you answered for my yearly questions. You know, I have been studying P6 since 2017 but I don't know why when I run schedule, the date change. I ask many people about this, but they don't want to explain to me. Thank you so much. I will study more P6
@PLANNINGP63 жыл бұрын
You are welcome. Me and my team is always available to help the beginners. please don't hesitate to contact us. also follow us on linden.
@fasiuddin50172 жыл бұрын
Really good way of explaining..
@PLANNINGP62 жыл бұрын
Thanks
@EngineeringSounds4 жыл бұрын
GOOD job
@PLANNINGP63 жыл бұрын
Welcome
@muhammadyousaf51564 жыл бұрын
keep it up bro.
@PLANNINGP64 жыл бұрын
Yes Insha Allah
@vasanthm59473 жыл бұрын
Thank you sir
@PLANNINGP63 жыл бұрын
Welcome
@ExploreSpaceSights Жыл бұрын
my progress line goes straight after updating the schedule it dont show ahead or delay activities why so?
@PLANNINGP6 Жыл бұрын
According to your comments, it seems you might be following the data date line. Please see the tutorial link for the Progress line below. kzbin.info/www/bejne/gKPWepyHr9uSfKc Please WhatsApp screenshots if you are still having problems. Thanks
@samiansari73244 жыл бұрын
Really helpful video, need one help i have on going progress in my schedule and baseline is fixed. Now iam going to shift to another laptop. What files should i take and what procedures should i follow to work without disturbing the baseline there. Should i make one copy of the one iam working on and export both? How will this work
@PLANNINGP64 жыл бұрын
Please contact me on Whatsapp +923088663797
@PLANNINGP64 жыл бұрын
Also please see chapter # 3
@suji7722 жыл бұрын
how to calculate engineering activity in project
@PLANNINGP62 жыл бұрын
Dear Concern, There are a lot of methods in project management and planning to measure, control, or monitor the design/engineering progress. Mostly it is defined in the contracts how to monitor the KPIs of each phase or key stage, if not then the planning department has to prepare a procedure/method statement or monitoring system for the above-mentioned purpose, and needs to describe theoretically and with the tabes and pictorial and graphicly that how to manage all above sections. Sometimes it's a contractual requirement to get the approval of the document from the client/Authority. Now, if we need to measure KPIs only for the design phase then we have to create a design control register and set weights for each step or approval. Secondly, we have the option of activity steps in primavera where we can use the same weights option. We can also use the enlisted documents for the design progress monitoring or measuring. Earned Value Calculation Sheets Document Delivery Register Design Control Register KPIs Monitoring Sheet Design Tracking Register Design Control Ledger etc.