Estimates: Bills of Quantities & Unit Price Analysis

  Рет қаралды 45,604

A Coffee Talk with Maestro

A Coffee Talk with Maestro

Күн бұрын

Пікірлер: 153
@archreyona
@archreyona 4 жыл бұрын
NOTES materials - direct cost at bill of materials form, labor cost by percentage 30 to 45% of materials cost 1. costings, unit price analysis, dont forget 15% profit margin + vat 2. hourly rate for labor/personnel 3. unit cost derived from unit cost analysis x qty. 3. rules of measurement and trade preambles at bid doc 4. bills of preliminaries - overhead, other cost and expenses- separate from line items Huge thanks for detailed insights between boq, bop (both for estimators copy/eyes only) and bom for client.
@jakdee4732
@jakdee4732 4 жыл бұрын
Thank you so much Maestro, very informative in promoting the practice of our profession, Mabuhay po kayo, God bless you and more power
@ricwaters4860
@ricwaters4860 4 жыл бұрын
great video sir. sakto ito po yung nirereview ko gawin. great help Architect.
@Ma3stro-752
@Ma3stro-752 4 жыл бұрын
Welcome
@joeysaavedra56
@joeysaavedra56 3 жыл бұрын
Comprehensive & correct info Architect, been under in PMCM before, I also like CSA as we're exposed to it..though am an EE, the concept is still applicable. God bless!
@rolandoobias2834
@rolandoobias2834 4 жыл бұрын
Sir marami pong salamat at marami po akong natutunan sa subject na ito.God bless you sir.
@999xantAnas
@999xantAnas 3 жыл бұрын
A new subscriber here. I'm a Mechanical Engineer but our PM asking me to this
@benzonjhermogeno
@benzonjhermogeno 4 жыл бұрын
thank you for the Information Architect. Kindly share the format of BOQ, I would appreciate it thus it is a big help to young qs like me
@jameskalaw9049
@jameskalaw9049 4 жыл бұрын
Thanks a lot maestro. Mas madali intindihin to😍
@jameskalaw9049
@jameskalaw9049 4 жыл бұрын
jameskalaw@gmail.com Thank you in advance para sa format maestro🥰
@mlmengineering3204
@mlmengineering3204 4 жыл бұрын
Nice sir alfred, narefresh ang knowledge ko sa QS, Thank you!
@AB-tn3fd
@AB-tn3fd 4 жыл бұрын
thank you po. kaka start ko lang magwork, and this is very informative po.😊
@ianjurylreyes7992
@ianjurylreyes7992 4 жыл бұрын
thank you po Architect! new subsciber po from pampanga.
@cheryldc9489
@cheryldc9489 3 жыл бұрын
Very on point. Common mistakes talaga ng mga estimator yan, di nako-consider yung actual site conditions. Pag nakikita ko yung quotations nila, andaming kulang na costing like yang equipments and trucks needed kasi puro direct estimates lang ginagawa hehe. 🙂 Thanks for this video, very informative. Napa-subscribe tuloy ako haha 😁
@Ma3stro-752
@Ma3stro-752 3 жыл бұрын
Thanks
@konstrakph
@konstrakph 2 жыл бұрын
Thank you so much Architect!
@carlorillera6400
@carlorillera6400 3 жыл бұрын
Thanks for the information Architect. I'm a new fan & subscriber here. But I just want to make clarification or verification. I think the no.of hours is not the rate of the mason & helper, it's the no. of hours to complete the 102.14 sq.m CHB laying. and the hourly rate is the rate per hour of the the workers. Then multiply it to no.of hours and no.of personnel equals the total amount. But overall topic is amazing and very informative. More power to you and God bless.
@artemplatesales
@artemplatesales 4 жыл бұрын
Hi architect, morning podcast ko po eto today.
@johnespelimbergo1185
@johnespelimbergo1185 4 жыл бұрын
New subscriber here architect! Waiting for more uploads 😊
@architectkas2597
@architectkas2597 4 жыл бұрын
very well explained sir, keep it up, more power to you sir, worth subscribing! :)
@Ma3stro-752
@Ma3stro-752 4 жыл бұрын
Welcome and thank you din.
@architectkas2597
@architectkas2597 4 жыл бұрын
@@Ma3stro-752 sir maestro pwede po ba ako maka hingi ng format niyo base sa mga na explain niyo sa video? :)
@architectkas2597
@architectkas2597 4 жыл бұрын
sarmiento.kenn@gmail.com
@kvc2334
@kvc2334 4 жыл бұрын
Very helpful Mabuhay po kayo
@Ma3stro-752
@Ma3stro-752 4 жыл бұрын
Your welcome and thank for watching my vlog.
@nathanielfrancisco2746
@nathanielfrancisco2746 4 жыл бұрын
Thank you Maestro
@paupolintan4806
@paupolintan4806 4 жыл бұрын
Sir i would like to ask. Magkano ang singil ng Architect for Preliminary costings/Bill of quantities/specification documents only... What is the basis for professional fees ? Per sqm ? Per sheets ? Or kasama na sa package ng working drawings. Thank you very much po.
@japroncualno8815
@japroncualno8815 2 жыл бұрын
TO OUR IDOL MAESTRO SANA PO MAKA GAWA KAYO NG LATEST VLOG SA BOM AT BOQ NEW PRICES PER SQM AS BENCHMARK PO PLEASE. PAKI SHOUT NYO NARIN PO KAMI NA PAULIT ULIT NA NANONOOD SA MGA VLOGS NYO PO DAHIL NAPAKA TRANSPARENT PO AT VERY INFORMATIVE AT MAKATOTOHANAN PO. MARAMING SALAMAT PO. FROM YOUR AVID FOLLOWERS - A. M. TULABUT CONS & SERVICES / SGMCKB ENTERPRISES
@daryljayraboy1584
@daryljayraboy1584 4 жыл бұрын
Maestro. Thank you
@ryukimura7302
@ryukimura7302 9 ай бұрын
Sa work ko na din na discover yan sir nasa dpwh ako gagawa kami ng pow(program of works)/abc(approved budget for the contract) at dupa(detailed unit price analysis) d ko na alala na discuss yan sa bldg tech
@robindeguzman8049
@robindeguzman8049 Жыл бұрын
Hi Sir, kapag may BOQ po ba most likely accurate po ba ung details na binibigay ng nagdesign ng plans?
@remilopingol709
@remilopingol709 4 жыл бұрын
Sir meron bang safe standard percentage or rule of thumb para maassess yung cost ng equipment to be used in relation to materials. Like what you said po yun labor is between 35 to 45 percent of the material cost. How about kaya sa equipment? Sir tanong ko rin ano pong percentage ang tama for contigencies saka yun contractors profit? Thank you so much po.
@Ma3stro-752
@Ma3stro-752 4 жыл бұрын
ACEL Equipment handbook
@kristinelei1511
@kristinelei1511 11 ай бұрын
Architect good day po, tanong lang po kung yung 15% po ba na mark up sa unit cost ay bukod pa po sa 10% contingency input? Thank you in advance po.
@jovinmilitar9362
@jovinmilitar9362 3 жыл бұрын
sir specifications ba ang rules for measurements and trade preambles? tnx po. saan po mkakakuha ng rules for measurements and trade preambles?
@Ma3stro-752
@Ma3stro-752 3 жыл бұрын
No. Its a different document
@ferdinandalitagtag5343
@ferdinandalitagtag5343 4 жыл бұрын
Hi Ar Maestro nangungulit po ulit 😅. Im under Diversified Working Experience and im still not fully knowledgeable in terms of Project Estimates. Can you please send a pdf file of BOQ and a sample Bill of Prelimenaries for my study reference😍. Thank you in advance. MORE POWER PO TALAGA MAESTRO😊😊😊
@anishchandran7383
@anishchandran7383 3 жыл бұрын
Sir, do you provide online traning???
@remilopingol709
@remilopingol709 4 жыл бұрын
Sir baka naman meron kang downloadable xcel file nyan Sir. Malaking tulong for fellow architects yan. Shout out Sir. Always watching your video. Architect Mel Pingol here ng Bulacan.
@johnpaulmichaelrodulfo6992
@johnpaulmichaelrodulfo6992 4 жыл бұрын
Hello maestro, suggestion ko po, sana mas naka zoom in yung nasa papel para clearer. Parang ganun po sa mga live streamer ng online games ang setup. Suggestion lang po. Thank you.
@carloaborde
@carloaborde 11 күн бұрын
Saan po mahahanap yung documents na itu? yung rules of measurement and trade preambles?? salamat po
@remilopingol709
@remilopingol709 4 жыл бұрын
Sir yung computation mo ng cost estimate / bill of materials for building permit application. Sinasama mo po ba doon yun 15 percent profit na nabangit mo sa vlog na ito o sa client na yun?
@roastertruck
@roastertruck 4 жыл бұрын
Bakit nilagyan pa ng profit margin yung materials? Diba dapat labor nalang ang pinagkaka kitahan?
@marvinesteron9914
@marvinesteron9914 2 жыл бұрын
thank you sir
@xianwhite5538
@xianwhite5538 2 жыл бұрын
Ar. Pwedi po ba sa BOM hindi na Detailed ang Labor Cost sa Last Part nalang po ilalagay lumpsum na for Example 40% sa materials Cost?
@rodcenmarieescamilla3804
@rodcenmarieescamilla3804 3 жыл бұрын
Sir, regarding sa UPA, yung (Estimated Direct Cost, EDC) di ba dapat include pa yung OCM, Profit, Tax, Mob./Demob..then Total Cost divide Qty..
@prempatel1777
@prempatel1777 4 жыл бұрын
Sir If bill quantities 100 and we received goods 90 what's journal entry
@Ma3stro-752
@Ma3stro-752 4 жыл бұрын
If it is a lump sum contract, the 90 received shall be converted into 100.. If it is remeasuravle still rhe entry should be 100... Unless it is aa product of value engineering... Soon in completion, there should be a re-alignment of cost in determining final account of the Contractor prior to close out of the project and that account must be recorded as an ajusted to to actual accomplishment of the work.
@prempatel1777
@prempatel1777 4 жыл бұрын
@@Ma3stro-752 I have to maintain stock with 100 quantities?
@Ma3stro-752
@Ma3stro-752 4 жыл бұрын
@@prempatel1777 yes. Because the general rule is the Contractor should complete the work in accordance with the plans and specifications and the contract requirements, tye BOQ during consultation operates as the basis of the measurement of payment accomplishment and not as the conclusive basis of the materials needed to the project.
@prempatel1777
@prempatel1777 4 жыл бұрын
@@Ma3stro-752 thank u sir
@FaveWorkOutRoutines
@FaveWorkOutRoutines 3 жыл бұрын
@@Ma3stro-752 hi maestro, tanong po ako ulit... Sir kpag ns package po n inoffer samin ay 10 sets of blue print (structural, engr, plunbing elec etc). Andun n rin po b ksama ung bill of quantity at line item. Thank u po and God bless po..
@remilopingol709
@remilopingol709 4 жыл бұрын
Sir where do we get rules of measurements and trade preamble? Pardon my ignorance.
@Ma3stro-752
@Ma3stro-752 4 жыл бұрын
Sir thanks for the inquiry. Marami po sa internet, owedi rin mo sa mga QS firms meron din sila ginagamit of their own like RLB, Arcades, POMI, SMM7, SMM7, Hongkong Rules for Measurement. In Government contracting Sir we have the DPWH Blue Book.
@lei749
@lei749 4 жыл бұрын
Thank you po! tanong ko lang po kung pano nacocompute yung number of days na work sa given area sa work?
@spatzky
@spatzky 3 жыл бұрын
Pwede po makahingi Arch ng rules of measurement pdf? Salamat
@zarsipanalo2185
@zarsipanalo2185 3 ай бұрын
Salamat po.
@MsJjvasquez
@MsJjvasquez 3 жыл бұрын
Hi sir, ano po ang comment nyo about sa mga owners na gusto hingiin ang equipment dahil sila naman daw ang nagbayad nito?
@johncromwell3987
@johncromwell3987 3 жыл бұрын
Cost consultant po ako dito sa Qatar in a British company. Gumagamit po kami dito ng CESMM3 at NRM for method of measurement. Balak ko po sana mangontrata sa Pinas, san po ako makakakuha nung Rules of Measurement and Trade Preambles in PH? Salamat po.
@Ma3stro-752
@Ma3stro-752 3 жыл бұрын
You can use some docs you have right now, or you may use HK Rules for measurement to fit in the asean region. You may just re align it to here later base on industry practices prescribed by CIAP.
@daveantstv1378
@daveantstv1378 2 жыл бұрын
Sir sino po ba ang allowed to signed and seal sa estimate,
@marcosatura1141
@marcosatura1141 4 жыл бұрын
Maestro pano yung may buliding permit pero d nasunod ung nsa design marami ni revised pano kaya un
@nicalim1111
@nicalim1111 3 жыл бұрын
Hello po, tanong ko lang po kung may Legal basis po ba ung percentage ng Labor cost, yung mga contingencies and mark up cost ng isang project? Kung appropriate po ba yung mga percentage base d sa law?? Thank you in advance po.
@yancydizon3942
@yancydizon3942 4 жыл бұрын
Ty much maestro....can i request a clear or zoom copy of the said formats...thanks in advance...
@christofescudero5562
@christofescudero5562 4 жыл бұрын
Hi sir! Ask ko lang po kung mag papakita ba ng estimation sa client ng price ng mga materiales at labor price agad? kadalasan po kasi parang kinukuha lang samin yun idea at ipapasa sa iba. Maraming salamat po! God bless!
@Ma3stro-752
@Ma3stro-752 4 жыл бұрын
Kung may service agreement kayo bago ka nag bigay ng estimates wala naman problema at protected ka ng Service agreement. Kung walang service agreement you violate the code of ethics
@jhoncalvinminon4684
@jhoncalvinminon4684 4 жыл бұрын
sir how much po ba magpagawa ng BOQ sa isang engr or architect. if per sq meter how much it cost per sq meter?thankyou
@leonilcabajes1351
@leonilcabajes1351 4 жыл бұрын
Sir tung Under Litigated na Lupa Ay pwede bang ma aplayan ng Building permit?
@Ma3stro-752
@Ma3stro-752 4 жыл бұрын
Pwedi po, unless my Court order of Les Pendins.
@senpaispoilme
@senpaispoilme 4 жыл бұрын
sir as an Architect, pag may nagpagawa sayo ng plano, ano po binibigay nyo na kasama sa mga Plano, BOQ po ba or BOM?
@jenzx-3762
@jenzx-3762 3 жыл бұрын
Ff
@bugoyjavier5934
@bugoyjavier5934 4 жыл бұрын
maestro sa overhead pareho den mark up sa direct cost,thanks
@Ma3stro-752
@Ma3stro-752 4 жыл бұрын
Overhead is for prelims, mark up profit is different.
@bugoyjavier5934
@bugoyjavier5934 4 жыл бұрын
@@Ma3stro-752 sir pede hingi email nyo...thanks
@bugoyjavier5934
@bugoyjavier5934 4 жыл бұрын
bugoyjavier488@gmail.com
@bugoyjavier5934
@bugoyjavier5934 4 жыл бұрын
ung bills of preliminary cnasabi nyo ser,,, ilang percent pede ilagay dyn para tumubo ako,,,salamat maestro,,,,,ngat ser
@Ma3stro-752
@Ma3stro-752 4 жыл бұрын
@@bugoyjavier5934 para tumbo ka you have the profit margin.. Which usually 10-15 %... You need to check your instructions to bidders... The bills of prelims is computed base on the requirement overhead of the project
@cjleongson
@cjleongson 4 жыл бұрын
Sir may concern po uli ako. Pano po kung nag produce po tayo ng ganyang proposal para sa client, tpos sa time na inispend para gwin ito, in the end sa iba pala ppnta ang client? Pano po kaya mallock in? Si client? Or atleast ung time na nilaan to produce these documents ay paid
@Ma3stro-752
@Ma3stro-752 4 жыл бұрын
Let the Client sign first a service agreement before provide a word.
@cjleongson
@cjleongson 4 жыл бұрын
@@Ma3stro-752 noted po sir. sir someday i hope ma tackle nyo po yung sa management ng manpower or workers. as a new contractor po, in my opinion ndi gnun ka reliable ang workers, you never know, ndi sila gnun ka predictable, unlike say engineers na more likely will show up. kaso ang hirap ung mga workers po ay direct na nagwwork on sa project
@augiecubian9425
@augiecubian9425 4 жыл бұрын
gudam po maestro hm po s 76.5 sq mtr bill of materials at ppgwa po house plans
@Ma3stro-752
@Ma3stro-752 4 жыл бұрын
You may email me your requirements and contact details at afernandezarchitects@gmail.com
@experimentoruser9917
@experimentoruser9917 3 жыл бұрын
sir ang detailed unit price analysis po ba ay same lang sa BOM?
@emmanuelpedron356
@emmanuelpedron356 3 жыл бұрын
New subscriber. Pwede po makahingi nung mga forms? Hehe salamat po
@BirdwellAviaryTv
@BirdwellAviaryTv 3 жыл бұрын
Thank you maestro. New subscriber here. Pwede po ba makahingi ng pdf file para mapagaralan po. Thank you in advance
@arstanzagustin5217
@arstanzagustin5217 4 жыл бұрын
Good day sir. pwde b ako makahingi ng sample templates for reference. thanks po
@Ma3stro-752
@Ma3stro-752 4 жыл бұрын
email add mo and prc no.?
@arstanzagustin5217
@arstanzagustin5217 4 жыл бұрын
arstanz0323@gmail.com prc no. 49072 contact no. 09066163503 Fullname: Ar. Stanley L. Agustin
@leomarlepalim8275
@leomarlepalim8275 3 жыл бұрын
Huli pero di kulong
@ricksjordan2863
@ricksjordan2863 Жыл бұрын
Hello po
@constructionlife6747
@constructionlife6747 4 жыл бұрын
Goodmorning po Maestro. Sana po isa ako sa mapili nio n mbigyan ng Book. Salamat po ng marami in advance.
@jamesalbertnealega
@jamesalbertnealega 4 жыл бұрын
Idol talaga architect. natututo talaga ko sayo architect. Sana one day makapagpractice na ko ng sarili kong firm. Sana naalala mo pa ko architect. Ako yung isa sa bumili ng book mo na binigay mo sir sa pia meeting sa makati. Ok lang ba architect makahingi ng boq format? Ito po email ko. jamesalbertnealega@gmail.com
@Ma3stro-752
@Ma3stro-752 4 жыл бұрын
Of course, na lasing ka pa nga nun... 😁
@jamesalbertnealega
@jamesalbertnealega 4 жыл бұрын
@@Ma3stro-752 hahaha oo nga. Nagmarathon ako sa mga blog mo sir and thank you sa ginagasa mo for our profession.
@jovinmilitar9362
@jovinmilitar9362 3 жыл бұрын
sir, pa share nmn ng BQM, tnx in advance jmilitarjmbmdesigns@yahoo.com.ph
@earltacneng1123
@earltacneng1123 3 жыл бұрын
Pasend nman po architect ng form po earltacneng@gmail.com
@jeraldanoc5726
@jeraldanoc5726 Жыл бұрын
Good day sir. pwde b ako makahingi ng sample templates for reference. thanks po
Estimates for Design and Build: An Overview of the Basics
15:21
A Coffee Talk with Maestro
Рет қаралды 11 М.
NEVER Break Down A Bid For A Customer - Here's Why
10:45
Successful Contractor
Рет қаралды 381 М.
“Don’t stop the chances.”
00:44
ISSEI / いっせい
Рет қаралды 62 МЛН
Quando eu quero Sushi (sem desperdiçar) 🍣
00:26
Los Wagners
Рет қаралды 15 МЛН
人是不能做到吗?#火影忍者 #家人  #佐助
00:20
火影忍者一家
Рет қаралды 20 МЛН
VIP ACCESS
00:47
Natan por Aí
Рет қаралды 30 МЛН
How to form a bill of quantities in excel from scratch
13:37
Cost Engineering Professional
Рет қаралды 93 М.
The difference between BOQ and BOM | Clear Explanation [ENG SUB]
11:12
Dear Client, This is how to charge my Architects Fee. Your Architect
30:14
A Coffee Talk with Maestro
Рет қаралды 129 М.
Simon Sinek's Advice Will Leave You SPEECHLESS 2.0 (MUST WATCH)
20:43
Alpha Leaders
Рет қаралды 2,1 МЛН
Unit rate build-up for trench excavations| Price estimation
21:58
Onalenna Marumo
Рет қаралды 9 М.
How To Prepare Construction Cost Estimation Format In Excel For Projects
13:17
Cost Engineering Professional
Рет қаралды 292 М.
Floor plan and perspective magkano?
12:36
A Coffee Talk with Maestro
Рет қаралды 3,6 М.
Estimating Overheads and Costs
39:51
Masters in Building Training
Рет қаралды 42 М.
Building Estimation Methods and Processes
20:26
Masters in Building Training
Рет қаралды 243 М.
How Do I to present my design to a Client
17:22
A Coffee Talk with Maestro
Рет қаралды 12 М.
“Don’t stop the chances.”
00:44
ISSEI / いっせい
Рет қаралды 62 МЛН