Creating an S-Curve from Primavera P6
14:37
P6 Filters: 4 Week Look Ahead
2:39
2 жыл бұрын
Import Resources from Excel to P6
11:32
Пікірлер
@eray1212
@eray1212 13 күн бұрын
great one
@MikePannell-h6r
@MikePannell-h6r 25 күн бұрын
Great video. What if you're trying to find the top ten driving paths to a milestone?
@moussaabbahouli361
@moussaabbahouli361 28 күн бұрын
is there any turorial about shipping delvery and supply on project?
@PJMScheduling
@PJMScheduling 27 күн бұрын
I have not done one regarding delivery of materials on a project. What are you looking for specifically?
@moussaabbahouli361
@moussaabbahouli361 23 күн бұрын
@@PJMScheduling I have multiple trucks and drivers to manage and plan their load and delivery destinations. also multiple machine with operators to plan their workload and back-to-back replacement. It may be close to make up a planning for factory production for example. it would be great if I can find a template.
@TheMinuteMasters
@TheMinuteMasters 2 ай бұрын
What is a "child" is not being created below our project? For me, it keeps adding not "child" WBS. Also my indent our outdent arrows don't function.
@PJMScheduling
@PJMScheduling 2 ай бұрын
Make sure that when you are in the WBS section, your "Group and Sort" is set to "Default".
@AbdulWajid-ns9pe
@AbdulWajid-ns9pe 2 ай бұрын
In the baseline that is the month of June and the have actual finish dates of even Jul., please can you explain this?
@afreemantc
@afreemantc 2 ай бұрын
completely unhelpful
@mithuns6577
@mithuns6577 3 ай бұрын
Very well explained in a neat and simple way... thank you brother...
@reginaldibenne6875
@reginaldibenne6875 3 ай бұрын
Thanks for the wonderful video.. Pls, I have a question. QUESTION.. What is the best way to cost load a project? Is the the export to Excel and Cost load or through resource in Detail view in Primavera P6. Thanks
@Imperium390
@Imperium390 3 ай бұрын
What happened to assignments 6 to 9?
@wwspamtrash
@wwspamtrash 4 ай бұрын
its sad that, no control+F2 :(
@Hagosea75
@Hagosea75 4 ай бұрын
That’s the best tutorial video ever. Thanks.
@elmira5949
@elmira5949 4 ай бұрын
how do we set up a one-on-one session?
@niheerthakur4128
@niheerthakur4128 5 ай бұрын
My manager after reviewing construction schedule on P6 commented “ several activities are riding the data date”. What does that means? Can anyone explain please
@PJMScheduling
@PJMScheduling 5 ай бұрын
It means that all of the predecessors are completed for the activity. Therefore, there are no more active predecessors that are preventing that work from occurring. Only the data date is preventing the activity from occurring. This either means that the activity has to start immediately or should be re-tied to a different predecessor to give it a more accurate projected date.
@niheerthakur4128
@niheerthakur4128 5 ай бұрын
@@PJMSchedulinghow is the data date preventing an activity from happening, isnt the data date just a date to measure the past progress? For example if the data date is 15th April so the P6 data is telling us what was completed on and before 15th April right? So if the activity is schedule to start on the data date how is data date driving it.?
@PJMScheduling
@PJMScheduling 5 ай бұрын
@@niheerthakur4128 You are correct, but all remaining work is calculated from the data date. If you move the data date from April 15th to April 20th, then all remaining work will be calculated based on the earliest start date of April 20th. For example, if you have an activity with no predecessor relationship, and you calculate the schedule, the start date for that activity will be equal to the data date. That is essentially what is happening when your manager says there are activities "riding the data date". All predecessors have been completed for that activity and, as a result, the projected start date for the activity is equal to the data date.
@niheerthakur4128
@niheerthakur4128 5 ай бұрын
@@PJMScheduling ok I understand it now but what is the right practice to follow here to avoid this. I mean if the predecessors are complete and the current activity should now ride the data date. What should be done here or is it nothing wrong to have activities riding the data date?
@PJMScheduling
@PJMScheduling 5 ай бұрын
@@niheerthakur4128 It depends. If there is literally nothing preventing the activity from starting and it is simply not getting done because it's low priority, then it's fine to let it ride the data date. But if it's riding the data date due to inaccurate logic, then I would tie the activity to an appropriate predecessor so that it is scheduled to start when you plan on getting work done.
@kunalbut
@kunalbut 5 ай бұрын
access violation error. cannot proceed
@bananarepublic8951
@bananarepublic8951 5 ай бұрын
One of the best P6 lessons I seen on KZbin. Thanks for this
@johnsafi1104
@johnsafi1104 5 ай бұрын
Please make some videos regarding global change and other advanced things in P6
@johnsafi1104
@johnsafi1104 5 ай бұрын
Great job
@mohamedahmedabdelrhem324
@mohamedahmedabdelrhem324 5 ай бұрын
The Best
@raja.mubbasshir9072
@raja.mubbasshir9072 6 ай бұрын
I had worked on a project A, adjusted its headers, columns, footer, titles etc, taken print outs and closed this. Then I worked on another project and I deleted old project and its enterprise. The second project has different title, header, footer etc. The problem I am having is when I try to access my First project A from .xer file it opens up in new settings even I added another enterprise to that. Can you please help on that
@s.faisal6613
@s.faisal6613 7 ай бұрын
Hi, where are the remaining assignments from 6 to 9? Do you also have other practice P6 projects?
@solomonagunsoye8064
@solomonagunsoye8064 7 ай бұрын
Thanks for the Excellent Video! I got an issue though. My original duration always changes whenever I update the activities with a different actual start and finish date to the baseline but doesn't change when the dates are same as the baseline. Please what am I doing wrongly?
@PJMScheduling
@PJMScheduling 7 ай бұрын
My guess is you have the resource setting checked called "Drive activity dates by default". This can be checked at both the project level and the resource level. So my question would be, #1 - Do you have resources assigned to the activities. #2 - If so, make sure to uncheck the "Drive activity dates by default" on the resource assignment. That should take care of the issue.
@abdullahiqbal7733
@abdullahiqbal7733 7 ай бұрын
When I upload and generate files from your link. It says there was a problem, please try again.
@PJMScheduling
@PJMScheduling 7 ай бұрын
Send me the files at [email protected] and we will take a look.
@Qwetri123
@Qwetri123 7 ай бұрын
Great tutorial!
@goldenknightsfanatic
@goldenknightsfanatic 7 ай бұрын
Thanks for making this playlist. You did a great job with these.
@bokangmukhansi2018
@bokangmukhansi2018 8 ай бұрын
I have assigned a baseline and resources but when I schedule the project my performance% and schedule % change in activities but not on the overall project percentage. How can i fix this so i can see the overall percentage of the project.
@claudiovelasco5627
@claudiovelasco5627 8 ай бұрын
when i try to maintain baseline, and after i pick a baseline i want, it says "The project has baselines of its own. You may not convert this project into a baseline", what do i do ?
@claudiovelasco5627
@claudiovelasco5627 8 ай бұрын
can i delete a baseline so i can start over with the updates
@shakeeln2020
@shakeeln2020 8 ай бұрын
If filter float path >1 putting why will happen
@shakeeln2020
@shakeeln2020 8 ай бұрын
Very nice it's work 👍 Thank you buddy🎉
@kupelwakasongo5937
@kupelwakasongo5937 8 ай бұрын
How do you arrange activities in numerical order? I am struggling to do that, I have say A10240 which is preceded A1000
@MrJithingopal143
@MrJithingopal143 9 ай бұрын
How we knows our data date while scheduling
@PJMScheduling
@PJMScheduling 9 ай бұрын
Click the "Tools" tab at the top of the screen, and click "Schedule". It will display the data date.
@MrJithingopal143
@MrJithingopal143 9 ай бұрын
@@PJMScheduling so we doesn’t need to change the date which coming as default.some times I noticed that while doing it entire schedule dates are changing
@PJMScheduling
@PJMScheduling 9 ай бұрын
@@MrJithingopal143 Try going to "Schedule Options" under schedule, and uncheck "Schedule automatically when a change affects dates". That should fix your issue. You can then manually reschedule the program after you make a change to recalculate the date.
@cervantes121
@cervantes121 9 ай бұрын
Any planning videos?
@PJMScheduling
@PJMScheduling 9 ай бұрын
What do you mean by planning videos? Would love to know what you're in search of.
@KehindeGlam
@KehindeGlam 9 ай бұрын
You're the absolute best! I'm extremely grateful for these free lessons. Thanks a lot!
@Mileyrubymiles
@Mileyrubymiles 10 ай бұрын
This video rescued me, thank you so much
@justchary
@justchary 10 ай бұрын
Thanks you!
@daziong
@daziong 10 ай бұрын
Thanks, I learned a lot from your video, really appreciate your great work. You are the best P6 teacher in KZbin.
@kadieanna1748
@kadieanna1748 10 ай бұрын
Thanks for the video, Pat! It's concise and very informative.
@samgriffith568
@samgriffith568 10 ай бұрын
I've was finally able to upload the mpx into p6 following your instructions but can you think of any reason why I'm getting incorrect dates/data? Especially on the activity types not-completed/in-progress.
@diverzzz.
@diverzzz. 11 ай бұрын
Let's suppose we don't remember the actual start date of the activity 'Foundation'. The activity was to finish by 21 July but it didn't finish by the Baseline finish date. Today is 24th of July and we know that the said activity is 70 % complete. Can we go to '% Activity Complete column' and directly write 70% and schedule it? Will it be right thing to do?
@CamilaHaas-v1x
@CamilaHaas-v1x 11 ай бұрын
Thank you for the video, super helpful! I'll definitely watch some other ones :)
@wind_blue_day
@wind_blue_day 11 ай бұрын
thank you so much. It is very useful and easy and I didn't know how to do it.
@lcoley99
@lcoley99 Жыл бұрын
Do you have a video showing how to cost loading that automatically updates through percent complete method?
@PJMScheduling
@PJMScheduling Жыл бұрын
I have not made a video showing the set-up of the resources for that yet! I need to though. I will put one together in the coming months as it's on my list of videos to do. If you are in a pinch - we can set-up a tutoring session by messaging me here and I can show you how: tools.pjmss.com/user/Patrick/ Essentially, you need to set your resources to $1/unit, ensure you have auto-compute actuals and calculate costs from units checked, and enter the budgeted cost in the budgeted units field.
@lcoley99
@lcoley99 Жыл бұрын
@PJMScheduling sure. How long will that take to show me how to perform that task and can it be recorded?
@PJMScheduling
@PJMScheduling Жыл бұрын
I think about 30 minutes. Yes, I record the session and send you a downloadable version; however, you are not allowed to repost. It's only for personal use.
@lcoley99
@lcoley99 Жыл бұрын
@@PJMScheduling I messaged you through the link but no response?
@PJMScheduling
@PJMScheduling Жыл бұрын
I don't see a message through there - Make sure you create an account and then message me. If it's not working, email [email protected] and I'll connect with you to set up a session.@@lcoley99
@raiseyourshieldboys1743
@raiseyourshieldboys1743 Жыл бұрын
I've learned a lot from your tutorials and see you as my mentor can you please made same for power bi? It will be great
@PJMScheduling
@PJMScheduling Жыл бұрын
Thank you! Really appreciate that! I would love to make some power bi videos. Great recommendation.
@jameskent6079
@jameskent6079 Жыл бұрын
The video is blurry. But great information
@PJMScheduling
@PJMScheduling Жыл бұрын
Thanks! Make sure to increase your video quality settings to 1080p. For some people, depending on your bandwidth, it may have started the video at a lower quality setting.
@andyli7598
@andyli7598 Жыл бұрын
awesome vis, can you make a vid for detailed resource loading and its fundamental.
@alextobar8706
@alextobar8706 Жыл бұрын
Are you able to teach a construction framing schedule for residential home building or tutor availability
@PJMScheduling
@PJMScheduling Жыл бұрын
Thanks for reaching out! If you are looking for tutoring, feel free to message me here: tools.pjmss.com/user/Patrick/ I am familiar with construction framing and residential home building schedules. Reach out and let me know what you're working on!
@hassanrasheed3148
@hassanrasheed3148 Жыл бұрын
wow you made it so easy and simple thanks, can you please also show how to update the S-curve to see earned values every month
@drew61377
@drew61377 Жыл бұрын
I have a problem I am being told from my P6 guy can't be done. lol T2/T4 schedule, lets say an activity starts on 1 Aug and ends 21 Aug. I want to see it populate on all 3 weeks, however it only shows on T2 from 1st to the 21st. I need it on show on all 3 weeks throughout the T2/T4 since the work is taking place over 3 weeks. Any help?
@PJMScheduling
@PJMScheduling Жыл бұрын
Can you clarify what you mean by T2/T4? I'm not familiar with that terminology.
@drew61377
@drew61377 Жыл бұрын
@@PJMScheduling the short version is, the T-week process is used for scheduling. If next week is T1, then T2/3/4 are how many weeks into the future that a facility is scheduling.
@PJMScheduling
@PJMScheduling Жыл бұрын
@@drew61377 Got it! Try this - You'll need to run several different filters to capture the work that is scheduled for the week of T2: Assume the start of T1 = Data Date. Start of T2 = DD+1 week. Start of T3 = DD+2 weeks. Filter 1: Start date is within range of DD and DD+1 week AND Remaining Duration is greater than 5 work days. Filter 2 Start date is within range of DD+1 week and DD+2 weeks Filter 3 Finish date is within range of DD+1 week and DD+2 weeks. All three filters can be run at the same time by selecting "Any of the following criteria"
@123rockstar2010
@123rockstar2010 Жыл бұрын
@3:00 If you set the Unit of Time from "hour" to "day" (and checked the Show Unit Label), the Default Units/Time would show 4d/d... And that makes it 4men/day? I am confused.
@PJMScheduling
@PJMScheduling Жыл бұрын
It takes it from 8 units/day to 1 unit/day. If you leave the Unit of Time in hours and want to resource load the activity, you'll need to multiply the number of men per day by the number of hours per day for that calendar. In this example, I was using men/day instead of manhours/day. There's been times on projects where I wasn't paying attention to the settings, and I incorrectly assigned manhours to an activity when I should have entered men/day, and visa versa. Just something to be aware of before you start resource loading.
@123rockstar2010
@123rockstar2010 Жыл бұрын
For those who don't know where the PJMSS-BL1 *Baseline Schedule* went: 1. Open PJMSS-UP1 *Update #01* project. 2. Project tab > Assign Baseline 3. Primary > (Remove *Baseline Schedule*) > OK 4. Project tab > Maintain Baseline 5. (Select *Baseline Schedule*) > Restore > YES to unlink 6. Go to Projects 7. PJMSS-UP1 *Update #01* is now under Updates WBS optional: 8. Cut and Paste PJMSS-UP1 *Update #01* to Baseline WBS