Variation means a deviation or change from the original scope of works/design/. Variation Process 1. Notice of Variation - informs client of change stating it involves this cost impact. 2. Confirmation of Variation - Client reviews and confirms. 3. Request for Variation Order - a comparison between existing and new program of works illustrating cost for works needed. This also begs the formal amendment of existing contract. 4. Variation Order - a document like a purchase order issued by the client to the contractor to formally include works that will be financially accounted for towards the contractor.
@CEPQS Жыл бұрын
Great 👍
@mhdmushfique97972 жыл бұрын
Thank you so much! Very useful and expecting more videos from you mentor!❤️👍🏽
@CEPQS2 жыл бұрын
Thank you for the support and wish you all the best 🙂👍🙏
@mhdmushfique97972 жыл бұрын
It would be really great if viewers can see examples and the way of clamming the variation through the documents that you previously worked in
@mohammedmakeen91322 жыл бұрын
Short and useful thank you
@CEPQS2 жыл бұрын
Thank you brother 😊. Appreciate your support 👍🙏
@ishtiaqkhan18322 жыл бұрын
Very nicely explained
@CEPQS2 жыл бұрын
Much appreciate your valuable support 🙏🙂👍
@friendsgroup3330Ай бұрын
Dear Sir, EOT (the extension of time) is another form of Variation with or without a change in price of the contract. Thank you.
@CEPQSАй бұрын
EOT is a claim so it can be considered as a variation without cost if no cost is claimed 👍
@sk-yw8pz2 жыл бұрын
Very nice video , add some examples with calculations also
@CEPQS2 жыл бұрын
Will do that in some other videos 👍🙂
@CEPQS2 жыл бұрын
Thank you for watching and support 🙏
@sk-yw8pz2 жыл бұрын
Thank you bro for new informative videos
@thuthutheinaung8042 Жыл бұрын
Thank you so much for your sharing ,sir May I know Myanmar people can apply QS in Dubai, pls
@michaelnguyen33982 жыл бұрын
As per the FIDIC contract, the contractor must execute the variations works even when they still haven't received the approval of their variations. Do you think that is the risk that must be accepted by contractors?
@CEPQS2 жыл бұрын
I believe it says the contractor shall not make any alterations without engineer’s instructions or approval. Hard to answer actually 😃, but if instructions are there then rights are preserved 👍. Contractor may proceed and agree the value in parallel to avoid delaying the works.
@fayazmuhammad25059 ай бұрын
Hi Engr.Ahmed, as watched your another videos for IPC and to deduct 10% of retentions from every month IPC, So for issuing variation amount to contractor, is the retention amount will also impact on variation amount or it will be fully issued to contractors? Thanks
@Messenger_5 Жыл бұрын
Thank you 🙏🏼
@gerardodacruz51882 жыл бұрын
Thank you for the content, sir. Btw I bought your course quantity surveying on udemy but it is no longer available on the platform. Is there something wrong?
@wajidsaleem73112 ай бұрын
Same problem with me
@hendriksaldua82087 ай бұрын
If the programme is changed by concurrently managed variations that increase value, will the cash flow forecast alter?
@gdfb35912 жыл бұрын
Hi Sir, i commented on your other video but that comment is more related to this video, Thanks for bringing me to this video link. Just a follow-up question about contract especially for variation order. First, My understanding about the calculation of variation order that it should be in detailed (same as class 1 estimate). Is it possible for a contractor to submit a variation order in a form of re-measurement? Or lumpsum?
@CEPQS2 жыл бұрын
Maybe better to make a video on this in the future. 👍
@MunyaradziMutye-m3h Жыл бұрын
Thank you
@shishimim77874 ай бұрын
❤❤
@ayadoleh3488 Жыл бұрын
Thank you for your videos its helpful, but i prefer to remove the music because we need to focus on the information it self no need for the sound effect .. thank u again
@CEPQS Жыл бұрын
Understood and thank you for watching. All the best 👍
@technology4453 Жыл бұрын
Thanks
@Toubah6702 жыл бұрын
what about the music attached plz i cant hear you.. thank u
@CEPQS2 жыл бұрын
Oh 😟. Apologies for that. I’ll take care about music in the next videos 👍
@rosiubaith5786 Жыл бұрын
Please give example for quantity and item ?? Client wants additional door in a room ?? Is it item or quantity ???
@CEPQS Жыл бұрын
If the door has a rate already in the BOQ, then it is Ana additional quantity. If it is a new door with new specs, then new item 😊
@aqtharaqadomaths9300 Жыл бұрын
Sir please add MEP measurement taking short cuys
@muhanadal-kamali60342 жыл бұрын
Dear Eng. Ahmad...The impact of variation on the Project Period is not explained
@azhardin6Ай бұрын
Dear please reduce the music sounds thanks
@CEPQSАй бұрын
Will do in the future videos 👍. Thanks for the feedback