When Updating Actual Units & Costs - Primavera P6 Settings EXPLAINED

  Рет қаралды 25,191

Plan Academy Inc.

Plan Academy Inc.

Күн бұрын

Пікірлер: 24
@didineboutem4303
@didineboutem4303 Жыл бұрын
Very well explained ...simple & clear ..just go on
@ashkan3484
@ashkan3484 3 жыл бұрын
You are the best I found in KZbin thank you
@YRSHAHI
@YRSHAHI 2 жыл бұрын
Great Explanation Michael as always :)
@GlobalProjectControl
@GlobalProjectControl 3 жыл бұрын
Nice Video, Thank you Micheal for sharing great videos
@mohammedabu-elghiet5652
@mohammedabu-elghiet5652 2 жыл бұрын
thanks for clarifying explaination
@ebenezerasare9934
@ebenezerasare9934 4 ай бұрын
Thank you so much for the video, I am doing a historical cleanup where the budgeted - Actual is not equal to the remaining. I have this data for about 589 projects. is there a way to change the settings to affect these past projects.
@syamalabalaravikanthreddy9546
@syamalabalaravikanthreddy9546 Жыл бұрын
When we do that how to calcluate the progress percentages does it should be based on at completion units or budgeted units
@abdelouahabbelalia2072
@abdelouahabbelalia2072 3 жыл бұрын
Great sir , tank you
@qazisalaheen8324
@qazisalaheen8324 Жыл бұрын
hi Sir, Good Explained.. i did same practice but still Actual Units and Remaining Units not calculating correctly. please advise
@PlanAcademy
@PlanAcademy Жыл бұрын
you'll have to explain more detail.
@grandfew8460
@grandfew8460 3 жыл бұрын
Hey dear, could yiu please suggest me a video or seriea if videos to learn peimavera p6. Im beginner in rhis and basically im mechanical engineer.
@dammikamahesh
@dammikamahesh Жыл бұрын
Dear Sir, I Have a small point to be clarified here. As I observed your budgeted units are 400 hrs. But your budgeted cost is Zero initially. Why it is happening? Is your rate Zero? Then you entered the budgeted cost separately. Could you please explain me this. Thanking you very much and I appreciate your work.
@PlanAcademy
@PlanAcademy Жыл бұрын
You can see I have unchecked "Calculate Costs from Units". This is because I often work with FIXED costs on activities - so I uncheck this option and manually enter a Fixed cost into the "Budgeted Cost" field. That way if durations or units change, my costs do not.
@dammikamahesh
@dammikamahesh Жыл бұрын
@@PlanAcademy Got it Sir. Thank you very much.
@PlanAcademy
@PlanAcademy 2 жыл бұрын
Our NEW Progressing Course just launched! Check out the best Advanced P6 Training available online: www.planacademy.com/
@afshinsavoj8907
@afshinsavoj8907 3 жыл бұрын
thank you a lot
@aroop2000
@aroop2000 3 жыл бұрын
Thanks
@Pacific998
@Pacific998 3 жыл бұрын
I normally input percentage complete, to get the earned value. but P6 won't calculate actual units. is there a way to do auto calculate? I used option B. i have a fixed lump sum contract, so i need to maintain at completion = budgeted cost
@arkanaejaz3538
@arkanaejaz3538 3 жыл бұрын
Sir Do you know how to make PV=EV while revising schedule in lump sum fixed contract?
@Pacific998
@Pacific998 3 жыл бұрын
@@arkanaejaz3538 PV is fixed. You've to use the planned percentage= physical percent complete to make EV=PV
@walidkhlil2872
@walidkhlil2872 3 жыл бұрын
thanks
Жыл бұрын
when I enter actuals manually and start the update progress it always recalculates the actuals I entered manually and fixes it budget units/time. how I can keep the actuals the same as I entered? can someone help me, please?
@peterwang4500
@peterwang4500 Жыл бұрын
I'm facing this problem too, have you by any chance already found the solution?
@getugebre8521
@getugebre8521 3 жыл бұрын
I like your tutorial; But on this presentation the words are invisible and undetectable; So it is difficult to follow the steps. Please as much as possible make clear the camera focus to be visible.
Recalculate Actual Units & Costs in P6, When Duration % Complete Changes
6:50
Motorbike Smashes Into Porsche! 😱
00:15
Caters Clips
Рет қаралды 17 МЛН
CAN YOU DO THIS ?
00:23
STORROR
Рет қаралды 47 МЛН
MY HEIGHT vs MrBEAST CREW 🙈📏
00:22
Celine Dept
Рет қаралды 107 МЛН
amazing#devil #lilith #funny #shorts
00:15
Devil Lilith
Рет қаралды 18 МЛН
Resource Loading in Primavera P6 - 5 Tips to make it EASIER
8:11
Plan Academy Inc.
Рет қаралды 32 М.
How to Equal At Completion Cost with Budgeted Total Cost
9:35
Ali Katary
Рет қаралды 3,1 М.
import progress updates with actual dates to primavera p6
10:32
Planning Engineer FZE.
Рет қаралды 26 М.
Critical Path Analysis in P6 - 5 Things I Wish I Knew Earlier
9:55
Plan Academy Inc.
Рет қаралды 204 М.
Motorbike Smashes Into Porsche! 😱
00:15
Caters Clips
Рет қаралды 17 МЛН