@zahir585 Жыл бұрын
Totally agree with you about the backwards planning/scheduling. Most of the time we this method when we know what the end results should look like then we plan backwards in order to determine FEL..
@PlanAcademy Жыл бұрын
not used very often these days.
@FA333568 Жыл бұрын
I don't use SF relationship, if Task A (even without predecessors) must be finished prior to the start of Task B, which has other driving predecessors, I will put a As late as possible constrain in Task A which is FS linked to Task B. So if the Task B is to move forward or backwards, the Task A will follow accordingly. The benefit is when in future there will be predecessors for Task A, the Task B is still under the sway of the movement of Task A.
@PlanAcademy Жыл бұрын
I'm not aware of anyone that actually does use SF relationships. No one is interested in planning in the backwards direction these days. ;)
@noorulhaq3047 Жыл бұрын
I love watching your explanation of P6 logic. i have troubled regarding resources. Can we define separate Recourses list to each individual project under on EPS?
@PlanAcademy Жыл бұрын
You can of course, but I'm guessing you want resources to be limited/available to certain projects and it doesn't work that way. In P6, ALL resources are Global and available on any project. So you can use the hierarchy in Resource Dictionary to organize your resources by project, but they won't be limited to a project. In theory, you can play with permissions in P6 to limit resources to being available to certain projects, but it's a pain to manage and most people who go that way eventually abandon it for the inflexibility.
@noorulhaq3047 Жыл бұрын
@@PlanAcademy I can use hierarchy option. Thanks a lot
@johnsafi110411 ай бұрын
it is suggested to make an example with relationship Finish to Start,
@umairmohammed5073 Жыл бұрын
Don’t we say in start to finish relationship, Successor activity cannot finish till predecessor activity has started .