Resource Allocation & Leveling - Project Management - Tutorial & Example

  Рет қаралды 106,824

AF Math & Engineering

AF Math & Engineering

Күн бұрын

Пікірлер: 31
@Chichi-ez1xo
@Chichi-ez1xo 3 жыл бұрын
My goodness!!! Where have you been the last 2 years of my life?!!!!!! Thank you Thank you very much! this was very helpful, well detailed and specifically explained!
@talk2minie
@talk2minie 3 жыл бұрын
This was very helpful! I was able to complete my course homework thanks to your explanation.Thank you very much!
@adityapatel8701
@adityapatel8701 3 жыл бұрын
As activity E depends on completion of activity C. It is not possible to keep both on same day. To lower the labor demand we will have to extend the duration of the project by one day.
@rinatbekmukhanbet3722
@rinatbekmukhanbet3722 Ай бұрын
activity E depends on C and D, since D's EF=12 and more than C's EF=8, we'll take 12 as activity E's ES, so activity E depends on the completion of D. in a backward pass LS=12, LF=13.
@vp-xk3rt
@vp-xk3rt 5 жыл бұрын
Thank you sir Your explanation is very accurate and to the point Helped me a lot for my exams
@AFMathandEngineering
@AFMathandEngineering 5 жыл бұрын
Glad to hear! Thanks!
@AFMathandEngineering
@AFMathandEngineering 5 жыл бұрын
At the end of the video we place Task 'C' and Task 'E' at the same day. As this is a Start to Finish relationship we can assume that the work will first start with assignment C and only once 'C' is done 'E' will start. We can do that as long as the question/project permits us to perform two tasks at the same day. when you think about it, it makes sense that first we pave and only later we demobilize. However, if we would have a curing time that requires a day or the question would specify that only one task is allowed per day we would have to further allocate the task. If this would be the case we would probably delay the project by one day. Check this link for the rest of our videos on project management! kzbin.info/aero/PLv11OuQcvb_C5j9lt9ijPIndiNqBEBh-C
@Kalosb
@Kalosb 4 жыл бұрын
but C is a predecessor of E so if the last activity of C comes to the day when E is meant to start, that means E cant start, because C has not finished .....what do you think?
@AFMathandEngineering
@AFMathandEngineering 3 жыл бұрын
See my comment above.
@edlakaumbi8619
@edlakaumbi8619 8 ай бұрын
yes and it is also 4 days long, so will it not delay the project?
@anhtruong2636
@anhtruong2636 3 жыл бұрын
Very good and funny videos bring a great sense of entertainment!
@Orthodox19.
@Orthodox19. 2 жыл бұрын
Your explanation is very accurate and to the point i.e it was very easy to understand SO Keep it up !!!@
@andrewmurschel2608
@andrewmurschel2608 6 ай бұрын
This also makes the assumption that task C can pause once started. Bear in mind that some tasks cannot pause like that without negative facets.
@elizemach
@elizemach 3 жыл бұрын
LF of activity C is day 12 - and you alocated it to day 13???
@engsingla85
@engsingla85 2 жыл бұрын
Pl resolve this conflict
@mongezinkandi6544
@mongezinkandi6544 5 ай бұрын
Can you please clarify this for me, the task C part that you reallocated to day 13, how did you do it, hence the task E depends on tasks C and D? I hope you'll get my question. Thanks in advance
@benyang6546
@benyang6546 3 жыл бұрын
so touching for an excellent video
@SadamHussain-yx4sl
@SadamHussain-yx4sl Жыл бұрын
Thank you for solution. Sir, I little bit confusion here because, we have Total Flot of activity C is 4, but we shift labour (8) five time why?
@navnithrajsn1705
@navnithrajsn1705 3 жыл бұрын
Very nicely explained thanks
@btpex536
@btpex536 2 жыл бұрын
Sir actually there is a mistake as C latest finish time is 12 but u took it too 13 which is not correct.
@quizzlerprofessor
@quizzlerprofessor 3 жыл бұрын
Helpful content thanks
@ahmeddesoky3599
@ahmeddesoky3599 Жыл бұрын
Thank you for the effort. I've noticed that the date you used in your example are not that precise. At the end you'll end up extending the project by 1 day.
@AFMathandEngineering
@AFMathandEngineering 4 жыл бұрын
If you liked this video check out our Project Management Cheat Sheet Tutorial video in the link below. kzbin.info/www/bejne/gHeyYoN_rrV6fbs
@PiyushKumar-ru6io
@PiyushKumar-ru6io 3 ай бұрын
Thanks.
@balamuruganr6840
@balamuruganr6840 3 жыл бұрын
If i want to use all 15 labors every day, what should i do? Thanks in advance.
@saharincuker7718
@saharincuker7718 4 жыл бұрын
Excellent Video! Sorry for chiming in, I am interested in your thoughts. Have you considered - Teannah Psychic Sucker (Sure I saw it on Google)? It is a good one off product for finding the best project management and business templates minus the headache. Ive heard some interesting things about it and my coo-worker after many years got amazing results with it.
@AFMathandEngineering
@AFMathandEngineering 4 жыл бұрын
Actually I am not really familiar with that method.
@samratparajuli6032
@samratparajuli6032 2 жыл бұрын
muhaah !!!
@carmenalcala6947
@carmenalcala6947 4 жыл бұрын
Great video content! Excuse me for chiming in, I would love your opinion. Have you thought about - Teannah Psychic Sucker (Have a quick look on google cant remember the place now)? It is a good one off product for finding the best project management and business templates without the normal expense. Ive heard some super things about it and my work buddy at last got amazing results with it.
@somethingdoesntaddup8413
@somethingdoesntaddup8413 4 жыл бұрын
4:13 modern feminist TRIGGERED
@АсенМирославов
@АсенМирославов 2 жыл бұрын
동영상에 있는 상당히 불쾌한 이미지
What is Resource Smoothing? (Resource Histogram Example)
7:43
Pieter Rademeyer
Рет қаралды 4,6 М.
coco在求救? #小丑 #天使 #shorts
00:29
好人小丑
Рет қаралды 120 МЛН
It works #beatbox #tiktok
00:34
BeatboxJCOP
Рет қаралды 41 МЛН
When you have a very capricious child 😂😘👍
00:16
Like Asiya
Рет қаралды 18 МЛН
Earned value analysis worked example
10:32
Engineer4Free
Рет қаралды 507 М.
Resource Leveling
6:03
AbleSim
Рет қаралды 36 М.
Problem on Resource levelling,  resource allocation,  Resource scheduling for project
27:01
Edutech Guru Engineering Learning-By Priyanka ma'am
Рет қаралды 26 М.
PMBOK® Guide: Resource Optimization - Resource Levelling & Resource Smoothing for PMP Success
8:05
Hardy's Integral
13:47
Michael Penn
Рет қаралды 15 М.
What is Resource Levelling? And how does it differ from Resource Smoothing?
6:44
Online PM Courses - Mike Clayton
Рет қаралды 41 М.
Resource leveling and allocation
29:35
Principles of construction management
Рет қаралды 32 М.
coco在求救? #小丑 #天使 #shorts
00:29
好人小丑
Рет қаралды 120 МЛН