MS Project Made Easy Tutorial 6, How To Update A Schedule

  Рет қаралды 17,539

Tom Stephenson

Tom Stephenson

Күн бұрын

Пікірлер: 26
Жыл бұрын
Great explanation! Thanks for sharing your knowledge with us.
@iSanjaySolanki
@iSanjaySolanki Ай бұрын
Excellent video!
@TomStephensontraining
@TomStephensontraining Ай бұрын
Thanks Sanjay very appreciated!
@thephongh
@thephongh 2 жыл бұрын
The best Ms Project tuto ever!
@TomStephensontraining
@TomStephensontraining Жыл бұрын
Excellent, I’m glad it helped you!
@Wisdom_heritage
@Wisdom_heritage 3 жыл бұрын
you tutorials are so helpful that i cant express in words sir.
@TomStephensontraining
@TomStephensontraining 3 жыл бұрын
Thanks Manem, I'm glad they are helping you. Have a great day!
@ammadkhan5380
@ammadkhan5380 10 ай бұрын
Great explanation sir, really helpful. Thank you. Also wanted to ask that, mark on track only works for status date?
@TomStephensontraining
@TomStephensontraining 10 ай бұрын
Thanks Ammad yes it updates only to what you put as the status, which you can change as needed
@markpalm672
@markpalm672 2 жыл бұрын
Great Tom. Could you pls clarify the meaning of %complete? It has to do purely with time (e.g. days compared to baselined duration of activity) or means the accomplished earned value of works (money)until the status date? And what is the meaning of %physical completion column?(shown empty in 13:00 next to % compl.)Thanks for your patience!
@TomStephensontraining
@TomStephensontraining Жыл бұрын
Hi Mark, percent completion is based on duration eg 60 percent complete of a twenty day activity is 12 days. Physical percent complete looks at what is installed or done 300 blocks of a thousand blocks is 30 percent physical completed even if it is day 6 of 10 days
@ig7061
@ig7061 Жыл бұрын
Hello Dear Tom. recourse on a summary task (PM) is not worked when you tracking the project. I assigned PM on a Summary Task but it is not calculated and still shows in variance column
@TomStephensontraining
@TomStephensontraining Жыл бұрын
Hi IG, It should show on the variance but will also include any variances on anything below the summary task. If you want to see the variance on onlt the PM go to the resource sheet and right click on the square icon box in the resource sheet select cost and it will show the variance of each individual resource
@ig7061
@ig7061 Жыл бұрын
@@TomStephensontraining thank you
@douglasdanje5224
@douglasdanje5224 Жыл бұрын
What about updating a plan with LOE activities please
@TomStephensontraining
@TomStephensontraining Жыл бұрын
I have one under my ms project playlist for hammock activities same thing. I plan to do another one though
@milner267
@milner267 Жыл бұрын
Thanks, Tom. A question, though... when selecting the earned Value view... I see columns such as Earned Value and Actual Cost generated, but yet, Planned value/BCWS still appears zeros. Any help with this would be greatly appreciated. Thanks again
@TomStephensontraining
@TomStephensontraining Жыл бұрын
Hi Milner, are your resources that you are monitoring listed as work with an hourly rate?
@milner267
@milner267 Жыл бұрын
Hey Tom. No, I had them set for cost resources.
@paulfallon45
@paulfallon45 Жыл бұрын
Hi Tom Can you help, I have been working on my schedule for quite a while now prior to the commencement of the Job it is a full house renovation I had only managed to assign 2/3rds of the resources prior to setting the base line last week, the schedule hasn’t been updated yet after over a week of progress on site, I had continued to assign more resources to the schedule over the weekend ,but have noticed that there is considerable sum of money showing in the variance column ‘ I am assuming that this is a consequence of me adding more resources after setting of the base line ‘ My question is should I set a new base line after I have finished the the full assignment of all the recourses
@TomStephensontraining
@TomStephensontraining Жыл бұрын
Hi Paul, you can clear the baseline under the project tab go toset baseline and then select clear baseline now reset the baseline and it includes all the changes resource costs that you made. Then you can update it. Always save a backup file that you can go back to.
@paulfallon45
@paulfallon45 Жыл бұрын
@@TomStephensontraining Thanks again Tom that has worked a treat
@darrengodden
@darrengodden 2 жыл бұрын
Hi Tom, at 12.00 minute mark approx. you talk to manually updating the Duration field in the Tracking Gantt view. Is updating the Duration field, the same as updating the Actual duration field, or should I only use duration field? In my testing if I update Actual Duration field it also updates Duration field, but when I update Duration field it did not update Actual Duration field. Thank you.
@TomStephensontraining
@TomStephensontraining 2 жыл бұрын
It really is a preference thing, i often like to adjust and review before i mark as complete. Also if it crosses the status date i mark on track after extending the duration. Nothing wrong with using actual duration at other times
@CalvinMasaseplus24
@CalvinMasaseplus24 2 жыл бұрын
Hi Tom, thanks a lot for the great tutorials I find them very rich and very helpful. I have a question, I see on your Resource Cost Sheet, ABC Plumbing is showing $0 actual cost but it has been assigned to Rough in Plumbing on item 10, does the actual cost for a cost resource update automatically or you do it differently? Many thanks.
@TomStephensontraining
@TomStephensontraining 2 жыл бұрын
Hi Calvin, It should update when you put it as complete in the tracking Gantt unless you change the cost then the new cost will show. I always say to studenrts true it with a few activities and experiment and see how it behaves eg update check then undo change cost update and check …. Make sure you check in the cost, tracking and resource cost screens. Have a great day!
MS Project for Beginners, Add Resources, Costs, and Review Work Usage
35:22
“Don’t stop the chances.”
00:44
ISSEI / いっせい
Рет қаралды 53 МЛН
If people acted like cats 🙀😹 LeoNata family #shorts
00:22
LeoNata Family
Рет қаралды 45 МЛН
Wall Rebound Challenge 🙈😱
00:34
Celine Dept
Рет қаралды 19 МЛН
The Best Band 😅 #toshleh #viralshort
00:11
Toshleh
Рет қаралды 21 МЛН
MS Project Tutorial 5 How to Update a Schedule
33:06
Tom Stephenson
Рет қаралды 187 М.
Project Management Tutorial: 12 Years of Experience in 45 Minutes
45:10
IT Project Managers
Рет қаралды 687 М.
How to set a BASELINE in your MS Project Schedule.  Tutorial #13
20:03
Tom Stephenson
Рет қаралды 29 М.
Minimum every Project Manager should know about MS Project to become successful
38:14
How to CORRECTLY status tasks in Microsoft Project
35:38
Structured Solutions Inc.
Рет қаралды 30 М.
“Don’t stop the chances.”
00:44
ISSEI / いっせい
Рет қаралды 53 МЛН