Chandoo, thank you. I've followed you for a long time. LOTS of great insights. However, for those of us who actually practice project management, there are a few items missing in many Excel Gantts. Tasks often need to include one of the following: Finish-to-Start (FS): Task A must be complete before Task B begins. Finish-to-Finish (FF): Task A must be complete before Task B can be complete. Start-to-Start (SS): Task A must have started before Task B can start. Start-to-Finish (SF): Task A must have started before Task B can finish
@chandoo_5 ай бұрын
Great points. Task dependency and hierarchy are tricky to implement with Excel alone. That is why I recommend using a Project Management software like MS Project for such complex needs. That said, I have a video that shows how to do critical path analysis. Do check it here - kzbin.info/www/bejne/np3XoXuqr8ZjeLc
@shanmugavelu953 Жыл бұрын
Hi Chandoo, Thanks for your video. I am good in excel VBA and have done many projects in the past. After coming across your video, I realised excel has got so many builtin functionality and does not need complex VBA to acheive the same result. Good work.
@miltontyotamkwaipo50343 жыл бұрын
Your tutorial is very simple with very clear guidance and instructions. Very much appreciated.
@chandoo_3 жыл бұрын
Thanks Milton.
@xbizuk14 жыл бұрын
Came in at the right time. Loved variety of conditional formatting
@chandoo_4 жыл бұрын
Thanks. Conditional Formatting can do so many wonders.
@rubenpereztorres4 Жыл бұрын
Mr. Chandoo, you are really Awsome..!!! Thanks for this help, I've been looking for this explanation and finally is here..!
@MPeixe11074 жыл бұрын
Hello from Brazil! Your videos are just great, they help me a lot.
@chandoo_4 жыл бұрын
Glad you like them!
@jansenstewart3 жыл бұрын
love the median rule for highlighting cell, very smart and simple calc.
@chandoo_3 жыл бұрын
One of my fav formula tricks too 😀
@MrAnandselva3 жыл бұрын
Thank you very much for the details. This makes my job a lot easier
@chandoo_3 жыл бұрын
Glad to hear that. All the best.
@anv.4614 Жыл бұрын
Thank you so much Chandoo. very good technique.
@vijaychauhan54474 жыл бұрын
Hello Sir I saw your all video. Your all video are very helpful. Thanks
@shoaibrehman99884 жыл бұрын
I really like date part in pivot table, overall lot of new things for learning, your all videos are very fruitful. New setup looks goods. Thanks Take Care Shoaib Rehman
@chandoo_4 жыл бұрын
Glad you like them!
@iliveinazoofoo Жыл бұрын
At 15:13 you are fixing the highlighted empty cells by changing the formula. What is the formula? I cannot see and it is not working. I was using " ", Is that correct? You said not equal empty spaces?
@rachelth16 ай бұрын
@chandoo I love the chart! It works brilliantly....until I tried to incorporate repeating activities (first example is 'Rachel holiday') and for that I would like one line item in the gantt chart with the actual holiday periods highlighted along the timeline - how can we get this view of exact dates and not just the whole time highlighted as a start and end from all of the line items for 'Rachel holiday'?
@tagamag Жыл бұрын
By definition, Gantt needs to do much more than just tabulation of work. Take this example. Simple case: There is project task A, task B, and task C. A requires 5 days to complete, B needs 3 days, and C needs 10 days. A and C are independent tasks, while B can be done only when both A and C are complete. Resources P1 and P2 are working on the project. P1 works 0.5 days sometimes, and P2 always works full time. I want to distribute the work so that I can make optimum utilisation of their time and skills. In Gantt: I can put P1 for 10 days on A, so that A gets completed in 5 days (i.e. 10 calendar days, 0.5 working day each). Parallel, I can put P2 on task C. So, C and A both get completed in 10 calendar days = 15 workdays. If I have 6 or more calendar days in hand, I can put P1 on task B, and assign something else to P2, or vice versa. No Excel sheet allows these variations, unless we enter everything manually with arithmetic of work per day per person. These variations are critical for managing any practical work. Even if I am managing my personal work, I should be able to plan a portion of task every day and do multiple tasks in parallel, subject to their interdependency and priorities. Sadly, there is no alternative to Microsoft Project. If anyone has a freeware solution, please reply to this comment.
@jhonalvarez56204 жыл бұрын
Thank you very much for the video. It makes my job a lot easier
@SaiNiveta Жыл бұрын
Wonderful tips and techniques! Thanks a lot!
@voodmann Жыл бұрын
i really like that the date columns in the gantt columns dynamically expand and contract depending on the slice of the data set. do you know of a way to do this with a regular table using the default filters?
@shyamsubran3 жыл бұрын
Hai! I am learning a lot from your uploads. Sessions are very descriptive and informative. Started using skills learnt from your videos and getting results. Fan of yours! Thank you and keep posting good sessions.
@chandoo_3 жыл бұрын
Thank you Sh...
@princeharryandmeghanmarkle33143 жыл бұрын
Learned so much from this, thank you
@jessc20646 ай бұрын
Can the gantt chart show a baseline, forecast and actual durations? Can it also show milestones?
@harkrishanchinnarasu11 ай бұрын
great work .thanks for your video . is it possible to add time on gantt chart
@gururaj267 Жыл бұрын
Super one for all, please tell us how to add today's line in Excel also. Thank you
@sharmacreatives2553 жыл бұрын
Simply superb sir 🙂
@shoaibafridi61855 ай бұрын
how can we look for actual work done vs planned in the same gant chart I mean how to check for target vs achieved
@AndyLoweUTube4 жыл бұрын
Nice video. There are some nice ideas in here and very clearly explained and demonstrated.
@chandoo_4 жыл бұрын
Glad you liked it!
@agrinnovation2 жыл бұрын
this is very useful. wondering if you have similar video to create Gantt chart by quarters instead of days..
@ROOOPSS Жыл бұрын
You are a real "Puli" .. I am a mallu.
@wmfexcel4 жыл бұрын
Nice use of MEDIAN. Awesome!
@chandoo_4 жыл бұрын
Thank you! Cheers!
@rizaldyesteban89342 жыл бұрын
Thanks for the video which I learned, but I have a question, for making a gantt chart, how to do format when 1 activity in 2 or more different duration time?
@mriduyadav8007 Жыл бұрын
hi. I have made a planned vs actual Gantt chart. but it has a problem, every time I add a new activity, I have to copy planned and actual formula in that whole row. Is there any formula or coding in vba so that formula applied by itself in the row looking/searching for planned or actual keyword? Please tell.
@BikashRoy-pz5ti2 жыл бұрын
Really its great and helpful, thanks
@JapjeetS4 жыл бұрын
@chandoo Hello, I got lost at "MIN(data[Start Date])", did you define a start date already in your sheet somewhere?
@chandoo_4 жыл бұрын
We are using Excel tables in this. If you give your table a name, then you can refer to the columns of the table with tablename[column name] notation. That is how I am getting the earliest start date.
@InsideMyWall2 жыл бұрын
I want to prepare a cost forecasting report into a Gantt chart. I have the cost between a duration and i want to allocate the cost monthwise. Kindly make a video on that.
@phaedragunita15 күн бұрын
Sir, is it open for private lessons?
@anglerweekenderrizalzi34192 жыл бұрын
thank for the awesome tutorial.....
@wayneedmondson10654 жыл бұрын
Hi Chandoo.. very nice chart and technique. Thanks for sharing! Thumbs up!!
@chandoo_4 жыл бұрын
Thanks Wayne...
@timplayer13 жыл бұрын
Can you help me? How can i have a milestone light up in this chart? And is it possible to have like a different groups and then a topic and then the activity of the topic? That people can choose the group and topic in the slicer? Thanks in advance!
@alisarfaraz37633 жыл бұрын
How to use median formula for WEEKLY timeline or MONTHLY time line ?
@chandoo_3 жыл бұрын
You can't use MEDIAN for that. You need a range overlap function. Something like this: chandoo.org/wp/date-overlap-formulas/
@alisarfaraz37633 жыл бұрын
@@chandoo_ its not working for smaller durations within the week but i got a work around .. =IF(MEDIAN(WEEKNUM($B24),WEEKNUM($C24),WEEKNUM(J$8))=WEEKNUM(J$8),"R",0)
@xbrito33682 жыл бұрын
Is there a way that 'date order' can be switched off so that rows remain in the order entered?
@darshanapatil29207 ай бұрын
Hello Chandoo, Workday function is returning wrong date, returns excess of 2 days. Pls help.
@riiximbhaanot18182 жыл бұрын
Many thanks DEar Chandoo for insighful video. This really saved my day for a client's project plan. One query- How did you bring slicer on Gantt chart sheet from Pivot table?
@chandoo_2 жыл бұрын
You can make the slicer, cut it (CTRL+X) and paste it anywhere else.
@riiximbhaanot18182 жыл бұрын
@@chandoo_ Great thankyou for being such a wonderful being 😊. Have a great time 🌼
@jhonalvarez56204 жыл бұрын
Once I saw a file in which the cells were compressed and decompressed by means of a character symbol inside a cell, similar to grouping and ungrouping applying schema, with the disadvantage that when applying it, the working field is compressed and is not optimal . I will greatly appreciate your help with this. Greetings from Peru
@chandoo_4 жыл бұрын
Could it be selectable cell technique demoed here - chandoo.org/wp/show-details-on-demand-in-excel/
@joseagundis14 жыл бұрын
All I liked, very well process. Best regards
@chandoo_4 жыл бұрын
Thanks for liking
@irfansadiq84482 жыл бұрын
Thank You. I have one question how did you move/created the module slicer in the plan sheet, whereas the pivot is on another sheet.
@chandoo_2 жыл бұрын
I think I explain it in the video. You can make the slicer, cut it and paste it on the other sheet.
@rrajapur2 жыл бұрын
Hi, learning a lot from you chandoo. I have a problem in a file of mine. When I put the data in pivot, the data is automatically sorted alphabetically, the original order is lost. How to get the same order when I put it in the pivot table.
@wasifabbas81603 жыл бұрын
Hi Your videos are great & beneficial for me specially for learning excel. I am working at this with little amendment as placing date in horizontal as showed in the video. I am trying to dynamic it as date start from minimum date in the start date and go to the end date in the table. Kindly address this issue as i am trying to do it through if condition at start date but as i drag it horizontally, table1 update columns & is not fixing it while if, i drag it vertically, it remain static.
@michibichi22123 жыл бұрын
awesome. thanks for doing this!
@chandoo_3 жыл бұрын
Thanks Michi...
@tahirvlogs11043 жыл бұрын
How to do a Monthly gantt chart? any idea? I don't want to show days/week in that chart and is this possible to make that automated too?
@chandoo_3 жыл бұрын
You can use =EDATE(previous date, 1) to move the date on top by months.
@melaniem.matute2372 жыл бұрын
Hi! Thanks for sharing the knowledge. I have a question regarding the zebra lines, how can I incorporate them at the Gantt without erasing the 'progress' bars?
@beardpower86702 жыл бұрын
Sorry couldn't help myself, I figured I'd answer your question. Click Conditional Formatting → Manage rules → From there move your zebra line rule to the bottom. Hopefully that helps.
@phamquyen0201 Жыл бұрын
Please shoe us how to highlight today?
@hanzreyes28543 жыл бұрын
How to make a gantt chart, that the highlighted cells will affected the date start & date end instead. I.e. I need to highlighted cells or move the gantt chart in order to balance the manpower for the project, and in doing so, I need the date start and date end will follow the gantt chart bar or the highlighted cells, and in addition each cells I need the input number of manpower and sum it at the bottom, in doing so I will know how many manpower need in daily basis for a specific project. Thanks.
@chandoo_3 жыл бұрын
Unfortunately, this is not an easy thing to do with Excel. Please use a Project Management software like MS Project or trello
@hanzreyes28543 жыл бұрын
@@chandoo_ Luckily one of my friend manage to do it, it completed my excel project management life!!!
@GAKTomory3 жыл бұрын
Just getting started, How do I add weekends? I need a full calendar week not just week days?
@chandoo_3 жыл бұрын
Refer to this video where I show another method (with weekends ofcourse) - kzbin.info/www/bejne/fInRqn6La92Nm6s
@vikasanand31703 жыл бұрын
Very informative video, but half work done. Please guide how to track plan vs actual progress in same format. Will be really very helpfull.
@chandoo_3 жыл бұрын
You can add another set of conditional formatting rules and that should work. Visit chandoo.org/wp/category/project-management-2/ for some inspiration and ideas.
@vikasanand31703 жыл бұрын
@@chandoo_ thanks for replying. If possible pls make a video on plan vs actual tracking on gantt chart. It will b helpful for millions of people.
@kaulamatoa4 жыл бұрын
Great video, thank you!!!
@chandoo_4 жыл бұрын
Glad you liked it!
@reshmagola69613 жыл бұрын
This video was really helpful! Would you be able to show us or update the template to roll it up to "quarterly" views?
@chandoo_3 жыл бұрын
Thanks Reshma... Good idea. I will make next-level version of this.
@reshmagola69613 жыл бұрын
@@chandoo_ Thanks so much! I wonder if it could be made for 2021 dates too. :)
@chandoo_3 жыл бұрын
Certainly.
@afrinmahaboob61013 жыл бұрын
Hi I am Afrin, How can I hide the grand total row in the pivot sheet. I have downloaded your template but could not find the solution. could you please tell me?
@chandoo_3 жыл бұрын
Hi Afrin... Select the Pivot Table Go to Design Ribbon Click on "Grand Totals" and off them for rows & columns.
@saisasidharbagavathula8342 жыл бұрын
How to represent delay in activity in Gantt chart
@aslamrangrej27143 жыл бұрын
I have abbreviations of activity. I want to display it in my chart instead of highlighting. Is there any way ?
@chandoo_3 жыл бұрын
You can use formulas to pull the activity abbreviations. As the cells are narrow, you may not be able to show much though.
@VinodNawab4 жыл бұрын
Excellent. Kindly show us a way to create two parameters on top side bar (from Start Date to End Date you showed there in terms of Month / Date) - we want to show working dates and number of hours per day. This way we should plan scheduling, in which we may enter number of working days per week. A provision to input for any other holiday or OFF also.
@chandoo_4 жыл бұрын
You can easily customize the template to add those feature Vinod. Give it a try. You would need workday.intl formula to enable custom working days situation.
@VinodNawab4 жыл бұрын
@@chandoo_ I tried same chart on time frame basis, initially distributed all activities within 24 hrs (planned all to happen in a day, otherwise it was difficult to differentiate 8:00 AM ) but failed.
@VinodNawab4 жыл бұрын
@@chandoo_ we used 11/05/2020 8:00 AM as Start Time / End Time format, so look forward to write function for the task bar, as you wrote =MIN(data[Start Date]) in the above video
@farhadnasir47592 жыл бұрын
Really amazing
@fengxu56253 жыл бұрын
what if the actual is different as plan ? how do it in one view?
@chandoo_3 жыл бұрын
You can see this page for some ideas - chandoo.org/wp/gantt-charts-project-management/
@marlondayday4 жыл бұрын
What version of excel did you use?
@chandoo_4 жыл бұрын
I am using Excel 365 in this video, but you should be able to apply this on Excel 2013 or above...
@pandharinathjoshi65653 жыл бұрын
Very well sir
@chandoo_3 жыл бұрын
Thank you Joshi ji.
@A_Proud_Indian3 жыл бұрын
Microsoft launches MS project, Chandu oh f off, let me build it in excel
@chandoo_3 жыл бұрын
😂🤣
@medicalparasitology34313 жыл бұрын
Good morning sir, I have a project in excel and i need your help. How can I contact you by telegram?
@chandoo_3 жыл бұрын
Thanks MP. I am not taking up any consulting work at the moment. I suggest finding some help thru freelancing websites such as upwork or fiverr.
@imrantpharma3 жыл бұрын
Sir How to make that module window for different sheet Plz guide
@prakashsathyapriya3 жыл бұрын
Excellent
@chandoo_3 жыл бұрын
Thank you so much 😀
@chakra5313 жыл бұрын
please explain the shortcut keys you are suing at each stage. please add it to the captions or modify the video to show the same, without the shortcuts, the whole tutorial is useless to a beginner like me because it cant be reproduced
@chandoo_3 жыл бұрын
Did you somehow miss the word "advanced" in the title? Please watch my begginer Gantt chart tutorial here. kzbin.info/www/bejne/fInRqn6La92Nm6s
@miraclefeliciaadeline61059 ай бұрын
I Like you video
@vijaychauhan54474 жыл бұрын
One time I send you one comment Can you make grocery items stock report.
@chandoo_4 жыл бұрын
Good suggestion Vijay... I will create a template like that and share later. Meanwhile, check this generic tracking template and use it - chandoo.org/wp/create-an-excel-tracker/