Variation & Claim | Are they same or different ? | Interview Question

  Рет қаралды 18,038

Quantity Surveying Studio

Quantity Surveying Studio

Күн бұрын

Пікірлер: 60
@johnclayden1670
@johnclayden1670 3 жыл бұрын
Good and clear. If I might add a further thought, I'd say that where the Employer has failed to issue a VO or rejected a legitimate request from the Contractor for a formal VO, that rejected request becomes a claim.
@QuantitySurveyingStudio
@QuantitySurveyingStudio 3 жыл бұрын
Thanks for the add in Sir.
@johnclayden1670
@johnclayden1670 3 жыл бұрын
@@QuantitySurveyingStudio My pleasure - and no need for the 'Sir'! And keep up the good work.
@QuantitySurveyingStudio
@QuantitySurveyingStudio 3 жыл бұрын
@@johnclayden1670 Thanks John. Fortunate to get knowledge from you. Have started following you in Linkedin.
@MrWasim148
@MrWasim148 Жыл бұрын
Explained in a Crystal clear way
@QuantitySurveyingStudio
@QuantitySurveyingStudio Жыл бұрын
Thanks
@sajajabeer
@sajajabeer Жыл бұрын
Your videos are simple and clear. thank you
@QuantitySurveyingStudio
@QuantitySurveyingStudio Жыл бұрын
Thanks
@mohamedrifkan4310
@mohamedrifkan4310 2 жыл бұрын
Hi sir I’m looking your video’s all are very useful for me and make many videos to improve our knowledge. Thank you 🙏 all
@QuantitySurveyingStudio
@QuantitySurveyingStudio 2 жыл бұрын
Thanks for the positive feedback !!!
@mohammadumarfarooq675
@mohammadumarfarooq675 2 жыл бұрын
Thanks for the clear explanation on the variation vs claims.However hereby I would like to request you please explain merits & demerits of lumpsum contract for Contractor comparatively to remeasurable contact.
@MrJuzail
@MrJuzail Жыл бұрын
Thanks, Good explanation
@QuantitySurveyingStudio
@QuantitySurveyingStudio Жыл бұрын
Glad it was helpful!
@159357982
@159357982 2 жыл бұрын
Your videos are simple and clear.Keep posting such useful videos 👌
@QuantitySurveyingStudio
@QuantitySurveyingStudio 2 жыл бұрын
Thanks a lot
@Boss-wd4hj
@Boss-wd4hj 2 жыл бұрын
Thank you Sir for clear explanation
@QuantitySurveyingStudio
@QuantitySurveyingStudio 2 жыл бұрын
You are welcome
@saddhaS
@saddhaS Жыл бұрын
Good one, simple
@QuantitySurveyingStudio
@QuantitySurveyingStudio Жыл бұрын
Glad you liked it
@oRaNgE-ty3fb
@oRaNgE-ty3fb 3 жыл бұрын
cleared in a simple way.
@QuantitySurveyingStudio
@QuantitySurveyingStudio 3 жыл бұрын
Thanks a lot !!
@wahiddawar7113
@wahiddawar7113 2 жыл бұрын
Very useful 👍 appreciate
@QuantitySurveyingStudio
@QuantitySurveyingStudio 2 жыл бұрын
Thanks a lot
@irzathmohamed3151
@irzathmohamed3151 Жыл бұрын
Best video bro❤
@QuantitySurveyingStudio
@QuantitySurveyingStudio Жыл бұрын
Thank you so much 😀
@sabirmazari8761
@sabirmazari8761 Жыл бұрын
Good lecture Sir
@QuantitySurveyingStudio
@QuantitySurveyingStudio Жыл бұрын
Keep watching
@selamawitamanuel73
@selamawitamanuel73 8 ай бұрын
Clear 👍👍
@QuantitySurveyingStudio
@QuantitySurveyingStudio 8 ай бұрын
Thanks
@bayan6325
@bayan6325 2 жыл бұрын
Amazing channel 👏 👌
@QuantitySurveyingStudio
@QuantitySurveyingStudio 2 жыл бұрын
Thanks a lot !!
@okaygo6196
@okaygo6196 2 жыл бұрын
Good and clear informative. Please include delay analysis method
@QuantitySurveyingStudio
@QuantitySurveyingStudio 2 жыл бұрын
Have explained it in another video on the topic EOT. You can go through the same.
@rajvlogs3926
@rajvlogs3926 2 жыл бұрын
Clearly understand thank you
@QuantitySurveyingStudio
@QuantitySurveyingStudio 2 жыл бұрын
You are welcome !!
@johnsonjoseph3377
@johnsonjoseph3377 2 жыл бұрын
Nice presentation
@QuantitySurveyingStudio
@QuantitySurveyingStudio 2 жыл бұрын
Thanks a lot.
@alvinsihombing18
@alvinsihombing18 2 жыл бұрын
Thank you for sharing, sir. Anyway, I would like to ask a question about Variation and Claim (EOT and/or cost). I guess any variations or changes to the Works usually impacts the original Time for Completion and/or cost. Therefore, in case there's a variation or changes to the Works and to secure the Contractor's entitlement to the Contract and applicable laws, normally the Contractor shall submit 1 (one) formal notice [only for variation] or 2 (two) notices [for variation and in further EOT+cost claim for such variation]? Thank you.
@QuantitySurveyingStudio
@QuantitySurveyingStudio 2 жыл бұрын
The notice for variation can include eot also.
@gianluigimarudut
@gianluigimarudut 2 ай бұрын
​@@QuantitySurveyingStudio So, if the Contractor have VALID variations and the Engineer/Employer acknowledges it, the Contractor does not need to submit Claim Notices?
@zulqarnainsatti6417
@zulqarnainsatti6417 2 жыл бұрын
Thanks for video. My question on which I need your insight is that if BOQ quantities differs for excavation and backfill works differ a lot and Contractor didn’t notice at the time of tendering but when contract awarded and work on site started so contractor mer with this unforeseen huge increase in quantity due to cut and fill. So now contractor is submitting his quantities based on real work executed let’s say 2 million m3 and BOQ quantities or contract quantities was 1 million m3 so what would the claim for this case. Thanks in advance
@QuantitySurveyingStudio
@QuantitySurveyingStudio 2 жыл бұрын
It will be a variation.
@alvinsihombing18
@alvinsihombing18 2 ай бұрын
@zulqarnainsatti6417: In brief, it will be variations (additional works/increased quantities).
@teshanrathnayake6122
@teshanrathnayake6122 3 ай бұрын
❤Best
@QuantitySurveyingStudio
@QuantitySurveyingStudio 15 күн бұрын
Thanks
@shyammohandas6293
@shyammohandas6293 2 жыл бұрын
If its an additional scope of works such as construction of an ancillary building to the adjacent plot,will it be considered as a variation or claim?
@QuantitySurveyingStudio
@QuantitySurveyingStudio 2 жыл бұрын
It will be a Variation.
@mohamedzafar9340
@mohamedzafar9340 2 жыл бұрын
Does Additional work and claim are same? Because the term“Claim” we used for all the payment request purposes
@QuantitySurveyingStudio
@QuantitySurveyingStudio 2 жыл бұрын
Additional works means variation from original scope.
@knowledgeistospread1934
@knowledgeistospread1934 3 жыл бұрын
why you dont post any more jobs in your linked in job page?
@QuantitySurveyingStudio
@QuantitySurveyingStudio 3 жыл бұрын
Was caught up with few works. Will start putting soon.
@sameeraummer5112
@sameeraummer5112 2 жыл бұрын
Any format for submission
@QuantitySurveyingStudio
@QuantitySurveyingStudio 2 жыл бұрын
Depends on companies and clients.
@gianluigimarudut
@gianluigimarudut 2 ай бұрын
@sameeraummer5112: Follow your Company's standard templates. If needed, you can also adopt and modify templates from your previous companies or other sources.
@mohamedhaneefaashrafali
@mohamedhaneefaashrafali 3 жыл бұрын
What about damage items by others…
@QuantitySurveyingStudio
@QuantitySurveyingStudio 3 жыл бұрын
Since it is an unexpected event it can be classified as claim
@knowledgeistospread1934
@knowledgeistospread1934 3 жыл бұрын
can you do a video about cost report please
@QuantitySurveyingStudio
@QuantitySurveyingStudio 3 жыл бұрын
Sure
@haripriya2495
@haripriya2495 9 ай бұрын
Need software
@QuantitySurveyingStudio
@QuantitySurveyingStudio 8 ай бұрын
Which ?
Quantity Surveying | Pre Contract vs Post Contract | Consultant vs Contractor
20:48
Quantity Surveying Studio
Рет қаралды 19 М.
إخفاء الطعام سرًا تحت الطاولة للتناول لاحقًا 😏🍽️
00:28
حرف إبداعية للمنزل في 5 دقائق
Рет қаралды 82 МЛН
Officer Rabbit is so bad. He made Luffy deaf. #funny #supersiblings #comedy
00:18
Funny superhero siblings
Рет қаралды 19 МЛН
Good teacher wows kids with practical examples #shorts
00:32
I migliori trucchetti di Fabiosa
Рет қаралды 13 МЛН
5 Skills Every Quantity Surveyor Needs
4:03
Metroun Quantity Surveying
Рет қаралды 11 М.
Cost Plan Preparation | RIBA Stages | Cost Estimation Methods
13:40
Quantity Surveying Studio
Рет қаралды 13 М.
Variation & Claim | Are they same or different ? | Interview Question #commercial #quantitysurveyor
25:39
QsClub - Quantity Surveying Practice
Рет қаралды 2,6 М.
24 Quantity Surveying Terms You Need To Know
5:12
Metroun Quantity Surveying
Рет қаралды 27 М.
Quantity surveying Interview questions - Variation #quantitysurvey #rics #contract
31:03
Midhun Suvarnan- Quantity Surveying world
Рет қаралды 1,7 М.
How To Develop Your Quantity Surveying Career - The Next Level
13:44
Cost Engineering Professional
Рет қаралды 15 М.
Variations & Claims, Misconceptions Part 1-3
40:46
CLAC Programme
Рет қаралды 13 М.
All You Need To Know About Lump Sum Contract In Construction
6:46
Cost Engineering Professional
Рет қаралды 15 М.
Variation Orders and EOT
3:58
Planning Engineer FZE.
Рет қаралды 6 М.
إخفاء الطعام سرًا تحت الطاولة للتناول لاحقًا 😏🍽️
00:28
حرف إبداعية للمنزل في 5 دقائق
Рет қаралды 82 МЛН