P6 Filters: 4 Week Look Ahead

  Рет қаралды 3,708

PJM Scheduling Services

PJM Scheduling Services

Күн бұрын

Пікірлер: 13
@JohnsonJLB
@JohnsonJLB Жыл бұрын
You actually don't need the second criteria in your filter. If an activity isn't started then the start date within the range criteria will capture both activities that haven't started and have a finish outside the range and activities that haven't started with a finish in the range. The in progress = true will capture BOTH activities that have started with a finish date within the range that have started but have a finish beyond the range.
@PJMScheduling
@PJMScheduling Жыл бұрын
How funny! I actually never thought of that but you are right! Thanks for the comment.
@reginaldibenne6875
@reginaldibenne6875 3 ай бұрын
Can you explain this in details, pls
@JohnsonJLB
@JohnsonJLB 3 ай бұрын
@@reginaldibenne6875 For a 2week lookahead filter there are only two necessary criteria for non-milestone activities. 1. Start is within a range of DD to DD+2W 2. Activity status = In Progress With the Any of the following selection at the top. Hope that helps!
@reginaldibenne6875
@reginaldibenne6875 3 ай бұрын
@@JohnsonJLB thanks in a millions, bro!
@karthikdhandapani4211
@karthikdhandapani4211 2 жыл бұрын
Hey patrick, Thanks for making these videos. Its good to see you again.
@PJMScheduling
@PJMScheduling 2 жыл бұрын
Hey Karthik! Great to hear from you! Hope you are doing well and thanks for reaching out! :)
@drew61377
@drew61377 Жыл бұрын
I have a problem I am being told from my P6 guy can't be done. lol T2/T4 schedule, lets say an activity starts on 1 Aug and ends 21 Aug. I want to see it populate on all 3 weeks, however it only shows on T2 from 1st to the 21st. I need it on show on all 3 weeks throughout the T2/T4 since the work is taking place over 3 weeks. Any help?
@PJMScheduling
@PJMScheduling Жыл бұрын
Can you clarify what you mean by T2/T4? I'm not familiar with that terminology.
@drew61377
@drew61377 Жыл бұрын
@@PJMScheduling the short version is, the T-week process is used for scheduling. If next week is T1, then T2/3/4 are how many weeks into the future that a facility is scheduling.
@PJMScheduling
@PJMScheduling Жыл бұрын
@@drew61377 Got it! Try this - You'll need to run several different filters to capture the work that is scheduled for the week of T2: Assume the start of T1 = Data Date. Start of T2 = DD+1 week. Start of T3 = DD+2 weeks. Filter 1: Start date is within range of DD and DD+1 week AND Remaining Duration is greater than 5 work days. Filter 2 Start date is within range of DD+1 week and DD+2 weeks Filter 3 Finish date is within range of DD+1 week and DD+2 weeks. All three filters can be run at the same time by selecting "Any of the following criteria"
@mahansor8295
@mahansor8295 Жыл бұрын
Hi , thanks for the video How about : Activity status is not equal to complete Start date less than DDD+4W and we need to chooche "All of the following" conditions not "Any of the following" Thanks again
@PJMScheduling
@PJMScheduling Жыл бұрын
That works! I like it! Thanks for sharing!
P6 Filters: Find the Driving Path to a Specific Activity (Float Path)
3:38
PJM Scheduling Services
Рет қаралды 4,8 М.
THE FASTEST Way to Cost Load a P6 Schedule
6:53
PJM Scheduling Services
Рет қаралды 5 М.
Шок. Никокадо Авокадо похудел на 110 кг
00:44
ПРИКОЛЫ НАД БРАТОМ #shorts
00:23
Паша Осадчий
Рет қаралды 6 МЛН
THE BEST WAY to Filter for Activities that have Made Progress in P6
8:55
PJM Scheduling Services
Рет қаралды 3,6 М.
How to Correct Out of Sequence Progress in P6
9:03
PJM Scheduling Services
Рет қаралды 2,1 М.
Creating an S-Curve from Primavera P6
14:37
PJM Scheduling Services
Рет қаралды 11 М.
THE BEST WAY to Filter for Out-of-Sequence Activities in P6
6:59
PJM Scheduling Services
Рет қаралды 4,7 М.
Scheduling Concepts - Part 1: Data Date
4:59
PJM Scheduling Services
Рет қаралды 1,1 М.
Create a Stacked Histogram in P6 from Daily Reports
17:04
PJM Scheduling Services
Рет қаралды 1,8 М.
2023-03-01 - Resources and Costs in Primavera P6
52:38
EAI Emerald
Рет қаралды 179
Шок. Никокадо Авокадо похудел на 110 кг
00:44