Good Presentation, But I believe it doesn't work for Weightage having value 0.001% as Primavera considers 0.00 value only. You have to enter it Manually is the best practice and more control.....Appreciate your work!
@faisalgulzar4538 Жыл бұрын
Sir, even if you export data with "Rs" or "d" symbol, it can easily be separated into 2 columns using the data tab in excel.
@billytubesАй бұрын
Hi Waqas, I dont have a cost loaded programme, can we use weightage and a fake cost resource to prsent s cruve and generate spi/cpi. ?
@reginaldibenne68759 ай бұрын
Nice presentation.🙏 I noticed after importing back the schedule, the weightage % go back to 0.2, 0.3, 0.89 just to say. ie the percentage did not multiples in those values. What's the cause, sir?
@saudpm402 ай бұрын
Whats the benefit of using weighted sheet ? Is it linked with EVM?
@engrwaqas2 ай бұрын
Yes , If your project progress measurement is based on such WTgs then yes it will create EVMs trends
@sarbelandkhan78305 ай бұрын
If all the amounts are entered into the P6 along with WBS, then why it cannot calculate the weightages by itself? Its just dividing individual costs by the cumulative project cost.
@nithinkokkula58662 жыл бұрын
Sir thnks for awesome video . Sir pls solve my query , after weightage is assign and when we enter actuals how to get project actual progress values against schedules ones
@engrwaqas2 жыл бұрын
Thanks
@minhazali4090 Жыл бұрын
Schedule values are derived from baseline. Actual is derived from updated schedule as physical progress or earned value
@carlodigma8199 ай бұрын
Hi, I have one Query I tried it but, when exporting P6 to excel the out come the activities are not in order. I tried to use the define and inter all percentages in all activities automatic wbs was filled with total wt. %, but when i Share the xer file to the client the outcome with them not the same value of Wt. % please guide Thanks
@engrwaqas9 ай бұрын
Whatsapp +92 3114396983
@madanmoharana772 жыл бұрын
wrong way of presenting ...it will not work in real time project. cost based weightage is not working most of the time & in update time your method also not work.
@engrwaqas2 жыл бұрын
Oh dear Oh Dear
@carlodigma8199 ай бұрын
Not coming when i export to p6 value are difference
@muhammadusmananwar8992 Жыл бұрын
how we can calculate weightage % if cost is not loaded?
@minhazali4090 Жыл бұрын
Man-hours
@engrwaqas Жыл бұрын
Duration based Man hour based
@muhammadusmananwar8992 Жыл бұрын
@@engrwaqas can you explain sir further
@muhammadusmananwar8992 Жыл бұрын
@@engrwaqas plz sir elaborate duration based....
@benzonjhermogeno7 ай бұрын
Use budgeted labor units @@muhammadusmananwar8992