How to Update & Revise a Project Schedule, MS Project Made Easy Tutorial 7

  Рет қаралды 22,302

Tom Stephenson

Tom Stephenson

Күн бұрын

Пікірлер: 41
@ig7061
@ig7061 Жыл бұрын
Dear Tom thanks for your all videos. they are explained very professionally. thanks again for your effort!!!
@TomStephensontraining
@TomStephensontraining Жыл бұрын
Glad you like them!, thanks for the kind words!
@ronaldbalikudembe8519
@ronaldbalikudembe8519 Жыл бұрын
I'M BALIKUDEMBE RONALD, A CIVIL ENGINEER BY TRAINING, FROM UGANDA. ON GOING WITH A MASTER IN CONSTRUCTION MANAGEMENT. YOUR VEDIO'S HAVE BE OF MUCH HELP.
@TomStephensontraining
@TomStephensontraining Жыл бұрын
Very nice, I’m glad that they help you. Thanks for the kind words Ronald
@ahmedel-assar1505
@ahmedel-assar1505 3 жыл бұрын
Thank you Sir, this and the previous videos were very useful to me as i was interested in tracking specifically wishing you all the best and great success please keep going
@TomStephensontraining
@TomStephensontraining 3 жыл бұрын
Thank you Ahmed, let me know if there are topics that would help that i have not done yet.
@ahmedel-assar1505
@ahmedel-assar1505 3 жыл бұрын
@@TomStephensontraining Thanks Mr Tom, yeah now i am learning now from your videos and apply them in my work Is there a tool or a way in MS Project like claim digger in primavera ?
@tadiosnyamuziwa5679
@tadiosnyamuziwa5679 Жыл бұрын
Great videos Tom. Thank you. I just want to find out, do you have videos covering issues to do with scope, planning, risk, stakeholder management etc in your play list
@TomStephensontraining
@TomStephensontraining Жыл бұрын
Yes many, look under cost control, site management, and pm tips playlists. Im glad the videos help!!!
@tadiosnyamuziwa5679
@tadiosnyamuziwa5679 Жыл бұрын
Thanks
@chariya8356
@chariya8356 Жыл бұрын
Thank so much for your video
@TomStephensontraining
@TomStephensontraining Жыл бұрын
You are very welcome
@etoe9405
@etoe9405 3 ай бұрын
Great work sir...From Pakistan. You are requested to please do tutorials on Primavera P6.
@TomStephensontraining
@TomStephensontraining 2 ай бұрын
Yes perhaps at some point! Thanks for the suggestion
@habenmussie1245
@habenmussie1245 3 жыл бұрын
hello sir,How great you are to make these videos. I really appreciate them. I am a civil engineer with little experience in construction. I am now thinking of shifting to construction management. I have some questions. Do your lessons go parallel with American methods of construction. My second question is can you tell me with which once of your playlist should I start to study.
@TomStephensontraining
@TomStephensontraining 3 жыл бұрын
Hi Haben, yes pretty much like the American, there might be some minor differences in safety and building code but that’s about it. Some things are total American like the Lean processes. I would suggest Introduction to Construction, then residential, then site mgmt, if you have Msproject they can occur during site mgmt, then cost control and then bus Mgmt which im currently working on. I also have the tools techniques plylist which is excellent to refer to throughout. I hope that helps. Im happy you are enjoying them 😀
@habenmussie1245
@habenmussie1245 3 жыл бұрын
@@TomStephensontraining I am so grateful for your quick reply sir. I will do as you said and continue this good work sir.
@madusankak.h.m.a782
@madusankak.h.m.a782 2 жыл бұрын
Thank you, mr. Tom.
@TomStephensontraining
@TomStephensontraining 2 жыл бұрын
You are welcome Madusanka
@dmurugank3809
@dmurugank3809 2 жыл бұрын
Thanks from India, Tamil nadu
@TomStephensontraining
@TomStephensontraining 2 жыл бұрын
Great, always nice to connect with viewers from India
@sarfrazrabbani8827
@sarfrazrabbani8827 2 жыл бұрын
Thanks a lot being such a mentor, I am new in MS Project have 1 complication like, in duration column most of the task showing with decimal if I remove the decimal schedule convert to the manual.how can I modify in auto schedule? Since I am using 11 hour a day in std calenders for the project.
@TomStephensontraining
@TomStephensontraining 2 жыл бұрын
Hmm not sure but I suspect it is because in the options setting you have 8 hr days instead of 11 hr test on a practice file and see if that helps.
@Tokoloko
@Tokoloko 2 жыл бұрын
Hello Tom! Thank you for your very interesting videos! Nevertheless, I still have a question about organizing tasks which is the follows: Consider there is a task to be done which is divided in 10 subtask. Every subtask takes a day and you can only do one subtask at a time, so the overall task takes 10 days. But: There is no specific order in which these subtasks have to be done. You may decide it on the spot or whatever comes handy next. So I would be reluctant to line them all up with finish to start relationships because it does not reflect reality and maybe I run into troubles when I update the plan and did not do the tasks in the order I planned them beforehand. However, I want to reflect that the sum of the tasks takes 10 days. Do you have a neat idea how to do that? Or is it maybe even explained in one of your videos (up to now I only saw the "Made Easy Tutorial" upto this one). Greetings from germany!
@TomStephensontraining
@TomStephensontraining 2 жыл бұрын
Hi, I would suggest giving them all a 9 day lag to the seem succeeding activity. Thencwhen you update you can put the actual dates given they all have flexibility within that zone.
@Nadia-yt6db
@Nadia-yt6db 9 ай бұрын
@@TomStephensontraining do you have a video explaining how to do this? I'm not sure I understand the response you gave the OP. What would the dependencies between the tasks be? Duration of each? How to set up the 9 day lag?
@anjotmohamed7324
@anjotmohamed7324 2 жыл бұрын
hello tom. is there any tutorial on how to revise project schedule after Project Extension of Time granted. thanks
@MandarJoshi-m3m
@MandarJoshi-m3m Жыл бұрын
Hi Tom, suppose today is the status date of update and the task was supposed to be finished today 100%. But it did finish only 75%. Do I move the incomplete 25% to status date?
@TomStephensontraining
@TomStephensontraining Жыл бұрын
Just enter actual dates mark on track that activity and it will indicate what is done to the status date and what is not done. Also if work started but did not complete then split the task accordingly and mark in track to satus date
@MandarJoshi-m3m
@MandarJoshi-m3m Жыл бұрын
@@TomStephensontraining ok thanks
@mylajanemalabanan5218
@mylajanemalabanan5218 7 ай бұрын
Hi Sir. Good Day. I encountered problems with Microsoft project which is Publish Failure (error 23000)I suspect it was corrupted. I am thinking of how am I going to unpublish the workplan since it always fail to publish. Your response will be appreciated. Thankyou
@TomStephensontraining
@TomStephensontraining 7 ай бұрын
Sorry I’m not familiar with that, try running your question on chat gpt
@Fenddy95
@Fenddy95 Жыл бұрын
Hello Tom! How about revising a program for the implementation of EOT? I have problem on the "% Complete" because it changes automatically when we extend the duration of tasks and it causes my actual cost to be changed. Is there any video of your showing how to revise for the implementation of EOT in project?
@Fenddy95
@Fenddy95 Жыл бұрын
P/s: I was trying to create a new baseline for the new completion date. TQ for your help!!😁
@TomStephensontraining
@TomStephensontraining Жыл бұрын
Hi Abdullah, sorry for the late reply Ill look at that when i get a chance
@Fenddy95
@Fenddy95 Жыл бұрын
@@TomStephensontraining Thank you very much sir..Youve been helping me a lot through all your videos..👍👍👍
@SajalAhmed1612
@SajalAhmed1612 9 ай бұрын
good
@adamthomas5732
@adamthomas5732 2 жыл бұрын
Tom, can you please assist me with creating a "Site Report of Activities Progress" to send to the Project Superintendent? Thanks!
@TomStephensontraining
@TomStephensontraining 2 жыл бұрын
Sorry I could not help, I’ve been really busy
@sebfromgermany3819
@sebfromgermany3819 2 жыл бұрын
While you are in the tracking screen you update the column duration instead of actual duration - any reason for this?
@TomStephensontraining
@TomStephensontraining 2 жыл бұрын
No big reason, just I like to see where it goes before i mark complete. Also easier for mark on track if it crosses the status date
MS Project Made Easy Tutorial 6, How To Update A Schedule
28:46
Tom Stephenson
Рет қаралды 16 М.
小丑家的感情危机!#小丑#天使#家庭
00:15
家庭搞笑日记
Рет қаралды 29 МЛН
Don't look down on anyone#devil  #lilith  #funny  #shorts
00:12
Devil Lilith
Рет қаралды 45 МЛН
Inside Out 2: ENVY & DISGUST STOLE JOY's DRINKS!!
00:32
AnythingAlexia
Рет қаралды 17 МЛН
Becoming a Construction Project Manager, with Chinyere Johnson
45:25
Efficiency Canada
Рет қаралды 28 М.
Prospective delay analysis using MS Project
16:12
JC le Roux
Рет қаралды 43 М.
How to set a BASELINE in your MS Project Schedule.  Tutorial #13
20:03
Tom Stephenson
Рет қаралды 27 М.
How to Use Microsoft Planner to Manage Your Project (2024)
27:15
Scott Brant
Рет қаралды 144 М.
MS Project 8 - Tracking Task Progress and Variance
22:19
PatJHeffernan
Рет қаралды 36 М.
小丑家的感情危机!#小丑#天使#家庭
00:15
家庭搞笑日记
Рет қаралды 29 МЛН