Thanks Ahmad. I would agree that if you have many OOS conditions this method might be prudent. I resolve these manually and check these conditions frequently. Appreciate you sharing your techniques.
@GlobalProjectControl7 ай бұрын
Yes, you are right. This method is helpful for big data modifications.
@abdelouahabbelalia2072 Жыл бұрын
Great , thanks
@GlobalProjectControl Жыл бұрын
I was glad to hear that 🙏
@Adeel20239 ай бұрын
I have done the same steps to modify out of sequence activity but the result come out schedule log txt does not exist?
@GlobalProjectControl8 ай бұрын
Go to "Schedule" and before "push the schedule" in the schedule dialog box TIK > LOG TO FILE. Now, if you schedule your project, then VIEW LOG will work.
@a.m27647 ай бұрын
hello sir ... i have two questions needing help 1- After fixing in execel , i found this message(The User Preferences used to create this Excel file are not the same as your current preferences. Importing this file could corrupt your data. Please refer to Help for more information about importing data from Excel. Are you sure that you want to continue?) Is there a problem or continue ? 2- After updating : why budgeded units or costs before D.D disappear and the distribution of them is reassigned on next months differently compared to baseline?
@GlobalProjectControl7 ай бұрын
For Error 1: I guess that you exported the file from another system and you want to import it on a different system that doesn’t have the same user preferences setting. This is the wrong approach. Your second question is not clear enough, I suggest you look into this video: 🔴 How to Update Multiple Resources in Primavera P6 with Excel Help 🎞 kzbin.info/www/bejne/pGS8mKGJpNmdrKc
@noumanzia3 жыл бұрын
Can please elaborate on the rationale behind changing the relationship in excel and not in primavera p6? Thanks
@GlobalProjectControl3 жыл бұрын
if you want to: 1. Add more relationships to the software, you need to fill all columns which I used in the video. 2. Modify the available relationship, need to change its base on the update. but the important note is, if the change included a compulsory field, you need to remove the available information and re-create it (this is software procedure)
@wasimahmad14233 жыл бұрын
Kindly make a video on revised and recovery schedule
@masoudshams12 жыл бұрын
Can you Ahmad Jan say why you simply did not click from P6 and change it to SS?
@GlobalProjectControl2 жыл бұрын
If you work with a big database then an excel spreadsheet update is easier than a manual update