After 2 years of reconstruction, the northbound tracks 3 and 4 have opened. This marks the halfway point of the Lawrence to Bryn Mawr portion of the Red and Purple Modernization project (RPM). With Phase 1 completed, now the old tracks 1 and 2 will be demolished and rebuilt using pre fabricated concrete segments being put in place with a gantry system.
New temporary stations have been built at Foster (Argyle), and a southbound only Bryn Mawr station.