Learn to Update, Track, & Monitor Projects using MS Project, MS Project for Beginners Lesson 6

  Рет қаралды 8,534

Tom Stephenson

Tom Stephenson

Күн бұрын

In this video I discuss how to update a project using MS Project. I do a quick review from the previous videos and then jump into how to set a status date, use the tracking screen, tracking Gantt and variance screen when updating. As well I discuss how to review the cost and resource cost screens with regards to cost variances. If you wish to see the other videos in this series review my playlists on my channel, click subscribe and the notification icon. If you have questions leave them in the comments section. Some previous videos in this series are listed below.
Previous video in this series include:
MS Project Beginners Series
Lesson 1 Activities • MS Project for Beginne...
Lesson 2 WBS CPM Linking • MS Project For Beginne...
Lesson 3 Calendars • How to setup a calenda...
Lesson 4 Resources • How to Create and Appl...
Lesson 5 Resource Usage • MS Project for Beginne...
Some sample videos from MS Project Made Easy playlist (more are on my playlists, click my channel to review):
Tutorial 1 Introduction • MS Project Made Easy T...
Tutorial 2 Calendars • MS Project Made Easy T...
Tutorial 3 5 things to improve • MS Project Made Easy T...
Tutorial 4 Resources • 8 Things & More on How...
Tutorial 5 Filter • MS Project Made Easy T...
Tutorial 6 Updating • MS Project Made Easy T...
Tutorial 7 Revisions • How to Update & Revise...
Tutorial 8 Change Orders • Update and Insert Chan...
Tutorial 9 Timeline scale • Make professional pres...
Tutorial 10 Work, Duration, Units, Effort • Learn Work, Units, Dur...
Tom Stephenson is a national award-winning professor (George Brown College, University of Toronto) and best-selling author whose background in education spans nearly three decades. His diverse teaching disciplines include construction project management, business management, human resource management, architecture, carpentry, and brick and stone masonry. As a dual-professional, Tom is called upon by industry leaders to translate knowledge, reinvigorate corporate culture, and inspire innovation in emerging and established companies across Canada. Before breaking into the academic realm, Tom acquired more than a decade of practical project-management experience, operating a mid-sized Toronto-based general contracting firm. He is also the author of the newly released Planning, Scheduling, and Control of Construction Projects with American Technical Publishers and the four best-selling editions of Understanding Construction Drawings for Housing and Small Buildings with Nelson Publishing Canada. Tom most recently received the Toronto Construction Association’s 2020 Chancellor’s Award for “helping his peers become more ethical, knowledgeable and professional.” A champion of change management, Tom takes pride in helping students and businesses navigate uncharted territories, take calculated risks and rise above the status quo. Some of the companies he’s worked with include Mattamy Homes, EllisDon, BIRD Construction, MCA, Maple Reinders, and Tucker HiRise, University of Toronto Project Managers.

Пікірлер: 27
@tadiosnyamuziwa5679
@tadiosnyamuziwa5679 10 ай бұрын
Great videos Prof. I'm not in construction, but your Ms Project principles can be applied in any industry
@Mostafa20268
@Mostafa20268 Жыл бұрын
Watching with passionate and joy and opened my mind to how to track the project..great lesson..great pro Mr. Tom.Thank you sir.
@TomStephensontraining
@TomStephensontraining Жыл бұрын
Great Mostafa, it took me a number of years to really see it thaat way, now im integrating Lean into that view as well.
@Mostafa20268
@Mostafa20268 Жыл бұрын
@@TomStephensontraining Yes that is clear.. I am watching your videos one by one, righting your instructions and making my manual book to keep it under hand with doing application with what you do in the video on my MS project on my PC .. Sending my Greetings and respect from Iraq. God bless you Sir Mr. Tom. Kind Regards. Civil Engineer Mostafa
@derekhale5802
@derekhale5802 2 жыл бұрын
Thank you for sharing you MS Project knowledge!
@TomStephensontraining
@TomStephensontraining 2 жыл бұрын
Thanks for the kind words Derek
@murin7185
@murin7185 2 жыл бұрын
Thanks for great lecture ,professor Tom
@TomStephensontraining
@TomStephensontraining 2 жыл бұрын
Thanks Mark! Glad they are helping you
@sahilpatel7308
@sahilpatel7308 Жыл бұрын
Sir, great lectures on MSP. I'm passionate about learning msp in construction. Usually i watch video and know how software works. I even read msp manual to know how to use it but they are very vague. I never know when to use which tool. To be honest, I never know about baseline. Today, after watching i came to know that i can track the project only if i put baseline. So yeah, this channel is blessings to me. Thank you so much. Guru.
@TomStephensontraining
@TomStephensontraining Жыл бұрын
Thanks Sahil for your thoughtful words. I’m glad the videos help you!
@artemallamosquiteros3662
@artemallamosquiteros3662 2 жыл бұрын
Really good videos, Thank you
@TomStephensontraining
@TomStephensontraining 2 жыл бұрын
You’re welcome Artemalla
@isaacchk
@isaacchk 2 жыл бұрын
Thank you Tom
@TomStephensontraining
@TomStephensontraining 2 жыл бұрын
Happy to help Isaac
@alessandroschippa4253
@alessandroschippa4253 6 ай бұрын
Why is it necessary to set a status date? If I update the task looking at the project today why should I put a status date in the past? The actual start, the actual finish and the % complete can be analyzed today
@excelbatais
@excelbatais Жыл бұрын
well done 👍
@TomStephensontraining
@TomStephensontraining Жыл бұрын
Thanks Excel, very appreciated!
@chiragkotecha6044
@chiragkotecha6044 11 ай бұрын
Sir, In my M.S.Project Tools-Mark on track not shown. Also in view - Level 1, Level 2 in WBS not shown ( your episode 12 ) So pl advice second method.
@nazirramguthee6568
@nazirramguthee6568 9 ай бұрын
Do you forward the variance screen or the tracking screen as a PDF to the client?
@primojosephbanisa2671
@primojosephbanisa2671 2 жыл бұрын
Do you also have tutorial videos on Earned Value Management?
@TomStephensontraining
@TomStephensontraining 2 жыл бұрын
I do under the cost control playlist but more on how it works as opposed to ms project. I have a few issues with how best to use ms project for eva so Im not quite ready to promote it. Thanks for watching Primo
@primojosephbanisa2671
@primojosephbanisa2671 2 жыл бұрын
Thank you and I learned a lot from your videos...primo
@stephaniemora3772
@stephaniemora3772 Жыл бұрын
I have a project that started in 2021 and is now restarting in 2022. What would be the best way to update that schedule?
@TomStephensontraining
@TomStephensontraining Жыл бұрын
Hi Stephanie you should be able to go to project tab and then project information and change the start date to whatever date you want to start and everything will move
@stephaniemora3772
@stephaniemora3772 Жыл бұрын
@@TomStephensontraining That's the issue, we don't want to restart the project, we want to pick up in the middle. For example, the initiation and planning has been completed. We are restarting in the execution phase. What would be the best way to update the schedule? Change the planned dates manually?
@chiragkotecha6044
@chiragkotecha6044 11 ай бұрын
Sir, For more than one supervisor we can take for 2 supervisor 200% ?, 3 supervisor 300% ?. Like laobur ?????
@TomStephensontraining
@TomStephensontraining 11 ай бұрын
Yes as long as you have them listed as work in the resource sheet
MS Project for Beginners, Add Resources, Costs, and Review Work Usage
35:22
Sigma Kid Hair #funny #sigma #comedy
00:33
CRAZY GREAPA
Рет қаралды 29 МЛН
That's how money comes into our family
00:14
Mamasoboliha
Рет қаралды 12 МЛН
A clash of kindness and indifference #shorts
00:17
Fabiosa Best Lifehacks
Рет қаралды 99 МЛН
MS Project 8 - Tracking Task Progress and Variance
22:19
PatJHeffernan
Рет қаралды 33 М.
How to Use Microsoft Planner to Manage Your Project (2024)
27:15
Scott Brant
Рет қаралды 115 М.
Sigma Kid Hair #funny #sigma #comedy
00:33
CRAZY GREAPA
Рет қаралды 29 МЛН