time, or finish in T/2 time and submit incomplete work with hidden errors. R.A knows he/she is now underperforming and feels bad about it. For the next Work Package B, R.A will submit time estimate of 2T. The PM will half it to T and allocate a buffer T. This will allow R.A to comfortably complete WP.2 on time. It will also wise up other resources to use inflated numbers in their estimates. Great, isn’t it? Another problem is, what happens if there is dependency, if R.A has to hand in completed WP.1 to Resource B. As I mentioned above, Resource B will either receive incomplete package on time, or will have to delay working on WP.1 because R.A is late and is using extra time from buffer. Also, this completely goes against principles of agile (self-organizing teams, and what not).
@vutsxx4 жыл бұрын
Yeah, CCPM is totally different than Agile. I dont like it, it can be put to work, but its just a mess system that ensure that the PM is blind to problems until the fever chart is on red.
@JohnMorleyJT7 жыл бұрын
I can't see how your software using TOC's CCPM methodology??? It's just only Gantt stuff???
@ProjectManager7 жыл бұрын
If you have a technical question, please send it to support@projectmanager.com. Thanks.