Where the project resilience falls? for emergent risks (unknowable-unknowns) within the baseline? Great videos btw.
@davidmclachlanproject4 жыл бұрын
Great question. Contingency reserves are built into the cost or schedule baseline, for planned risks. Management reserves are added on top of the cost baseline for the "unknown unknowns". Increasing project resilience could come from either or both, plus improving processes / team etc. The burndown chart would typically be referencing the baselines though.