Thank you so much,what I couldn't understand in one week of attending lectures done in 5 minutes.
@Engineer4Free Жыл бұрын
Glad I could help!! =)
@fabriceras9562 Жыл бұрын
How convenient.....I was looking for this and this video is coincidentally 1 day old....Thanks champ
@Engineer4Free Жыл бұрын
Haha nice!! Welcome to the party 🎉
@Kaygee47Ай бұрын
Thank u and God bless bro!!!Struggled to get this topic for months and ubdid that in less than 7mins I appreciate u for that!prepping for my final exam!
@aryanpatil492 ай бұрын
Very nice, simple and quick explanation. Exactly what I needed. Thank you!
@giuseppe7892 ай бұрын
Thank you so much, your explanation is very simple and easy to learn!
@markanthonynisperos76598 ай бұрын
Thank you for this much appreciated❤ , i really understand it well better than the long explanation in our lectures 😩
@Engineer4Free8 ай бұрын
Glad I could help! 🙂
@diannapatrick32478 ай бұрын
Thank you
@Engineer4Free8 ай бұрын
You're welcome thanks for watching! 😁
@dangj1133Ай бұрын
My exam it’s tomorrow you really helped me thankkk u
@kanishkabharti78033 ай бұрын
Before making the graph, how would we know how long the graph will go? From 1-n? How do we decide n for graph?
@Lee-vc8nt10 ай бұрын
Thank you! This helped a bunch
@monks-m7j2 ай бұрын
thanks bro u made life easy
@vaishnavinaik99245 ай бұрын
explained in simple manner
@noumanhassan480510 ай бұрын
Thanks you so much
@suparna_saha7 ай бұрын
Subscribing because he deserves❤
@mhatreprem78474 ай бұрын
Nice explanation
@Kiyotaka_Ayanokoji692 ай бұрын
best and simple
@sagarsah75368 ай бұрын
Thank you 🙏
@Engineer4Free8 ай бұрын
Thanks for watching 🙂
@tahmidaisra26698 ай бұрын
Thank you so much ❤
@Strangeruser2332 ай бұрын
I LOVE your voice
@dianasakala91418 ай бұрын
Thank you. Can you please explain how we found the project duration?
@FaustineOkoth8 ай бұрын
Thanks alot
@Engineer4Free8 ай бұрын
You're welcome! Thanks for watching 🙂
@AbhinavMotha10 ай бұрын
how to know predecessor ??
@yolekevin688029 күн бұрын
Hey it's in the table.
@sarajann549310 ай бұрын
Activity b needs 4 days and Activity c needs 2 days but we are giving them 4 days in general. Shouldn't it be 6 days?
@Engineer4Free10 ай бұрын
Heyy so look at each one separately. B needs 4 days, and it can only start once A is finished, so B finishes 4 days after A finishes. Now consider C. C needs 2 days, and it can only start once A is finished, so C finishes 2 days after A finishes. There is no significant relationship between B and C, only relationships between A and B, and A and C. And the relationships are actually finish to start, so the start of the successor depends on the finish of the successor, rather than the finish to finish wording that I used above. Take a look at this video as well, it talks about the numbers in the Gantt chart and might help to clarify the idea: kzbin.info/www/bejne/aF69lJSnZ755iZo 👍