The joint beach nourishment between the City of Deerfield Beach and the Town of Hillsboro Beach will place approximately 233,000 cubic yards of beach-compatible sand onto the southern beach. The project will utilize a 30’’ cutterhead suction dredge located at the Boca Raton Inlet ebb shoal.
The dredge will first construct the South Boca Raton Beach Nourishment Project prior to extending the pipeline approximately 17,000 feet south into the Town of Hillsboro Beach. The South Boca Raton project will also place approximately 200,000 cubic yards of sand. The South Boca Raton project is anticipated to last approximately 3-4 four weeks and conclude by the end of March. Once the pipeline is extended, the Deerfield/Hillsboro Beach portion is anticipated to last approximately 3-4 weeks and be concluded by the end of April.
For further more questions/Information, visit: