Thank you so much. This tutorial covered things I have never used before. It is very helpful.
@TomStephensontraining3 жыл бұрын
Thanks I’m glad I hit on some new things for you
@theclozer7 ай бұрын
I cant seem to get my critical path correct. YOUR tutuorials are awesome! Thank you!
@vgm3702 жыл бұрын
Sir Tom I have a question can we extract a data for projected weekly accomplishment from the schedule? Do you have any tutorial videos that shows how can we do it or is it possible to do it?
@subratbhoi46002 жыл бұрын
Nice video thanks sir,Any video to watch only linked activities
@TomStephensontraining2 жыл бұрын
Yes if you check my playlists earlier videos like one and 2
@markpalm6722 жыл бұрын
Dear Sir, up to now i have participated in 2 big construction projects (lasting more than 3 years) and the Employer demanded the use of P6 instead of MS Project. From your experience, does MSP finds difficulties handling big projects ?
@TomStephensontraining2 жыл бұрын
Primavera is a better enterprise product in my mind though some may argue that point. Multi billion dollar projects that are cost and resources loaded is best on Primavera. With that said a 400 million dollar condo project often uses ms project. Projects less than 100 million or more often using MS project as it is easier to learn and less costly per user. I could go but it really depends. There is the whole claims side which is another story
@markpalm6722 жыл бұрын
@@TomStephensontraining Many thanks Tom for your valuable experience-gained points of view