Do you use the FIDIC form of contracts or do you use another form of contract?
@engrmidrar3 жыл бұрын
Yes FIDIC form of contract.
@mikiyasshumu8437 Жыл бұрын
We are using FIDIC form or contract . If you have case study like actual claims issue that's arise during construction and the same solving mechanism by referring FIDIC It will help us more. Thanks for your commitments !!!!
@Er.Sunil.Pedgaonkar Жыл бұрын
FIDIC should support encourage Consulting Engineers of all disciplines & all kind of engineering/technology contracts, arbitration,mediatoon, mediation -- Er. Sunil Pedgaonkar, India, Consulting Engineer, India
@Metroun Жыл бұрын
Thanks for the comment!
@Agproperty6772 ай бұрын
Nice intro to the contracts
@Metroun2 ай бұрын
Thank you. Take a look at our FIDIC playlist for more FIDIC videos.
@kwesicrayon12892 жыл бұрын
Great video. You haven’t followed up with the mini series of the main book as you promised. Thank you for the great l videos.
@Metroun2 жыл бұрын
Hi Kwesi, Please find attached playlist for everything FIDIC related. Here you will find videos on the contract books. We hope this helps. kzbin.info/aero/PLEqD73qa8q99NuOmn3UGOENToyN04qthA
@amjadaliikram35602 жыл бұрын
Wonderful video.
@Metroun2 жыл бұрын
Thank you!
@aneeshaneeli35632 жыл бұрын
Thank you❤🔥
@Metroun2 жыл бұрын
You're very welcome! We hope it's been useful to you
@mikiyasshumu8437 Жыл бұрын
pleased realised more vedio
@Metroun Жыл бұрын
Thanks for your comment! We have released a new video every week over the past 3 years and will continue to do so :)
@mhmdmhmdd2413 Жыл бұрын
do you have session about types of bond especially the different between performance bond and retention bond ..etc
@Metroun Жыл бұрын
Yes we do. Here's a couple of links for you kzbin.info/www/bejne/iajCdGOpgbNsbKM kzbin.info/www/bejne/ZnbGkn5snNuqfpY
@douglasmanyadza90623 жыл бұрын
A great summary
@Metroun3 жыл бұрын
Hi Douglas, That's great to hear! Do you use the FIDIC form of contract?
@douglasmanyadza90623 жыл бұрын
@@Metroun yes
@Metroun3 жыл бұрын
Great! Is there anything in particular you'd like us to cover?
@ridwaanmohamoud23 ай бұрын
Well note
@Metroun3 ай бұрын
Thank you. We'll be issuing an updated video shortly.
@hassanh9372 Жыл бұрын
I am looking for EPC form of contract agreement template? If you can help please. Thanks
@Metroun11 ай бұрын
Unfortunately that’s not something we’re able to help with at this stage. We do not currently provide contract form templates.
@hassanh937211 ай бұрын
@@Metroun okay,please advise who can provide if you know.. Thanks
@amjadaliikram35602 жыл бұрын
Sir which FIDIC book you recommend for thorough understanding of construction projects. Old Red book or new one? Best regards.
@Metroun2 жыл бұрын
New red book :)
@nayeemshaikh16823 жыл бұрын
Great explanation👌 I need complete tutorial link on fidic 1999 Please share with us
@Metroun3 жыл бұрын
Maybe that's something you'll see soon then 👍😊
@guruduttrao306 Жыл бұрын
Hi, Are you providing paid services for fidic course from basic to advanced level? Please suggest. Thanks.
@Metroun Жыл бұрын
Hello, not yet, but stay tuned and we may have something that will of use to you.
@eshleyngomane92763 жыл бұрын
Great video! Can you also make a video on the JBCC contract, if you're familiar with it? Thanks in advance 👍
@Metroun3 жыл бұрын
Hey Eshley, We will definitely look into it. We know it's a contract that is mainly used in South Africa and we are based in the UK so unfortunately we are not familiar with it. That doesn't mean we won't research it and give you guys a "Jbcc Explained" video. Make sure you're subscribed and you may see a familiar titled video in the next few weeks 😏
@amjadaliikram35602 жыл бұрын
Sir I m facing an issue regarding interpretation of Latent Defects. Is the contractor responsible for rectifying Latent Defects after expiry of Defects Liability Period? Which clause of FIDDIC deals with Latent defects? Thank you. Regards, Engr. AMJAD ALI IKRAM, Pakistan
@Metroun2 жыл бұрын
The expiry of the Defects Liability Period does not relieve the Contractor of further liability for defects. The Contractor remains liable to the Employer for any defects that may appear subsequently (commonly called ‘latent defects’) for the duration of the applicable statute of limitation.28 However, an important difference, from the Employer’s point of view, is that the Contractor’s responsibility to rectify latent defects is no longer secured by either the retention money or the performance security. As a consequence, unless the Contractor can be persuaded to rectify the defect voluntarily, the Employer would normally have to pursue the Contractor and/or its assets wherever they can be found in order to obtain relief. Please see link that may help www.fidic.org/sites/default/files/Fourth%20Commentary%2C%20ICC%20Bulletin%2C%20offprint.pdf
@amjadaliikram35602 жыл бұрын
Sir I am really honoured for the very detailed and comprehensive reply. Best regards, Engr. Col(Retd) Amjad Ali Ikram, MS(Engineering),MSc(PM),PE,PMP, CCM, ASQ-Cettified Quality Engineer & CSSGB,Fellow Institution of Engineers Pakistan.
@Metroun2 жыл бұрын
No problem at all, we're always looking to help fellow construction professionals as much as possible!
@amjadaliikram3560 Жыл бұрын
Good day sir, hope you are fine. I need clarifications as under:- 1. Can a contractor get Mob Advance on production of AA Rating Insurance Certificate? 2. Is it possible to open the tenders on the basis of Insurance Guarantee instead of Bid Security? Best regards . Engr. Amjad Ali Ikram
@Metroun Жыл бұрын
As per the FIDIC contracts, the contractor is entitled to a mobilization advance after providing proof of a performance security or guarantee. However, whether or not the contractor can receive a mobilization advance upon production of an AA rating insurance certificate would depend on the specific terms and conditions of the contract between the contractor and the employer. It is recommended that you refer to the contract and seek legal advice to understand the specific terms and conditions related to mobilization advance in your contract. It is generally required that bidders provide a bid security, which is typically in the form of a bank guarantee or a bond. However, the specific terms and conditions related to the bid security requirement may vary depending on the particular FIDIC contract being used. In certain cases, it may be possible for bidders to offer alternative forms of security, such as an insurance guarantee. However, this would need to be agreed upon and specified in the tender documents, and the employer would need to be satisfied that the proposed security is adequate and suitable for the project. It is recommended that you refer to the specific terms and conditions of your FIDIC contract and seek legal advice to understand the requirements related to bid security or alternative forms of security.
@Mamun-bn4wl2 жыл бұрын
Great. today I watched your video and learn many things. Do you recommend me a Quality University and low cost for MSc Quantity Surveying and Contract Management Course?
@Metroun2 жыл бұрын
Hello! We're glad you enjoyed our video. We do have a video that may be useful. Take a look kzbin.info/www/bejne/iprPhXtmrq9prtE
@khaledhassan83043 жыл бұрын
fidic 1987 fourth addition didn't mention,?
@Metroun3 жыл бұрын
This is a brief overview of FIDIC contracts. Each contract will be detailed separately. Both the Yellow and Red book have videos in our library.
@chrispenmuzondo59632 жыл бұрын
Where is it written that Fidic contracts are immeasurable contracts
@Metroun2 жыл бұрын
The Red and Pink Books are remeasurement contracts, whereas the Yellow, Silver and Gold Books are lump sum fixed price contracts.
@nestorguarachibarreto72142 жыл бұрын
Porque no en español 😢
@Metroun2 жыл бұрын
Lamentablemente no hablamos español. Los subtítulos deberían traducirse al español si eso es útil. Gracias por ver