Thanks for sharing...its been a long time I'm doing manual ways in changing the activity links to remove out of sequence activities until I watch this video. This will now make my life easy fixing out of sequence activities
@SoftEdemy10 ай бұрын
Welcome
@Nithishkumar-wl2mp2 жыл бұрын
after long time good to see you back with some valuable content thanks buddy
@SoftEdemy2 жыл бұрын
Thanks, Nithish Kumar.I was just busy with some other projects. As professional Commitment. This time I will sure some pure professional and useful content. With a new interface. Stay connected with Softedemy. Also, Suggest to us the content you required.
@shakeeln2020 Жыл бұрын
Thanks Buddy Keep updating such video Valuable information
@SoftEdemy Жыл бұрын
Thanks Mr. Shakeel Ahmed ,your feedback is valuable for us.
@aalamgeer20592 жыл бұрын
Mashallah Sir thank you so much for creating this video.Regaring I asked number of planning manager but no one has the this short cuts .jaza kum Allah Khair sir
@SoftEdemy2 жыл бұрын
Thanks, @Alam Geer for your valuable and inspirational comment on our hard work. We are coming up with more valuable content. Keep watching @Softedemy
@mohammadalamgir63472 жыл бұрын
@@SoftEdemy Thank you very much Sir
@mahansor8295 Жыл бұрын
Very informative, thanks for sharing. Would you have any plan to resolve the rest of out of sequences activities (75 activities)? Thank you
very well explained thank you but i have one question can we delete the relationships in excel itself after that we can export rather than putting "d"
@SoftEdemy Жыл бұрын
You have to delete in P6 in Excel. If you just remove than in P6 relationship will be remain their. The d commands the P6 to delete the relationship.so it's necessary.P6 will only do what you instruct to do. Also watch below video it's fixer tool .Its very easy nothing much to do in it.
@SoftEdemy Жыл бұрын
kzbin.info/www/bejne/ammbmqOda5hoZ80 Watch this video
@SoftEdemy2 жыл бұрын
To see all below questions answers visit at www.softedemy.com/out-of-sequence-activities-in-p6/ What are out of sequence activities in Primavera P6 Why are they called out of sequence activities What is the impact of an out of sequence activity on a project schedule What are some best practices for avoiding out of sequence activities in Primavera P6 How can out of sequence activities be identified? Step by Step Guide to resolve of Fix out of Sequence Activities in Primavera P6
@rupeshns0310 ай бұрын
Thanks for the wondeful video. I have a query. When you apply FF relationship to Out of sequence activities why don't you consider the lag. If you do not maintain lag (equal to remaining duation of the activity), FF relationship mayl pull ahead the overall schedule end dates?
@SoftEdemy10 ай бұрын
By adding lag your finish dates will be changed in that case. No lag should be applied.out of sequence will be only detected when predecessor activity get started or completed. So in this senerio their is no sense to assign lag. Please first understand why out of sequence appears in monitoring phase of schedule. Thanks
@AhmedAli-dj9jo2 жыл бұрын
Thank you for your time What you meant activity deviation +/- 5% What minus -5% mean?
@SoftEdemy2 жыл бұрын
@Ahmed Ali, You have followed my words that true learners' spirits lead to professionalism. you have maybe read some in the contract or other procedures. In most general conditions of the contract and in the programme section you read this. "In the event that progress of an element of the Works deviates by plus or minus five percent (± 5%) from that shown in the associated Activity Programme the Contractor shall submit a revision of such Activity Programme for the Engineer’s information" If you revise your programme on 5% deviation then out of sequence will not occur in this bulk that was 1162 activities. There will be some out of sequence but not in huge nos. I hope you understand (± 5%) meaning that's not a division word i used deviation may be my pronunciations lead you wrong. Also maybe a question comes into your mind how can we find out (± 5%) deviation in activities. To find out (± 5%) deviation in activities. you just need to see the variance = (planned % (Which is Schedule %) - Earned % (which is Performance %).If the variance of an event is more than or equal to± 5% then you need to revise the activity program . The revision of activity according to the site should be done monthly basis and the consultant /Engineer should be informed about the changes by a summarized narrative report. That Programme will be not considered a revision it will be considered a monthly update. That's the best Practice >I would recommend to all planners to stay away from unrealistic forecasting results in EVM and Completion dates. Further, the choice depends on how your client is well known in Planning and Scheduling Practices. Thanks Again Ahmed Ali for Asking to keep asking these types of questions also let us know what you more want to hear from us.
@AhmedAli-dj9jo2 жыл бұрын
@@SoftEdemy thank you, I appreciate your work
@SoftEdemy2 жыл бұрын
@@AhmedAli-dj9jo Welcome
@mdzubairahmed6819 Жыл бұрын
please come with an example for window analysis method..
@SoftEdemy Жыл бұрын
We haven't started for any delay analysis content yet. In future our best content will be uploaded. All methods of delay with their case of work and different senerios . The video's will be practical. Meanwhile you can contact to our influencer as per above contact details for any urgent help. This may take sometime
@UnofficialFaizan Жыл бұрын
Have you uploaded the video for activities with no predecessor.
@SoftEdemy Жыл бұрын
No.
@SoftEdemy Жыл бұрын
Just apply a filter in which predecessors = empty
@skghomedesignideas5086 Жыл бұрын
Sir can you please add video for window analysis and time impact analysis step by step with example schedule.
@SoftEdemy Жыл бұрын
Sure, thanks for your comment
@RHSkills2 жыл бұрын
MA SHA ALLAH THANKS SIR
@SoftEdemy2 жыл бұрын
Welcome you are also doing great work. Keep it up RH Skills
@RHSkills2 жыл бұрын
@@SoftEdemy 💖
@BedarBukhat5 ай бұрын
Hi sir , We use all these Cases to resolve out of sequence activities in one time?
@SoftEdemy5 ай бұрын
Yes
@BedarBukhat5 ай бұрын
Ok sir thankyou so much 😊
@SoftEdemy5 ай бұрын
@@BedarBukhat welcome
@محمدالامينمحمدالمأمون Жыл бұрын
Thanks a lot
@SoftEdemy Жыл бұрын
Welcome
@mohammedalmaky9637 Жыл бұрын
What if completed activity on predesser?
@SoftEdemy Жыл бұрын
Than their is no of sequence. For last case 4 you need to delete relationship
@electricalengineer2950 Жыл бұрын
Hi Sir Thank you so much for sharing valuable Knowledge 😊🤗😊 I have a Doubt here in you Excel sheet there is no lag but in our sheet there is Some lags for activities how should we do for those activities to fix out of sequence please help sir thanks in Advance
@electricalengineer2950 Жыл бұрын
I tried this proceess as usual but I didn't get its showing "Process did not complete successfully.see log file for details" please help if you can give any idea sir please help
@SoftEdemy Жыл бұрын
Remove the lag to zero
@SoftEdemy Жыл бұрын
Avoid using lag or lead in scheduling
@SoftEdemy Жыл бұрын
kzbin.info/www/bejne/ammbmqOda5hoZ80 Follow the above video This is the same video with automated sheet
@rahulnagarwal499010 ай бұрын
can i level resource of my project without fix "out of sequence activities"?
@SoftEdemy10 ай бұрын
Yes but P6 resource level is resource constraint.
@rahulnagarwal499010 ай бұрын
@@SoftEdemy what’s the mean of resource constraint?
@rahulnagarwal499010 ай бұрын
Any issue or error occurred after resources leveling without fixing out of sequence activity?
@SoftEdemy10 ай бұрын
@rahulnagarwal4990 inprogress activities have always issue in resources. Because you need to consider remaining units not budgeted
@muhammadusmanjanjua6235 Жыл бұрын
Due to 4th case relationships of many activities removed. How to solve it??
@SoftEdemy Жыл бұрын
After resolving out of sequence, Assign new relationships
@SoftEdemy Жыл бұрын
kzbin.info/www/bejne/n6jMfqyBlJ6Sm9E
@vino18172 жыл бұрын
Sir, Thanks Having small doubt in this video. Before import why don't you deleted the activities. You clear the four rules first with the copy paste method. After that u did not delete existing activities Pls clarify sir
@SoftEdemy2 жыл бұрын
if you delete all of them, your activities relationship will be broken. The previous relationship should be known. This is not a copy-paste method. This is a trick found after a lot of research. The second one is that there are more than 10 K activities or more than 35K relationships are there. By mistake, if you removed necessary relationships and forget to replace a new one. It will take days to know where your relationships are creating problems. If your project is in the monitoring stage. Now come to your question answer. you said I haven't deleted old relationships. The answer is that I deleted the relationship before importing. I put d in the delete column which instructs P6 to delete the relationship. If you just delete the row and import it back the relationship will be there. You have to put d in front of the delete row column. To instruct the p6 delete it. Watch again you will see it. thanks for your appreciation.
@vino18172 жыл бұрын
First I say special thanks to you sir. For me u have spent this much time to type mes it is really thanks for your response. I got the answer from your reply sir.
@SoftEdemy2 жыл бұрын
@@vino1817 you understood right, Before importing into p6, I have added d in the delete row column. Welcome me, my team, always work for free and we are focusing to deliver the best to the people. Although there is no earning from these services. In the market, the trainers and consultants charge 100s of dollars. But our services and response are free. Although our skills are not hidden from anyone. We have recently launched our website www.Softedemy.com.Now we are expanding ourselves and believe to be the best service providers. Stay with us. and keep sharing your feedback, What should be published next.
@rahulnagarwal499010 ай бұрын
sir is it for running project or completed project?
@SoftEdemy10 ай бұрын
In progress project
@siddiqkhan9142 жыл бұрын
Sir, For last 75 activities remaining out of sequence how to fix it? Do we need to repeat the same steps?
@SoftEdemy2 жыл бұрын
Thanks for asking, I was expecting this question. That events are due 4th Case as I have explained that it does not impact Schedule strength. These 75 activities are completed but their predecessor and successor are not completed. So this is a totally different case. Normally when a scheduler uses fewer relationships during scheduling this does appear. IN this schedule he has used a lot of irrelevant relationships. this was falling in the 4th case Predecessor not started and Successor Completed. This can be resolved by deleting all activities in this case. One line answer is that you have to delete just the 4th Case Predecessor Not started and Successor Completed relationship to resolve 75 activities. In my case, not every Schedule. I hope you got the point. Also @Saddiq Khan thanks for asking.
@siddiqkhan9142 жыл бұрын
@@SoftEdemy Thanks for quick reply.
@SoftEdemy2 жыл бұрын
@@siddiqkhan914 Welcome my pleasure.
@a.m27648 ай бұрын
hello sir ... i have two questions needing help 1- After fixing in execel , i found this message(The User Preferences used to create this Excel file are not the same as your current preferences. Importing this file could corrupt your data. Please refer to Help for more information about importing data from Excel. Are you sure that you want to continue?) Is there a problem or continue ? 2- After updating : why budgeded units or costs before D.D disappear and the distribution of them is reassigned on next months differently compared to baseline?
@SoftEdemy8 ай бұрын
The excel export file and then imported files are different. Like while exporting you setting if users preferences was different and in import was different. This cause the issue
@a.m27648 ай бұрын
thanks ... and what about the second enquiry pls???@@SoftEdemy
@SoftEdemy8 ай бұрын
@a.m2764 when you remove out of sequence your relationship changes. So changes in relationship means changes in dates . And changes in dates means change in resources assignments.
@a.m27648 ай бұрын
@@SoftEdemyhow to solve (failed to find a matching object for activity relationship) whenever I import from excel to p6?..pls tell me
@SoftEdemy8 ай бұрын
@a.m2764 predecessor I'd nort matching or type of relationship not matching. Or your deleting any relationship which doesn't exist. Any possibility from above