Pond Constructions
Step 1.
08-01-2021
Using 4 nos of TRACTOR mounted with Excavator & Blades.
Excavation, Leveling & Compaction done more accurately and professionally.
Step 2.
31-01-2021
After Completion of excavation we have use 5 bags of Limestone as the limestone will act as a coagulant which causes the algae and the phosphorous to settle to the bottom of the pond.
Step 3.
31-01-2021
Pumping of water through nearby Cannel which is connected with a river called Merakhong River.
Will show the progressive work taken place at the newly constructed farm.
To be continued.