The final important step is to demagnetizing a transformer to remove the residual magnetic flux. otherwise they they will be a large inrush currents on the primary side, that could trip the protective relays.
@electronicatutorial4 жыл бұрын
Hipot is a different test than Megger. Hipot measures leakage current and Megger measures insulation resistance.
@shahulexplore3 жыл бұрын
But he did insulation test ; it means device he used is meggar ; I too little confuse ....
@electronicatutorial3 жыл бұрын
@@shahulexplore There are many insulation tests like tan delta, hipot, resitance of insulation, partial discharge etc. Hipot measures current leakage and Megger or insulation resistance measures de resistance of the insulation which is very high os supposed to be very hihg in hte Gigahoms and current leakage in in the mA.
@Tonhu20023 жыл бұрын
Do I need to short circuit the busing terminals of each side together
@ssennonojohnmary4406 Жыл бұрын
Excellent demonstration.
@maazahmad16314 жыл бұрын
Pls can you make this test on digital megger, so we will understand the exact value
@Greystonewet2 жыл бұрын
All right, but what about safety? As it’s a high voltage test you should prepare proper PPE like certified rubber gloves and safety-hook, and buddy system.
@mdanwaralam26534 жыл бұрын
What should be Megger voltage for 11000/415 volt distribution transformer
@sujitkumardash5650 Жыл бұрын
2500 V for HT-E & HT-LT 500 V for LT-E
@goldfish56063 жыл бұрын
Should you not have disconnected all the line and neutral terminals of the transformer?
@drichidominic46453 ай бұрын
Good work
@meksen20004 жыл бұрын
Why is the guard tip of the meter empty?
@Rahul-bp9vl4 жыл бұрын
Please provide link of magger 🙏to purchase
@runbou34852 жыл бұрын
Thanks ticher 👏អគុណ
@nasiruddinhimu50754 жыл бұрын
How many time measure HV-GND , LV-GND , HV-LV....1 minute or 5min....plz details explain
@pancakeface7773 жыл бұрын
what device did you use to shoot the video with?
@veeruppcltarget56429 ай бұрын
very nise I am from India 👌👌
@visakhpradeepedathil21774 жыл бұрын
Why only one phase is checking in primary and secondary. Usually we need yo check between each phase and earth.
@imadewn4 жыл бұрын
Visakh pradeep edathil Look at the winding...if one of the bushing's insulation failed, the transformer is failed. for both primary and secondary.
@visakhpradeepedathil21774 жыл бұрын
@@imadewn thanks bro. @ site i saw people testing between all pahses and earth. Is that ok.
@imadewn4 жыл бұрын
Visakh pradeep edathil no problem, but it waste of time i think haha
@toqeerahmad73783 жыл бұрын
Great Demonstration...
@ridhoalpha4 жыл бұрын
is this in central java? the MV is 3-phase 4-wire?
@imadewn4 жыл бұрын
Ridho yes it is
@razaulkarim67964 жыл бұрын
can u give pdf link of accptable value of resistance
@ardy6804 жыл бұрын
1000 x volt
@electricaltech4u454 жыл бұрын
Nice bro
@mintipatel21833 жыл бұрын
Right but short dtr possigen
@surendrakverma5554 жыл бұрын
Very good
@mirtunjaykumar93493 жыл бұрын
Nice
@salmansheikh8384 жыл бұрын
nice video
@mikeadler4349 ай бұрын
👍👍
@dharampalsingh3262 жыл бұрын
👍👌🙏🙏🙏
@zavidsayed3402 ай бұрын
Aap acchi tarah se video nahin banaya clarity nahin hai aapka video sahi nahin hai