This Video shows you how to complete the dead testing sequence. It will guide you though testing a lighting circuit and a ring final test.
C - continuity of CPC
R - Ring Final
I - Insulation resistance
P - Polarity Dead
P - Polarity Live
E - Earth Loop Impedance
R - RCD

Пікірлер: 42
@georgebrassington1244
@georgebrassington1244 2 жыл бұрын
So many oversights on this video. 1 - No Lock off , 2 No supply voltage check with test lamps confirmed working with proving unit. 3 You disconnect main protective conductors to copper pipe work so has not to pick up false readings on R1 + R2 tests via parellel paths. 4 To get a correct R1 + R2 result on the ring main you divide the reading by 4. 5 When doing an R1+R2 test on lighting take a reading from all fittings + switches and record the highest !
@pepperthekobold
@pepperthekobold 6 жыл бұрын
Very helpful, thank you. Just what I needed as a quick refresh before my exam tomorrow.
@ifyougetstucklookitup237
@ifyougetstucklookitup237 Жыл бұрын
excellent summary - thank you
@soniajaynefelton5049
@soniajaynefelton5049 5 жыл бұрын
Surely you check at every point on R1 + R2 test and switch the light switch on and off to prove polarity
@jamesglover650
@jamesglover650 6 жыл бұрын
How did u get those results, the first three tests the main switch was on except for the last one, doing my practical, at college and just noticed it
@petergambling671
@petergambling671 3 жыл бұрын
Excellent thanks you so much
@jackcooper4655
@jackcooper4655 7 жыл бұрын
Thankyou v helpful
@edwardcoe8838
@edwardcoe8838 3 жыл бұрын
what page shows the correct readings for r1+r2?
@petg9473
@petg9473 6 жыл бұрын
Hi mate great video but could you please do one more in depth, demonstrating how youre setting up your megger for each test and explain the purpose of each test phase of cripper. Thanks again.
@jamesoconnor2417
@jamesoconnor2417 Жыл бұрын
Could you do live tests never heard of “CRIPPER” but best video I’ve seen for my am2 not complicated just straight to the point cheers
@9T9times
@9T9times 6 жыл бұрын
Would be great if you'd show the actual meter settings and the readings you get. What you appear to be doing here is just enacting the CRIPPER testing sequence without actually showing much. Sorry if I sound negative, but thanks for the vid. ;)
@leebrown3895
@leebrown3895 6 жыл бұрын
Well done dave please could you let us know what setting the testers are on every test, good luck
@WVRElectricalTraining
@WVRElectricalTraining 6 жыл бұрын
Lee Brown i will do this not a problem. Will upload next couple of weeks. Will keep you posted.
@izuchukwucollins5687
@izuchukwucollins5687 2 жыл бұрын
Helpful, could you still complete the pper ?
@AlexEatonPDPIGaming
@AlexEatonPDPIGaming 6 жыл бұрын
Hi, could you please do a video finishing the sequence with the live tests
@WVRElectricalTraining
@WVRElectricalTraining 6 жыл бұрын
Alex Eaton i will do a live testing Video in the next couole of week. Ill keep you posted.
@CommonInvesting
@CommonInvesting 2 жыл бұрын
For the first test (continuity of cps) do you place ALL cpc's in the connector block? including ring etc?
@caincawkwell8092
@caincawkwell8092 2 жыл бұрын
Remove bonding, everything else can be used via croc. Clips onto earth terminals on DB
@CommonInvesting
@CommonInvesting 2 жыл бұрын
@@caincawkwell8092 perfect! Thanks for clearing that up
@no_short_circuit
@no_short_circuit 6 жыл бұрын
Good stuff. Please can you do the "live" tests in a future video?
@WVRElectricalTraining
@WVRElectricalTraining 6 жыл бұрын
GrumpyGrampa i will do a live testing video in the next couple of weeks.
@Hiccup77
@Hiccup77 7 жыл бұрын
1st test is. continuity of protective conductor (disconnect cpc from met) 2nd test is. continuity of main and supplementary bonding conductors (disconnect cpc from met) 3rd test is. continuity of final rind circuits (no need to disconnect the cpc from the met)
@saidtoubi6751
@saidtoubi6751 6 жыл бұрын
Not done safe isolation!!!
@seandempsey7351
@seandempsey7351 2 жыл бұрын
Point 2) is wrong testing supplementary bonding , the conductors remain connected at the MET or earth bar .also he should of used a crock clip on one of the test leads and clipped onto the earth conductor to insure a good connection and a good reading
@ruaraidhmaccormick4677
@ruaraidhmaccormick4677 Жыл бұрын
And Bulbs grow in gardens 😅 and he forgets to null leads 😂 not bad for an apprentice tho
@Raf-el4pu
@Raf-el4pu 5 жыл бұрын
where are live tests?????
@easyfix5366
@easyfix5366 4 жыл бұрын
Can't see where you are connecting your tester
@yusufrehman2157
@yusufrehman2157 4 жыл бұрын
Good effort, can you please make this video with zooming the camera and showing all wires and tester reading
@Robert-ts2ef
@Robert-ts2ef 3 жыл бұрын
My only negative comment is that you did not specify what readings you got for each test. Why not?
@jackcahill7746
@jackcahill7746 Жыл бұрын
U never made sure the circuits were isolated and checked they were dead
@seandempsey9396
@seandempsey9396 3 жыл бұрын
Nothing like an instructor giving a demonstration with his back to you and you can't see what he is doing, maybe I could do a corce at his college and I could then a job and no one would be any the wiser weather or not I have done it properly
@llVIU
@llVIU 5 жыл бұрын
mate, I can see that you're working live
@pblazi
@pblazi 4 жыл бұрын
This video is a joke. Should've nulled his leads before he started, should've done a safe isolantion before doing anything. He is removing live and cpc conductors while MCB and main isolator is ON and LIVE. Didn't flick the light switch ON and OFF as he was doing his r1r2 at the light circuit. Used a bloody painters ladder. Didn't null the crock clips before doing end to end on ring. IR at 500V he tested between the Live and the entire Netral bar instead of removing the Neutral from the circuit in question, while still having a bulk head with a light still on above the dis board. Don't do what this guy is doing under exam condition. You're bound to fail.
@Tryingtimes007
@Tryingtimes007 4 жыл бұрын
painters ladders 😂 first thing i noticed.
@oldgrunger5
@oldgrunger5 4 жыл бұрын
Might be a great Idea to also confirm polarity before energizing the circuit and operating the switches on the ring final circuit ...just saying ! 😎
@oldgrunger5
@oldgrunger5 4 жыл бұрын
Also Ive always taught to verify continuity of cpc at every point served on the lighting circuit
@zumber2811
@zumber2811 4 жыл бұрын
Pretty sure he is JUST showing how to test it and which conductors to connect/cross-connect.
@brinxmatty1
@brinxmatty1 5 жыл бұрын
Ok but as said show results
@valentinokennedy7672
@valentinokennedy7672 4 жыл бұрын
, please don't use this method for your exam or for your job !!!
@colintatum6872
@colintatum6872 5 жыл бұрын
As clear as mud unless you’ve prior experience. Crap.
@colinhumphryes5664
@colinhumphryes5664 7 ай бұрын
Poor
Live testing
10:58
Paul Lansdowne
Рет қаралды 11 М.
Initial Verification - Testing someone else's crap work
32:55
SparkyNinja
Рет қаралды 272 М.
ВОДА В СОЛО
00:20
⚡️КАН АНДРЕЙ⚡️
Рет қаралды 30 МЛН
Finger Heart - Fancy Refill (Inside Out Animation)
00:30
FASH
Рет қаралды 25 МЛН
Inside Out Babies (Inside Out Animation)
00:21
FASH
Рет қаралды 13 МЛН
Fault finding on a Ring Final Circuit using R1+R2 & R1+RN, the only way to prove polarity AM2 AM2S
19:09
Pure Electrical Training - by Adrian Davey
Рет қаралды 41 М.
2391 THE EXAM! Electrical Inspection and Testing Ep2
33:40
Apprentice 121
Рет қаралды 11 М.
AM2 Common Errors
7:21
Warrington & Vale Royal College Electrical Training
Рет қаралды 15 М.
How to do an EICR start to finish - Electrical Safety Inspection and Test
46:34
Mark The Sparky Allison
Рет қаралды 58 М.
Guide to completing an Insulation Resistance test and test sheet completion
10:10
ВОДА В СОЛО
00:20
⚡️КАН АНДРЕЙ⚡️
Рет қаралды 30 МЛН