Find Loops in Your P6 Schedule and How to Fix Them

  Рет қаралды 23,003

Plan Academy Inc.

Plan Academy Inc.

Күн бұрын

Пікірлер: 25
@PlanAcademy
@PlanAcademy 2 жыл бұрын
Need to learn P6? Check out the best Advanced P6 Training Available online: www.planacademy.com/
@kasriabdelhak3339
@kasriabdelhak3339 4 жыл бұрын
I'm proud of you,thanks for your support to us
@divster1977
@divster1977 3 жыл бұрын
Love the new style of video, Michael
@adeolajide5230
@adeolajide5230 2 жыл бұрын
You're a great teacher. God bless you
@ajinkyakale830
@ajinkyakale830 Жыл бұрын
Thanks a lot, Michael!
@mahansor8295
@mahansor8295 4 жыл бұрын
Thanks Michael
@naveediqbal03
@naveediqbal03 3 жыл бұрын
Thanks a lot. That was quite efficient to track the error!
@mahmoudoulbah7641
@mahmoudoulbah7641 2 жыл бұрын
SO HELPFUL
@roccospena
@roccospena 4 жыл бұрын
Thanks Michael for this helpful explanation... very clear. Muito obrigado👌
@solomondavid288
@solomondavid288 4 жыл бұрын
Thank You!
@colcot50
@colcot50 3 жыл бұрын
I had lots of these today in a schedule I was rebuilding for someone else, the logic was abysmal, no thought into a common approach at all. Good video though, thank you
@Aryanss5743
@Aryanss5743 3 жыл бұрын
Hi Sir. Please make a video on how to make a recovery schedule. Please it will be highly appreciated
@vedantsharma5191
@vedantsharma5191 2 жыл бұрын
can you upload videos related to delay analysis using primavera P6 and the concurrent delay analysis
@MuayThaiSong
@MuayThaiSong 6 ай бұрын
Hi Micheal, how do I extract overlapping / clash activities for example between Construction and Commissioning. There are areas on the Project where Construction cannot work because the Commissioning team are working, and vis Versa.
@PlanAcademy
@PlanAcademy 5 ай бұрын
In these circumstances, it's crucial to ensure that the relationships we establish between activities are accurate. If you believe that certain construction activities cannot commence until commissioning is completed, please add a finish-to-start relationship from commissioning to construction activity.
@danishhasware3762
@danishhasware3762 Ай бұрын
WHY MY SCHEDULE PERCENTAGE & PERFORMANCE PERCENTAGE COMPLETED IS NOT ROLLING IN WBS & AT TOTAL
@Поранагора
@Поранагора 4 жыл бұрын
If I understood right have I install Primavera P6? What version and where I can do it? Thx
@khanstephens4955
@khanstephens4955 9 ай бұрын
I am using P6 2023 and I cant change my start milestone to have a FS relationships with my second activity. How do i fix it?
@PlanAcademy
@PlanAcademy 8 ай бұрын
Yeah - that's newish. A start milestone can't do a F-S relationship anymore. Just use S-S.
@alaanagy5952
@alaanagy5952 4 жыл бұрын
Please can u share way to import activity realationships from excel to P6
@awadasad5357
@awadasad5357 4 жыл бұрын
Hi Could you pls. Guide me how to reduce the no. Of critical activities
@PlanAcademy
@PlanAcademy 4 жыл бұрын
We actually don't want to do this. If we linked up everything properly then, have correct durations, then the critical path is true - we don't mess it. If you think it's incorrect, check your linking and durations.
@mahansor8295
@mahansor8295 4 жыл бұрын
I've got a question, how can we assign a virtual resource to all activity as a weight factor to see the project's s-curve, I mean wee preserve the current resources and cost, just add this virtual resource and see the result without affecting these two types of resources on eachother. Please don't hesitate if you need any further information, many thanks.
@PlanAcademy
@PlanAcademy 5 ай бұрын
You can define a resource named "Virtual Resource" and assign it to all activities. The resource type can be either Labor or Non-Labor; just ensure that the standard rate is set to zero. After assigning it to all activities, add your specified weightage in the resource's budgeted unit section. You can then view the results in the resource assignment tab by filtering activities based on the assigned resource.
@mahansor8295
@mahansor8295 4 жыл бұрын
Hi,
Are YOU Using this Primavera P6 Float Paths Feature?
10:06
Plan Academy Inc.
Рет қаралды 17 М.
When Updating Actual Units & Costs - Primavera P6 Settings EXPLAINED
9:04
I tricked MrBeast into giving me his channel
00:58
Jesser
Рет қаралды 27 МЛН
Это было очень близко...
00:10
Аришнев
Рет қаралды 7 МЛН
UFC 308 : Уиттакер VS Чимаев
01:54
Setanta Sports UFC
Рет қаралды 919 М.
🔴 How to Fix Loop Error in Primavera P6
9:22
Ahmad Setayandeh
Рет қаралды 1,7 М.
The Problem with Longest Path in Primavera P6 and how you can fix it
6:03
Earned Schedule (ES) - What is it?
5:55
Plan Academy Inc.
Рет қаралды 6 М.
How to solve Circular Relationships LOOP in Primavera P6
6:27
Planning Engineer FZE.
Рет қаралды 6 М.
How To Do Rolling Wave Planning in Primavera P6
10:41
Plan Academy Inc.
Рет қаралды 22 М.
Define Critical Activities - Primavera P6 Settings EXPLAINED
7:04
Plan Academy Inc.
Рет қаралды 10 М.
Primavera P6 Layout for EASY Earned Value Analysis
8:52
Plan Academy Inc.
Рет қаралды 13 М.
Update P6 Schedules Easier with Excel [How To]
13:01
Plan Academy Inc.
Рет қаралды 3,1 М.
I tricked MrBeast into giving me his channel
00:58
Jesser
Рет қаралды 27 МЛН