SAFe®️ PI Planning: PI Objectives - Committed Uncommitted -5 of 7

  Рет қаралды 6,158

iZenBridge Consultancy Pvt Ltd.

iZenBridge Consultancy Pvt Ltd.

2 жыл бұрын

At the end of the PI Planning meeting, each team identifies a business-level goal for the upcoming Program Increment (PI). This goal is called Team's PI Objective. To make the commitment on PI Objective more reliable, SAFe recommends having committed and uncommitted PI Objectives
Our Seven PI Planning Videos
------------------------------------------------
#1: Program Backlog Readiness • SAFe® PI Planning : Pr...
#2: PI Planning Readiness with Agile Teams • SAFe®️ PI Planning: Re...
#3: Agenda and Structure of PI Planning meeting • SAFe®️ PI Planning : A...
#4: PI Planning Team Breakout Sessions • SAFe®️ PI Planning: Te...
#5: PI Objectives - Committed / Uncommitted • SAFe®️ PI Planning: P...
#6: Preparing Program Board • SAFe®️ PI Planning: Pr...
#7: PI Planning Roles and Responsibilities • SAFe®️ PI Planning: Ro...
Check our upcoming SAFe sessions here: www.izenbridge.com/scaled-agile/
In case of any query feel free to reach sales@izenbridge.com or (+91) 9958287711
More information on scaled agile framework can be found at : scaledagileframework.com/

Пікірлер: 16
@pareshgheewala8933
@pareshgheewala8933 Жыл бұрын
thank you .. this video made it clear about committed v/s uncommitted related to PI.
@emmanuelchukwudubemduru5737
@emmanuelchukwudubemduru5737 2 жыл бұрын
Thank you for all these videos, you're awesome !
@izenbridge
@izenbridge 2 жыл бұрын
Glad you like them!
@CuteDoggyBhairu
@CuteDoggyBhairu 9 ай бұрын
Sir, wonderful session. Love your way of explaining with a smiling face. can you please explain how the business value is assigned to PI objectives?
@mahnarayan2185
@mahnarayan2185 Жыл бұрын
Sir what is the frequency of PI planning event ? Do we have any situation that PI planning is conducted at ad-hoc basis ..pls suggest
@izenbridge
@izenbridge Жыл бұрын
Frequency is once in PI, and PI is of 8 to 12 Weeks , ad-hoc as name suggested is can't be planned to things happen as they needed.
@jaycee1363
@jaycee1363 Жыл бұрын
Very informative video. What happens if the team is unable to complete 100% of all the committed PI objectives by the end of the PI?
@izenbridge
@izenbridge Жыл бұрын
Things can go wrong, but better we come to know as they go wrong, mean good to identify is some of the PI objectives are not going to get met during the PI itself rather than at the end. What we do, we depend on the situation, SAFe suggest apply SAFe principles to make decisions.
@jaycee1363
@jaycee1363 Жыл бұрын
@@izenbridge Thank you. And how do we do it? Do we carry over the objectives to the next PI?
@izenbridge
@izenbridge Жыл бұрын
@@jaycee1363 it depends , yes if the priority remains high for given features they are most likely to get planned in upcoming PI , so we discuss them along with other items in coming PI planning meeting
@jaycee1363
@jaycee1363 Жыл бұрын
@@izenbridge thank you!
@anniegrace6526
@anniegrace6526 2 жыл бұрын
Who prioritizes program increment objectives? IS it Product Owner or Business owner?
@izenbridge
@izenbridge 2 жыл бұрын
Unlike Scrum we do not have one person taking decision on prioritization, its a joint effort. So group of business owners gives Business Value to a Team's PI Objectives and these business values drives the prioritization. The fine grain prioritization of Team backlog is later done by Product Owner.
@anniegrace6526
@anniegrace6526 2 жыл бұрын
@@izenbridge Thank you
@gipsiuful
@gipsiuful 11 ай бұрын
@@izenbridge What if the uncommitted objective has the highest Business Value? Should it be done first in the PI? Or maybe committed objectives should be done first even tough they have lower Business Value?
@izenbridge
@izenbridge 11 ай бұрын
@@gipsiuful If uncommitted objective has higher business value it is expected to be done first, team may discuss how can they bring higher business value one in committed area, where team lack confidence of doing something but it is high in value, that can be in uncommitted but have high value.
SAFe®️ PI Planning: Preparing Program Board - 6 of 7
7:25
iZenBridge Consultancy Pvt Ltd.
Рет қаралды 4,9 М.
SAFe® PI Planning : Program Backlog Readiness - 1 of 7
13:53
iZenBridge Consultancy Pvt Ltd.
Рет қаралды 24 М.
Inside Out 2: Who is the strongest? Joy vs Envy vs Anger #shorts #animation
00:22
Опасность фирменной зарядки Apple
00:57
SuperCrastan
Рет қаралды 9 МЛН
Roles & Responsibilities of a SAFe® Product Owner (SAFe PO)
19:23
iZenBridge Consultancy Pvt Ltd.
Рет қаралды 9 М.
SAFe®️ PI Planning: Roles and Responsibilities - 7 of 7
16:13
iZenBridge Consultancy Pvt Ltd.
Рет қаралды 7 М.
06 pi planning breakouts
12:45
Steve Adolph
Рет қаралды 21 М.
Weighted Shortest Job First (WSJF) in SAFe® - iZenBridge
23:23
iZenBridge Consultancy Pvt Ltd.
Рет қаралды 15 М.
How to write good PI Objectives
29:53
AGILIZER-ACADEMY
Рет қаралды 1,5 М.
PI Planning in SAFe
9:42
Daniel Gilio
Рет қаралды 89 М.
What is Agile?
11:56
Mark Shead
Рет қаралды 2,9 МЛН