@faynasser21682 ай бұрын
You are amazing!. Thank you so much.
@markrosenberg43698 ай бұрын
How do you add months to duration? How do you modify the quality of the final Gantt Chart?
@workflowmyworkload8 ай бұрын
To add a month to Duration it would be “4w” for 4 weeks. Here is a break down of each character: W = week (example ‘2w’= 2 weeks) D = day (example ‘3d’ = 3 days, ‘3.5d’ = 3 1/2 days) H = hour (example ‘5h’ = 5 hours M = minute (example ‘45m’ = 45 minutes S = second (example ‘23s’ = 23 seconds MS = milliseconds (example ‘30ms’ = 30 milliseconds) E = elapsed time (example ‘e4d’ = 4 elapsed days)
@markrosenberg43698 ай бұрын
Thank you. But what about months?@@workflowmyworkload
@workflowmyworkload8 ай бұрын
As of now Smartsheet doesn’t have a month letter to put in (would be great if they did) so as of now we have to use w for weeks.
@ranamaalouf20438 ай бұрын
what if one task has 2 predecessors?
@workflowmyworkload8 ай бұрын
You would just add both to the Predecessor cell, separated by a comma. For example: say I want Predecessors from rows (46) and (52). I would just write that as: “46, 52” in the Predecessor cell for the task.
@faynasser21682 ай бұрын
How to add milestones into the Gantt chart?
@workflowmyworkload2 ай бұрын
Hi! I actually created a video specifically on milestones! Here it is: How to Create Milestones in a Gantt Chart in Smartsheet kzbin.info/www/bejne/iKCzY5qgbJmer7s