What do you do to make tracking EV metrics easier in P6?
@CristinaCosma-o8v6 ай бұрын
Thought that EV is actually the BCWP (Budgeted Cost of Work Performed), and AC is ACWP (Actual Cost of Work Performed) and PV is BCWS (Budgeted Cost of Work Scheduled). Am I confusing the EVA/EVM terms?
@HassanAhmed-nc7kcАй бұрын
very nice thank you a lot
@othanertv215219 күн бұрын
Mabuhay po kayo lahat PNP
@bbcc2020 Жыл бұрын
Hi Michael, many thanks for contributing to the body of knowledge, no doubt your videos have saved many from embarrassment. Thanks a lot! Could you please advise how to calculate the Cumulative SPI in a project, I've been searching online for videos to no avail. 😊
@reginaldibenne68756 ай бұрын
Thanks, Mike
@mikeloughery6422 Жыл бұрын
Great video. Thanks for explaining why the labor units' fields as an alternate option if not loading indirects & material in P6. Going to look into the course for my team & I.
@PlanAcademy Жыл бұрын
Thanks Mike - FYI - check out our offering for team training from the website. "Solutions for Companies".
@mohammadjavadnaderi52036 ай бұрын
Hi What's the formula calculate sch % complete when change resource curve to back loaded
@VladimirKozomara11 ай бұрын
Thanks Michael !
@PlanAcademy11 ай бұрын
You're welcome Vlad.
@sakooo12 Жыл бұрын
can i take the course if am a beginner in P6?
@ggmu799210 ай бұрын
Great video Michael . Kind of putting my schedule review hat on here and was just curious. Why does Activity ID A1000 have earned value as 0 despite some progress and actual costs. Does that mean there is something wrong with the data input. I know this is a sample schedule but just curious
@ggmu799210 ай бұрын
Does that mean along with the schedule % complete the activity % complete and performance % complete need to be updated for each and every summary/cost activity to accurately track down EVM ? Seems to cumbersome tbh .
@PlanAcademy9 ай бұрын
Hey - not exactly - if the activity is done, those values all go to 100% automatically. But if they remain in-progress during a period update, you will have to specify those values.
@PlanAcademy9 ай бұрын
A1000 is a WBS summary activity used for capturing indirects or overhead costs. So it's not an activity that "earns" value because there is no work on it.