hi, is V model and Agile applicable for same project at a time?
@AutomationTestingInsider Жыл бұрын
I don't thik combining both agile and v model for the same project is a good idea. It depends on your needs of the project. Basically in Agile model, the coding and testing phase gains more focus than the design phase. And In V-model, the design phase gains more focus than the implementation phase.
@maheshbabu637 Жыл бұрын
@@AutomationTestingInsider okay thanks for the clarification
@AutomationTestingInsider Жыл бұрын
On the other hand It is possible to combine the Agile and V Model approaches in a hybrid approach, where the Agile approach is used for the development phase, and the V Model is used for the planning, testing, and deployment phases. This can be useful in situations where the project requires a high level of structure and discipline, but also needs to be able to respond to changes and adapt to new requirements.