SRP Tools - Sozhinganallur Metro Work ! Corridor 3 ! Madhavaram - Siruseri Sipcot

  Рет қаралды 6,244

Nambi Valavan

Nambi Valavan

4 ай бұрын

SRP Tools - Sozhinganallur metro work shared in this video.
This stretch is part of Chennai Metro Phase 2 Corridor 3 of Madhavaram Milk Colony - Siruseri Sipcot. It is elevated section. Contractor : L&T.
Nehru nagar, Kandanchavadi, Perungudi, Thoraipakkam, Mettukuppam, PTC Colony, Okkiyampet, Karapakkam, Okkiyam Thoraipakkam & Sozhinganallur are the metro stations will be constructed in this stretch.
SRP Tools to Kandanchavadi work progressing at slow speed. Kandanchavadi to Sozhinganallur work is progressing at decent speed.

Пікірлер: 44
@shrisharma4904
@shrisharma4904 4 ай бұрын
Yesterday I have travel to Madhvaram to Kilambakkam bus stand i reach in 1 hours 5 mins just 40 rs ticket with Brand new BS6 yellow colour bus vera level speed ❤❤❤❤
@pg4832
@pg4832 4 ай бұрын
Metro Work Update Vera Level Capture
@NambiValavan
@NambiValavan 4 ай бұрын
Thanks
@suryabala_005
@suryabala_005 2 ай бұрын
சகோ, இத்தகவலை தமிழ்நாடு அரசிடம் தெரிவியுங்கள் 👇👇👇 சோழிங்கநல்லூர் பேருந்து நிலையம் மற்றும் இரயில் நிலையம் 1) சோழிங்கநல்லூரில் (சாலை சந்திப்பிற்கு அருகில்) பேருந்து நிலையம், பணிமனை மற்றும் இரயில் நிலையம் அமைக்க வேண்டும் 2) புதிய இரயில் பாதை அமைக்க வேண்டும் தாம்பரம் முதல் சோழிங்கநல்லூர் வரை வழி: கிழக்கு தாம்பரம் - சேலையூர் - இராஜகீழ்ப்பாக்கம் - கௌரிவாக்கம் - செம்பாக்கம் - மேடவாக்கம் - ஜல்லடியம்பேட்டை - எல்காட் செஸ் (ELCOT SEZ) (அக்கரை, கிழக்கு கடற்கரை சாலை நோக்கி)
@vijayadurailakshmanan
@vijayadurailakshmanan 4 ай бұрын
We god coverage. Believe your work and updates are far better than cmrl. The stretch from Sholinganallur to Spicot has been stopped since 6 months. No work any update from cmrl.
@NambiValavan
@NambiValavan 4 ай бұрын
Thanks
@karagis75
@karagis75 4 ай бұрын
Excellent as always
@NambiValavan
@NambiValavan 4 ай бұрын
Thanks
@saran.seenivasan
@saran.seenivasan 4 ай бұрын
Bro thuraipakkam and Sholinganallur junction la flyover epdi nu brief ah explain panunga bro..Adhoda uses and epdi andha flyover oda map and construction irukum andha rendu places la.
@NambiValavan
@NambiValavan 4 ай бұрын
Will try
@Karalmarks_Pvm
@Karalmarks_Pvm 4 ай бұрын
Good work
@NambiValavan
@NambiValavan 4 ай бұрын
Thanks
@shankarsankar364
@shankarsankar364 4 ай бұрын
Bro note my comment ✋ indha U gliders lam strongahnadha bro adhellam thanguma
@NambiValavan
@NambiValavan 4 ай бұрын
Yes
@sudarsan2622
@sudarsan2622 4 ай бұрын
Nice capture bro 🤩🎉❤😊
@NambiValavan
@NambiValavan 4 ай бұрын
Thanks
@mohanmurali5310
@mohanmurali5310 4 ай бұрын
Could you please give us map update on where there are new bridges - integrated grade coming along with metro pillars in total phase 2 map.
@NambiValavan
@NambiValavan 4 ай бұрын
Will try
@Fansofcrafting
@Fansofcrafting 4 ай бұрын
❤ nice
@NambiValavan
@NambiValavan 4 ай бұрын
Thanks
@heisenberg-145
@heisenberg-145 4 ай бұрын
👏🏻👏🏻
@user-uw1hq6dr4b
@user-uw1hq6dr4b 4 ай бұрын
Bro please update bus stop names bro after okkiyampet stop, tcs stop ila.. TCS stop name changed to KCG COLLEGE stop long ago bro.. infact tcs karapakkam shut down pantanga
@NambiValavan
@NambiValavan 4 ай бұрын
Noted
@TheFiretiger20
@TheFiretiger20 4 ай бұрын
can you explain further about u grider why and how they placed 30m long .. it looks like normal bridge to me so want to know what makes it spwcial
@NambiValavan
@NambiValavan 4 ай бұрын
I think in metro viaduct construction it is not easy to transport such long girder . So special fabricated trailer with 12 axles has been used for this girder launch. Longest U girder erection at a height of 20 meters is challenging. Mainly this kind of long girder launch will be useful to speed up the viaduct construction .
@Sanjeevkumar-lx4ni
@Sanjeevkumar-lx4ni 4 ай бұрын
Let's see the work condition in march 2026
@vigneshkuppusamy8643
@vigneshkuppusamy8643 4 ай бұрын
Tidel park u turn flyover enna stage la iruku bro
@NambiValavan
@NambiValavan 4 ай бұрын
Major portion of the work completed. Finishing touch work need to be complete. Due to election code of conduct it might be opened to traffic very soon without any inauguration i guess
@viswanathanc.v4576
@viswanathanc.v4576 4 ай бұрын
The longest girder yet to be placed, I think. Please checkup.
@NambiValavan
@NambiValavan 4 ай бұрын
www.thehindu.com/news/cities/chennai/chennai-metro-rail-launches-a-30-metre-long-u-girder-at-omr/article67728026.ece
@elanchezhiyans2042
@elanchezhiyans2042 4 ай бұрын
Poonamalle metro depot please upload
@NambiValavan
@NambiValavan 4 ай бұрын
Will try
@shobharani1670
@shobharani1670 4 ай бұрын
S bro
@mbala8148
@mbala8148 4 ай бұрын
MMBT Metro progress podunga bro
@NambiValavan
@NambiValavan 4 ай бұрын
Will try
@gemrish6774
@gemrish6774 4 ай бұрын
Avoid reflection.
@NambiValavan
@NambiValavan 4 ай бұрын
Noted
@gokulsundar2096
@gokulsundar2096 4 ай бұрын
Why metro work not started after sholinganallur.
@vahin.r516
@vahin.r516 4 ай бұрын
Existing contractor terminated. Now new contractor assigned.
@NambiValavan
@NambiValavan 4 ай бұрын
Due to sub contractor/ agency problem it was delayed and they ( RVNL ) terminate their contract. Now new firm has been identified, they will start the metro work soon in this stretch
@karagis75
@karagis75 4 ай бұрын
Does it mean shollingnallur to Tiruvanmuyur will be opened before Siruseri? From which. Depot train will come...
@NambiValavan
@NambiValavan 4 ай бұрын
@@karagis75 No. Small Metro depot will be constructed at Siruseri Sipcot. So without completion of Siruseri Sipcot - Sozhinganallur section metro trains can't be operate in OMR road i guess
@manikavel2264
@manikavel2264 Ай бұрын
ரயில்.செல்லும்.தூண்கள்.மிகவும்.மெலிந்து.காணப்படுகிறது.பெங்களூர்மாநரகத்தில்..தூண்கள்.நல்ல.தொலை.நோக்கு‌பார்வையோடுமிக.பிரமாண்டமாய்.திருமலைநாயக்கர்மகால்தூண்கள்சிறப்பாக.அமைக்கப்பட்டுள்ளது.சங்கிமைனாரட்டி.அரசு.தமிழ்நாட்டை.வஞ்சிக்கிறது.காந்தியை.கொன்றகொள்ளை.கூட்டம்.விரைவில்.சமாதியாக.போகிறது.அண்ணல்மீது.சத்தியம்.காவி.கொலைகாரகூட்டத்ததை.தமிழக.மண்ணில.காலூன்ற.விடமாட்டோம்
Iron Chin ✅ Isaih made this look too easy
00:13
Power Slap
Рет қаралды 29 МЛН
Русалка
01:00
История одного вокалиста
Рет қаралды 7 МЛН
New L Shape Flyover ! Under Construction ! Madhya kailash ! Adyar
6:50
Velachery - St Thomas Mount MRTS Work ! Track Work Started
11:03
Nambi Valavan
Рет қаралды 16 М.
Perungalathur Flyover Work ! Nearing Completion ! GST Road Portion
8:27
Iron Chin ✅ Isaih made this look too easy
00:13
Power Slap
Рет қаралды 29 МЛН