Create S Curve Without Resources from Primavera P6 | By activity weightage calculation and Resources

  Рет қаралды 13,051

SoftEdemy

SoftEdemy

Жыл бұрын

WhatsApp:wa.me/+923155537580
Contact us on info@softedemy.com
Article Link: www.softedemy.com/s-curve-wit...
In this video, I'll walk you through: Create S Curve Without Resources from Primavera P6 | Assign Resources by Weights and create S-Curve | By activity weightage calculation and Resources
ABOUT OUR CHANNEL
Project Controls & Engineering Software Academy Offers Accredited Courses and Resources on Project Management & Engineering Tools. Check Out our New Blog - Incorporating Articles on Projects.
Check out our channel here:
kzbin.info/door/fte...
Don’t forget to subscribe!
CHECK OUT OUR OTHER VIDEOS
FIND US AT
www.softedemy.com/
GET IN TOUCH
Contact us on info@softedemy.com
FOLLOW US ON SOCIAL
Get updates or reach out to Get updates on our Social Media Profiles!
Twitter: / faisalm15432091
Facebook: / softedemy
Instagram: / softedemy
LinkedIn: / softedemy
Telegram: t.me/Softedemy
Contact Us
WhatsApp:wa.me/+923155537580
#softedemy,#Planningengineer,#primaverap6
Related or Similar Asked Questions related to the Video
s curve from p6 to excel, how to create s curve in primavera p6,p6 resource histogram, manpower histogram in p6, manpower histogram template excel, how to make s curve in excel, how to export resource usage spreadsheet p6,s curve from primavera to excel, how to print resource histogram in p6, how to make s curve in excel from primavera, how to get s curve from primavera, how to do s curve in primavera, how to generate progress s curve in primavera, s curve in excel planned,How generate S curve histogram from Primavera P6,How do you show histogram in Primavera,How do I create a resource histogram in Excel?,How do I create a labor histogram in Excel?,How do I create a resource plan in Excel?,How do you make a 2022 histogram on Excel?,How do I make a normal distribution curve in Excel?,How do you create a manpower histogram in Primavera?,What is manpower histogram?,What is resource histogram?,How is manpower calculated in Primavera?,S curve construction sample,Create S Curve Without Resources from Primavera P6,Assign Resources by Weights and create S Curve,By activity weightage calculation and Resources,weight factor in primavera p6,weightage in primavera p6,activity weightage calculation,activity weightage in primavera,s curve from primavera to excel,s curve in excel,how to make s-curve without cost or resources in primavera p6,without Resource,assign resource by weights,Top down estimation,P6 S Curve
Disclaimer:- This channel does not promote or encourage any illegal activities and all content provided by this channel is meant for EDUCATIONAL PURPOSE only. Copyright Disclaimer: - Under section 107 of the
Copyright Act 1976, allowance is made for FAIR USE for the purpose such as criticism, comment, news reporting, teaching, scholarship, and research. Fair use is a use permitted by copyright statutes that might otherwise be infringing. Non- Profit, educational, or personal use tips the balance in favor of FAIR USE.

Пікірлер: 18
@SoftEdemy
@SoftEdemy Жыл бұрын
Read the relevant article for more details www.softedemy.com/s-curve-without-resources-in-primavera-p6/
@ammarkhan8548
@ammarkhan8548 9 ай бұрын
Awsome
@SoftEdemy
@SoftEdemy 9 ай бұрын
Thanks
@mahansor8295
@mahansor8295 Жыл бұрын
👍👍
@SoftEdemy
@SoftEdemy Жыл бұрын
👍👍
@Howtoexcel14
@Howtoexcel14 Жыл бұрын
Good one but try and reduce your speed overall you are doing great
@SoftEdemy
@SoftEdemy Жыл бұрын
To reduce the speed please use the KZbin player option. Where you can change video speed 0.5 . I hope it's suite you
@nkoketsengkonopi6316
@nkoketsengkonopi6316 Жыл бұрын
Hi Sir. Thank you very much. This was very helpful. How do you copy the formula to the rest of the spreadsheet to "Apply throughout the project" like you do at 12:38?
@SoftEdemy
@SoftEdemy Жыл бұрын
It's simple copy then select cells and paste
@chinenyeegwuagu3874
@chinenyeegwuagu3874 Жыл бұрын
Thanks a lot for this. Can we run the report so we have the timelines in weeks instead of months.(I. e when trying to build the report in excel). Cos it didn't work .
@SoftEdemy
@SoftEdemy Жыл бұрын
You can create S Curve with any interval , monthly weekly daily ,you have select the right timeline,
@SoftEdemy
@SoftEdemy Жыл бұрын
Also you can copy it directly from resource assignment and draw S Curve
@muhammadusmananwar8992
@muhammadusmananwar8992 Жыл бұрын
how we create physical s curve if resource and cost is not loaded?
@SoftEdemy
@SoftEdemy Жыл бұрын
Watch the video. One option is that you can assign units by weights as per the above video . The other option video will be unloaded in upcoming Month. In that method we directly calculate schedule percent from data date and finish date and we put physical in the curve.
@muhammadusmananwar8992
@muhammadusmananwar8992 Жыл бұрын
@@SoftEdemy got it how import in excel to modify curve for better presentation?
@muhammadusmananwar8992
@muhammadusmananwar8992 Жыл бұрын
@@SoftEdemy as well you please explain complete progress percentage without cost n resources?
@SoftEdemy
@SoftEdemy Жыл бұрын
@@muhammadusmananwar8992 kzbin.info/www/bejne/aITMp5lslMqSkJY
@SoftEdemy
@SoftEdemy Жыл бұрын
@@muhammadusmananwar8992 in upcoming video .we will explain for sure
Manpower Resource Loading including S-curve in Primavera P6
13:30
Happy 4th of July 😂
00:12
Pink Shirt Girl
Рет қаралды 61 МЛН
I Can't Believe We Did This...
00:38
Stokes Twins
Рет қаралды 102 МЛН
Stacked Histogram and S Curve in Primavera P6
4:29
Construction Techie
Рет қаралды 25 М.
Lecture L94 Plot our Late Payments on a Line Chart
8:32
The Analytic Scholar - Data Analytics Training
Рет қаралды
Graph S Curves in Primavera P6
8:03
Plan Academy Inc.
Рет қаралды 9 М.