There is a common issue while updating the materials and shop drawing's status in your schedule.
For example,
1. Submission & Approval: of material If we submit the material we considered the activity completed and awaiting approval. But we have received a Revised and Re-submit status. How to consider this situation?
2. Material delivery: After approval of the material we placed the order.
One of our long lead items has 86 days. How to update this progress every week for the weekly report?
---------------