PMP Exam Questions 2024 (Jan) and Answers Practice Session | PMP Exam Prep | PMP for Project Manager

  Рет қаралды 23,671

PMPwithRay

PMPwithRay

Күн бұрын

Пікірлер
@PMPwithRay
@PMPwithRay 11 ай бұрын
Join my FREE Webinar for PMP Exam Prep 2024: event.webinarjam.com/channel/pmpwithray2024 10 Tips for PMP Exam in 2024 (FREE e-book): www.pmpwithray.com/pmp-certification-exam-study-guide-for-beginners
@guruprasadhn5525
@guruprasadhn5525 11 ай бұрын
I got 4 correct, for last question, I got a very good insights from your explanation, thanks
@PMPwithRay
@PMPwithRay 11 ай бұрын
Thank you for watching and commenting!
@MohammedWaseemMulla-sm9cj
@MohammedWaseemMulla-sm9cj 11 ай бұрын
Hi sir .regarding the below question request you to answer with clarification A project manager is assigned to a critical software development project. The team is using a hybrid approach and has divided development into four sprints. At the end of sprint three, the project manager discovers that the earned value (EV) is US$500,000 and the planned value (PV) is US$550,000. What should the project manager do? A. Fast track the project B. Adjust the budget C. Introduce a float D. Adjust the project time line
@PMPwithRay
@PMPwithRay 11 ай бұрын
Hi, I think the answer and clarification should come from you rather than me :) Then I am all happy to correct you where you go wrong!
@cheimaeroudane9454
@cheimaeroudane9454 10 ай бұрын
@@PMPwithRayis it A because we are here behind schedule ?
@winnermon803
@winnermon803 5 ай бұрын
In question 4, the product owner prioritizes the backlog, the feature would be part of the next backlog, so the Project manager and product owner taking action would make the most sense, no?
@PMPwithRay
@PMPwithRay 5 ай бұрын
Yes, decisions should be taken in collaboration, but you have to select the BEST answer form the given options.
@donnamartin9569
@donnamartin9569 8 ай бұрын
Question 4 - You decided D was a better option than B because we are empowering the team. I concur that the piece about telling the team how to implement is almost never the agile way. But it does allow the the Product Owner to be involved in the decision about whether to include the change or not and since the PO has ultimate responsibility for the project - it seems like excluding him from the discussion in answer D makes that as equally incorrect. So I feel like these types of questions end up being a crap shoot for us. I feel like we need an assumptions log for these types of questions so we can at least get partial credit when our reasoning is sound but the answer is not what was given. Thoughts?
@russ4u4love
@russ4u4love 7 ай бұрын
33:13 I also have similar opinion. Since as per agile practice , product owner is the owner of backlogs, the first person to discuss any new changes to the backlog is to product owner not the team hence I also believe answer b is better than d.
@TEverettReynolds
@TEverettReynolds 6 ай бұрын
​@@russ4u4love I agree and want clarification from Ray. The problem I see with B is that the PM is dictating the update to the team. So... who is "the team"? I assume the team is everyone from the PO, the PM or Scrum Master, and the Devs. In that, the PM is wrong. He must include everyone in the feature request discussion. He must at least engage the Devs to get an idea of how much time and effort would be spent on the new feature. Collaboration and facilitation are the keys here. D is the better choice since the PM engages the whole team to discuss the feature request and then discuss the impact with the stakeholders.
@siddharthsharma8567
@siddharthsharma8567 3 ай бұрын
Agree.. and assuming that coaching came from impact analysis that you did with product owner and ignoring key words like impact analysis and inclusion of PO doesn't feel right.
@creatdino1
@creatdino1 2 ай бұрын
I also feel ambiguous about selecting option D, because in this question PM has a situation to respond to and is the PM really expected to start coaching the team and rely on the team's decision ( assuming that the team is inexperienced and hence requires coaching).
@Sahnoun23
@Sahnoun23 11 ай бұрын
I got 5 correct, for question 5, I wasn’t sure but I got better insights from your explanation, many thanks
@PMPwithRay
@PMPwithRay 11 ай бұрын
Thank you for watching and commenting!
@EduWorld1690
@EduWorld1690 10 ай бұрын
I have PMBOK guide edition 7. Please let me know which additional books will be needed to cover complete syllabus
@ilanchezian822
@ilanchezian822 10 ай бұрын
This is really well explained 5 top notch questions and much to learn, Thank you Mr. Ray 3/5
@PMPwithRay
@PMPwithRay 10 ай бұрын
Glad it was helpful! Keep practising :)
@faisalgulzar4538
@faisalgulzar4538 7 ай бұрын
In question no 3, PMO stands for project management office (not project management organization) right?
@PMPwithRay
@PMPwithRay 7 ай бұрын
Yes, PMO stands for project management office
@SIAMAK_R
@SIAMAK_R 11 ай бұрын
I'm confused about what was selected in question no.2 Each backlog item should have a set of conditions of satisfaction as specific acceptance criteria that is specified by the product owner. DoD is an internal agreement between developers to assure of task characteristics and tests are completed. I cant undrestand changing DOD or making it more robust may not help to change the situation .
@PMPwithRay
@PMPwithRay 11 ай бұрын
DoD is an agreement within developers for sure, but that should be aligned with the customer as well keeping them in loop. DoD cannot be drafted by isolating the customer/end-user.
@SIAMAK_R
@SIAMAK_R 11 ай бұрын
Got it 👍 thanks
@susanbenny8522
@susanbenny8522 9 ай бұрын
4/5. 4th question was very tricky
@PMPwithRay
@PMPwithRay 9 ай бұрын
Thank you for participating and commenting!
@fahimrahman4001
@fahimrahman4001 9 ай бұрын
Your training classes are very helpful ❤👍
@PMPwithRay
@PMPwithRay 9 ай бұрын
Glad you like them!
@SamuelJohnKC
@SamuelJohnKC 2 ай бұрын
Nonchalant means relaxed and calm in a way that shows you don't care or aren't worried about something. For example, you might describe someone as nonchalant about winning an award.
@PMPwithRay
@PMPwithRay 2 ай бұрын
You're right!
@steventhomas7761
@steventhomas7761 6 ай бұрын
Question4: The correct ✅ option is B. As per PMBOK: It emphasizes the importance of conducting an impact analysis as part of the integrated change control process and ensures that any change/s are assessed in terms of their effect on the project scope, schedule, cost, and resources before any decision is made. As per Agile Practice Guide: In Agile frameworks, changes are often reviewed and analyzed during sprint review meetings. The product owner plays a key role in determining the value and priority of changes or backlogs , and an impact analysis helps the team understand the implications and decide the best course of action.
@ihabjalal9
@ihabjalal9 5 ай бұрын
You are great and simple
@PMPwithRay
@PMPwithRay 5 ай бұрын
Glad to hear that! Thank you!
@sumitmitra7336
@sumitmitra7336 11 ай бұрын
Nonchalant- Indifferent
@PMPwithRay
@PMPwithRay 11 ай бұрын
That's correct :)
@INCOMuratKoluk
@INCOMuratKoluk 7 ай бұрын
Question no:1 Is the product owner's responsibility to arrange a training? I think, product owner supposed to discuss this with PM and suggest a training for the team?
@PMPwithRay
@PMPwithRay 7 ай бұрын
Yes, it can be done either ways but for this question that is the best option.
@anandrajput6654
@anandrajput6654 11 ай бұрын
Nonchalant means, lost the interest in a project
@PMPwithRay
@PMPwithRay 11 ай бұрын
That's correct :)
@SasidharReddy-fs3xe
@SasidharReddy-fs3xe 10 ай бұрын
Very good explanations highlighting the mindset of a PM from PMP recommendation. Thank you
@PMPwithRay
@PMPwithRay 10 ай бұрын
Glad you liked it! Thank you for watching and commenting!
@VBHAT99
@VBHAT99 9 ай бұрын
4/5, really good
@PMPwithRay
@PMPwithRay 9 ай бұрын
Thanks for watching and participating!
@vishalsuvarna2896
@vishalsuvarna2896 11 ай бұрын
Is there any question bank I could refer and get exams cleared
@PMPwithRay
@PMPwithRay 11 ай бұрын
Hello, please check my mock question bank on Udemy: bit.ly/raypmpmock
@kennguyen1066
@kennguyen1066 11 ай бұрын
@@PMPwithRay I don’t see your courses on Udemy Business. Any idea?
@ibrar051
@ibrar051 11 ай бұрын
scored 3 /5 , Hi ,, ray i m looking for parctice q/a to prepare my self for 2024 pmp exam... pls advice.. do u have simulation .. ?
@PMPwithRay
@PMPwithRay 10 ай бұрын
Please check my mock simulator on Udemy: bit.ly/raypmpmock
@guything1234
@guything1234 9 ай бұрын
​@@PMPwithRayThe stimulator course isn't visible at the Udemy business??
@shahbazrana6713
@shahbazrana6713 11 ай бұрын
Asslam O Alikum Amir Sir I need one information regarding PMP 3xame. I,m doing self preparation. I want ask In 2024 have any chance of change the exame criteria of pmp exame for example course outline or anything. Right I, m doing focus people, process domain
@metroswiftmovers1284
@metroswiftmovers1284 9 ай бұрын
Great. keep it up
@PMPwithRay
@PMPwithRay 8 ай бұрын
Thanks for watching and commenting!
@etimasuquo6167
@etimasuquo6167 9 ай бұрын
Ray is one of the best. I am happy I bought your course on Udemy, I am about taking my PMP exam , am enjoying and learning from you course already
@PMPwithRay
@PMPwithRay 9 ай бұрын
Great to hear! Thank you for watching and commenting!
@ajoydas9863
@ajoydas9863 11 ай бұрын
question 2 answer is C
@PMPwithRay
@PMPwithRay 11 ай бұрын
Thank you for participating & commenting! :)
@Dr.PreshU.Okoroafor
@Dr.PreshU.Okoroafor 11 ай бұрын
Thank you very much for this video
@PMPwithRay
@PMPwithRay 11 ай бұрын
My pleasure!
@PrabhuDHA23
@PrabhuDHA23 9 ай бұрын
Nonchalant- doesn’t bother about project
@PMPwithRay
@PMPwithRay 9 ай бұрын
Thank you for watching and commenting!
@ajoydas9863
@ajoydas9863 11 ай бұрын
QUESTION NO3 ANSWER IS B
@PMPwithRay
@PMPwithRay 11 ай бұрын
Thank you for participating & commenting! :)
@AbdelrahmanAbdelrahman-rx8is
@AbdelrahmanAbdelrahman-rx8is 8 ай бұрын
Thanks
@PMPwithRay
@PMPwithRay 8 ай бұрын
Welcome! Thank you for watching and commenting!
@BRYANTPEARS
@BRYANTPEARS 11 ай бұрын
Love It. Thank You
@PMPwithRay
@PMPwithRay 11 ай бұрын
Thank you for watching and commenting!
@kunlesegun3737
@kunlesegun3737 6 ай бұрын
non challant mean lackadaisical attitude.
@PMPwithRay
@PMPwithRay 6 ай бұрын
Yes, that's correct :)
@mahsainitaly
@mahsainitaly 7 ай бұрын
i got 4/5 ( could be 5 also )
@PMPwithRay
@PMPwithRay 7 ай бұрын
Thank you for participating and commenting!
@saeedfakhr1773
@saeedfakhr1773 4 ай бұрын
2/5
@PMPwithRay
@PMPwithRay 3 ай бұрын
Thank you for watching and participating!
@refaatelshamy1006
@refaatelshamy1006 11 ай бұрын
I got 2 correct
@PMPwithRay
@PMPwithRay 11 ай бұрын
Thank you for watching and commenting!
@nidhisangam3450
@nidhisangam3450 7 ай бұрын
5/5
@PMPwithRay
@PMPwithRay 7 ай бұрын
Thank you for participating and commenting!
@divinegula9172
@divinegula9172 6 ай бұрын
4/5
@PMPwithRay
@PMPwithRay 6 ай бұрын
Thank you for participating and commenting!
@raghvendramishra6641
@raghvendramishra6641 11 ай бұрын
I got 4/5
@PMPwithRay
@PMPwithRay 11 ай бұрын
Thank you for watching and commenting!
@ajoydas9863
@ajoydas9863 11 ай бұрын
QUESTION 3 IS ANSWER IS c
@PMPwithRay
@PMPwithRay 11 ай бұрын
Thank you for participating & commenting! :)
@bpvadivel
@bpvadivel 10 ай бұрын
3/5
@PMPwithRay
@PMPwithRay 10 ай бұрын
Thank you for participating and commenting!
@prabhjotkaurbedi3016
@prabhjotkaurbedi3016 2 ай бұрын
i got 4, last one got incorrect. but got the explanation
@PMPwithRay
@PMPwithRay Ай бұрын
Thank you for watching and participating!
@souptiktirtha8136
@souptiktirtha8136 11 ай бұрын
Got 3 /5. It was tough. Thank you ❤
@PMPwithRay
@PMPwithRay 11 ай бұрын
Thank you for participating and commenting!
@chikaonyedibe501
@chikaonyedibe501 11 ай бұрын
I got 3
@PMPwithRay
@PMPwithRay 11 ай бұрын
Thank you for watching and commenting!
@nijammohideen128
@nijammohideen128 9 ай бұрын
2/5 only.
@PMPwithRay
@PMPwithRay 8 ай бұрын
Thanks for watching and participating!
@ogisgomez5807
@ogisgomez5807 5 ай бұрын
I scored 4 out of 5. I missed the last question.
@PMPwithRay
@PMPwithRay 4 ай бұрын
No worries. Thank you for participating and commenting!
@azharbashir8208
@azharbashir8208 11 ай бұрын
2/5
@PMPwithRay
@PMPwithRay 11 ай бұрын
Thank you for watching and commenting!
@PrabhuDHA23
@PrabhuDHA23 9 ай бұрын
Only 3😢
@PMPwithRay
@PMPwithRay 9 ай бұрын
Thank you for participating and commenting!
@souvikdasgupta652
@souvikdasgupta652 9 ай бұрын
Hi Ray, PMO = Project Management Office or Project Management Organization ?
@josephj1234567
@josephj1234567 6 ай бұрын
Office
@JohnsonSeun-h7t
@JohnsonSeun-h7t 10 ай бұрын
Many thanks for the video
@PMPwithRay
@PMPwithRay 10 ай бұрын
Thank you for watching and commenting!
@soorajh8043
@soorajh8043 5 ай бұрын
3/5
@PMPwithRay
@PMPwithRay 5 ай бұрын
Thank you for participating and commenting!
@mayanktandon3
@mayanktandon3 10 ай бұрын
4/5
@PMPwithRay
@PMPwithRay 10 ай бұрын
Thank you for participating and commenting!
@rabiakhan264
@rabiakhan264 3 ай бұрын
2/5
@PMPwithRay
@PMPwithRay 3 ай бұрын
Thank you for participating and commenting!
@sheillaayot5745
@sheillaayot5745 9 ай бұрын
3/5
@PMPwithRay
@PMPwithRay 9 ай бұрын
Thank you for participating and commenting!
@souvikdasgupta652
@souvikdasgupta652 9 ай бұрын
3/5
@PMPwithRay
@PMPwithRay 9 ай бұрын
Thank you for participating and commenting!
Что-что Мурсдей говорит? 💭 #симбочка #симба #мурсдей
00:19
Арыстанның айқасы, Тәуіржанның шайқасы!
25:51
QosLike / ҚосЛайк / Косылайық
Рет қаралды 700 М.
How to treat Acne💉
00:31
ISSEI / いっせい
Рет қаралды 108 МЛН
PMP JOURNEY| Where should I start
31:15
Edward Coke, Jr
Рет қаралды 5 М.
PMBOK 7th Edition Questions and Answers to Pass Your PMP (1 to 10)
30:02
David McLachlan
Рет қаралды 120 М.
The Most Important 10 PMP Mindsets to Approach PMP Questions
40:03
PMBOK® Guide 6th Ed Processes Explained with Ricardo Vargas!
53:23
Ricardo Vargas
Рет қаралды 1,9 МЛН
Что-что Мурсдей говорит? 💭 #симбочка #симба #мурсдей
00:19