The #Morogoro - Makutupora section has eight passenger stations (Mkata, Kilosa, Kidete, Gulwe, Igandu, Dodoma, Bahi and Makutopora) and six freight terminals. The section is complete and operational up to Dodoma.
The section is being build by the consortium that did phase 1 dar -moro.
Financing
Tanzania’s Ministry of Finance signed a facility agreement with Standard Chartered Bank (acting as Global Coordinator, Bookrunner and mandated Lead Arranger) for a US$ 1.46bn long-term loan to fund the construction of the SGR project from Dar es Salaam to Makutupora (Lot 1 & 2):
• $900m ECA-backed loan
• $200m DFI tranche from the Development Bank of Southern Africa (DBSA), the Trade and Development Bank (TDB) and the African Export-Import Bank (Afreximbank)
• $360m commercial loan
Participating ECAs include EKN (Sweden), CESCE (Spain), OEKB (Austria), SACE (Italy), SERV (Switzerland) and EKF (Denmark).
Project Consultant
Joint Venture of Korea Railroad Corporation, Cheil Engineering, Dong Myeong Engineering Consultants & Architecture, Unitec Civil Consultants, Multi-Tech Consult, SSF Ingenieure, D’Appolonia, Balaji Railroad Systems.
The consultant is responsible for design review, construction supervision and project management.