We write exception reports when events take over - something happens that is outside of our planning assumptions. So, how do you write a good exception report? Thank you for watching. Please support the channel and all the free content I provide. - Like, comment, and subscribe to the channel. - Why not join my community, free! Sign-up at onlinepmcourses.com/assets440251/the-onlinepmcourses-newsletter/ - And to show maximum appreciation, use the $ Thanks button, under the video, to make a small donation with a highlighted comment.
@Jasmine-cn4wc9 ай бұрын
Thanks for sharing these practical insights; I'll definitely be implementing them in my project management approach!👍
@Onlinepmcourses9 ай бұрын
You're very welcome.
@joshuaramcharan97359 ай бұрын
Thank you for sharing. Can some examples of project controls to issue this report be discussed?
@Onlinepmcourses9 ай бұрын
Sure... - A key piece of equipment you need for your project is delayed indefinately - A substantial, unanticipated risk materializes - an exceptional weather event causes damage and delay - A significant technical challenge arises with no clear route to resolution - A key individual is taken ill and likely to be off work for a long period - An important stakeholder makes an unhelpful intervention that looks likely to derail a large part of the choices the team agreed on The list can go on and on. Anything big that happens, for which you don't have a contingency plan in place.
@Newbreed02049 ай бұрын
@@Onlinepmcourses Thank you for your lectures, they have been very helpful. I want to ask if a change request could be written in the above listed examples.
@Onlinepmcourses9 ай бұрын
@@Newbreed0204 You're very welcome. If you are asking *can a change request be written in the above listed examples? - then the answer is clearly 'yes'. If you are asking if I will create sample change requests, then the answer is, sadly, 'no'. I just don't have the time.
@Newbreed02049 ай бұрын
@@Onlinepmcourses Thank you for your feedback. Yes, I was asking if a change can be written in the above listed examples. So if a change request can be written, how do we know which to use between change request and exception report.
@Onlinepmcourses9 ай бұрын
@@Newbreed0204 We write an exception report when an exceptional event sets your project back. One option to recover control of the project will often be to change the scope, specification, or some other aspect of the project. If that is the preferred option, you would then prepare a change request. It is not a case of a or b. It's more about the change being the recommendation from the exception request process.