Very well explained ...simple & clear ..just go on
@ashkan34843 жыл бұрын
You are the best I found in KZbin thank you
@YRSHAHI2 жыл бұрын
Great Explanation Michael as always :)
@GlobalProjectControl3 жыл бұрын
Nice Video, Thank you Micheal for sharing great videos
@mohammedabu-elghiet56522 жыл бұрын
thanks for clarifying explaination
@ebenezerasare99344 ай бұрын
Thank you so much for the video, I am doing a historical cleanup where the budgeted - Actual is not equal to the remaining. I have this data for about 589 projects. is there a way to change the settings to affect these past projects.
@syamalabalaravikanthreddy9546 Жыл бұрын
When we do that how to calcluate the progress percentages does it should be based on at completion units or budgeted units
@abdelouahabbelalia20723 жыл бұрын
Great sir , tank you
@qazisalaheen8324 Жыл бұрын
hi Sir, Good Explained.. i did same practice but still Actual Units and Remaining Units not calculating correctly. please advise
@PlanAcademy Жыл бұрын
you'll have to explain more detail.
@grandfew84603 жыл бұрын
Hey dear, could yiu please suggest me a video or seriea if videos to learn peimavera p6. Im beginner in rhis and basically im mechanical engineer.
@dammikamahesh Жыл бұрын
Dear Sir, I Have a small point to be clarified here. As I observed your budgeted units are 400 hrs. But your budgeted cost is Zero initially. Why it is happening? Is your rate Zero? Then you entered the budgeted cost separately. Could you please explain me this. Thanking you very much and I appreciate your work.
@PlanAcademy Жыл бұрын
You can see I have unchecked "Calculate Costs from Units". This is because I often work with FIXED costs on activities - so I uncheck this option and manually enter a Fixed cost into the "Budgeted Cost" field. That way if durations or units change, my costs do not.
@dammikamahesh Жыл бұрын
@@PlanAcademy Got it Sir. Thank you very much.
@PlanAcademy2 жыл бұрын
Our NEW Progressing Course just launched! Check out the best Advanced P6 Training available online: www.planacademy.com/
@afshinsavoj89073 жыл бұрын
thank you a lot
@aroop20003 жыл бұрын
Thanks
@Pacific9983 жыл бұрын
I normally input percentage complete, to get the earned value. but P6 won't calculate actual units. is there a way to do auto calculate? I used option B. i have a fixed lump sum contract, so i need to maintain at completion = budgeted cost
@arkanaejaz35383 жыл бұрын
Sir Do you know how to make PV=EV while revising schedule in lump sum fixed contract?
@Pacific9983 жыл бұрын
@@arkanaejaz3538 PV is fixed. You've to use the planned percentage= physical percent complete to make EV=PV
@walidkhlil28723 жыл бұрын
thanks
Жыл бұрын
when I enter actuals manually and start the update progress it always recalculates the actuals I entered manually and fixes it budget units/time. how I can keep the actuals the same as I entered? can someone help me, please?
@peterwang4500 Жыл бұрын
I'm facing this problem too, have you by any chance already found the solution?
@getugebre85213 жыл бұрын
I like your tutorial; But on this presentation the words are invisible and undetectable; So it is difficult to follow the steps. Please as much as possible make clear the camera focus to be visible.