# 31 MS Project 2019 ● Tasks Links Relationships ● Dependencies ● PMP or CAPM

  Рет қаралды 6,942

Vision 6D : Ms Project / AI Project Management /AI

Vision 6D : Ms Project / AI Project Management /AI

Күн бұрын

Пікірлер: 22
@mohieali7317
@mohieali7317 3 жыл бұрын
Tasks links relationship is bit complicated but your demo made it so simple well done !!!!!! thank you .... !!!
@vision6D
@vision6D 3 жыл бұрын
Glad you liked it! Good explanations make things simple to share. Greetings from Geneva.
@davidwaller3449
@davidwaller3449 4 жыл бұрын
Excellent example. Very clear and made what might have been a difficult concept very easy to understand. Well done!!
@vision6D
@vision6D 4 жыл бұрын
Many thanks! It's not always easy to find the right example, to make it simple enough. Have a great day.
@margaretroche3544
@margaretroche3544 3 жыл бұрын
Thumbs up to you. Easy to follow bitesize pieces.
@vision6D
@vision6D 3 жыл бұрын
Thank you kindly! I wish I would have had such a video when I learned about it. Greetings from Geneva.
@salk2555
@salk2555 3 жыл бұрын
Thanks learning that was freaking me out but your video made it easy
@vision6D
@vision6D 3 жыл бұрын
You're welcome! This topic is a tough one till you find the right example. Have a great day.
@jedzheng
@jedzheng 2 жыл бұрын
Thanks for this but a bit confused about sf example, logically the dinner will only start after the completion of the dinner prep, it will be FS instead of SF. If using sf, it will become the dinner will not finish until the prep start, or the dinner can finish after the prep start, either of above two doesn’t make sense.
@vision6D
@vision6D 2 жыл бұрын
Thank you for your comment. There are always several ways to do a planning and I thank you for sharing yours. Have a great day.
@suryatejamadala9888
@suryatejamadala9888 2 жыл бұрын
Firstly, I thank you for presenting us a scheduling demo. But I have a doubt that "is it a good practice to link the relationship between the task dependent activities and WBS?". If yes, could you please share the justification on this issue. For example, from the demo you explained, the task dependent activity ID 10 is linked with WBS ID 14 and WBS ID 11 is linked with WBS 14. Here I didn't understand why we need to link the relationship between the task dependent activities and WBS, as well as WBS with WBS. In my opinion, if I am not wrong, the relationship should be only between activities (task dependent or milestones) but not with WBS. Could you please explain me more? Thanks for your time considering.
@vision6D
@vision6D 2 жыл бұрын
Hello, Thank you for your comment. I'm not sure to get it. In this module I do not use WBS, so could you precise a bit more, by may be giving me the minute of the video?
@suryatejamadala9888
@suryatejamadala9888 2 жыл бұрын
@@vision6D Hi, thanks for responding. We have the rows WBS 1 - Your Top Event (say WBS Level 1) 2 - Welcome cock tile preparation (say WBS Level 2) 7 - Dinner Preparation (say WBS Level 2) 10 - Welcome cock tile (say WBS Level 2) 14 - Dinner (say WBS Level 2) Activities 6 - Drinks Preparation (under the row 2 - WBS Level 2) 12 - Offer drinks (under the row 11 - WBS Level 2) 15 - Serve first plate (under the row 14 - WBS Level 2) Relationships you assigned at 8:45 - ID 14 has a predecessor with ID 11, but why not to ID 12 at 9:40 - ID 10 has a predecessor with ID 14, but why not to ID 15 at 11:45 - ID 6 has a predecessor with ID 11, but why not to ID 12 As mentioned in the previous comment, is it a good practice to link the task dependent activity (6, 12, 15) with WBS (11, 14)? If there is any authorized publication saying we can kink the activities with WBS, could you share those journals or any authorized institute weblinks. In my opinion, according to PMBOK, chapter 6.3 - "Sequence Activities is the process of identifying and documenting relationships among the project activities". If I am wrong, I request you to correct me. Thank you!
@vision6D
@vision6D 2 жыл бұрын
@@suryatejamadala9888 I understand your point. Take those examples as what they are; simples examples of the different kinds of relations you can have between different tasks. Avoid mixing up with WBS. Have a great day.
@suryatejamadala9888
@suryatejamadala9888 2 жыл бұрын
@@vision6D Ok, I agree with your explanation. Thank you very much!
@vishwanathhegde178
@vishwanathhegde178 5 жыл бұрын
I found the Finish to Start a bit hard to understand. Guess it might just be me. Thanks for an excellent video!
@vision6D
@vision6D 5 жыл бұрын
Thank you for your comment. FS relation is the default and most common one found with MS Project. Have a great day.
@gregory35665
@gregory35665 2 жыл бұрын
Please provide link to download relevant mmp file for this tutorial
#32 MS Project 2019 ● Learn to use Task Path to find predecessors in Complex Projects ● Simple
5:21
Vision 6D : Ms Project / AI Project Management /AI
Рет қаралды 7 М.
#2.1 MS Project 2019 ● Team Planner ● Tasks Attribution
17:26
Vision 6D : Ms Project / AI Project Management /AI
Рет қаралды 26 М.
# 33 MS Project 2019 ● Split Tasks ● Simple
8:16
Vision 6D : Ms Project / AI Project Management /AI
Рет қаралды 13 М.
# 21 MS Project ● Margins / Slacks ● Successful Projects  ● Float ● PMP or CAPM
17:23
Vision 6D : Ms Project / AI Project Management /AI
Рет қаралды 8 М.
# 50 MS Project 2019 ● Learn to build phases in projects ● Advanced  ● PMP or CAPM
24:45
Vision 6D : Ms Project / AI Project Management /AI
Рет қаралды 4,5 М.
# 22 MS Project 2016 ● Add a Lag Between Tasks ● Easy  ● PMP  ● CAPM
7:07
Vision 6D : Ms Project / AI Project Management /AI
Рет қаралды 10 М.
# 15 MS Project 2016 ● Critical  Path ● Howto
13:59
Vision 6D : Ms Project / AI Project Management /AI
Рет қаралды 97 М.
MS Project 2019 ● #6.2  Learn to Use the Timeline  ●  Simple
8:26
Vision 6D : Ms Project / AI Project Management /AI
Рет қаралды 26 М.
# 1 MS Project 2019 ● Basics in 20 Minutes ● Easy
29:37
Vision 6D : Ms Project / AI Project Management /AI
Рет қаралды 1,1 МЛН
6 ChatGPT Prompts for Project Managers | 5 Minute Friday
9:01
Construction Brothers
Рет қаралды 4,2 М.
# 13 MS Project 2016 ● Solve Overallocation ● Level Resources
10:34
Vision 6D : Ms Project / AI Project Management /AI
Рет қаралды 65 М.