As a product manager, I did notice the time to deliver the video was about 50% longer than was time promised in the title (JK: very simply put, well done)
@Onlinepmcourses4 жыл бұрын
Mea culpa!
@akshaykumarpatel43747 ай бұрын
Great Explanation but have one question, how do you plan second resource? If the first resource complete the task in 4 days (early than expected), should second resource should drop everything she is doing and continue on this project?
@Onlinepmcourses7 ай бұрын
If you are going to use critical chain - or critical path - scheduling, you need resources to have time flexibility. Where this is not the case, you need to build contingency into each task allocation and accept that this can create gaps in progress.
@martinnobrega78373 жыл бұрын
Very good! There is one concern about this method. Let's say Amit completes his task in 5 days, there won't be any problem as you still a 5 days buffer, but what about Becky and Chang allocations? You would have 4 mwd (man working days) without charging them to any project.
@Onlinepmcourses3 жыл бұрын
Every technique is useful in some circumstances, less useful in others, and not appropriate in some. If you need to pay a team for time available, rather than time worked - or you are unable to redeploy people onto other tasks, this may not be the right approach.
@jdogjr95094 жыл бұрын
From a management perspective, how would I explain this to the workers? Take Chang, for example, would I just disregard his worries and say "get it done in 4 days"? Wouldn't this advocate for lower quality work for him to meet the 4 days? I'm new to project mgmt so I want to understand this better.
@Onlinepmcourses4 жыл бұрын
Jason - god question. No - you don't disregard Chang's worries. His estimate is 4 days, so you are giving him that 4 days. But he has concerns that this could be compromised. So, you would reassure him that, if he does need it, you do have contingency you'll be able to give him. But his need to justify the contingency now will change his psychology. Now he knows that the extra time is not just his of right.
@jdogjr95094 жыл бұрын
@@Onlinepmcourses Sounds good. That makes sense. Thanks so much for the reply!
@Onlinepmcourses4 жыл бұрын
@@jdogjr9509 You're welcome.
@vikaskulkarni63343 жыл бұрын
Excellent explanation! Thank you.
@Onlinepmcourses3 жыл бұрын
Thank you, Vikas.
@kunalwaghmare1433 жыл бұрын
Excellent explanation, love your work !!
@Onlinepmcourses3 жыл бұрын
Thank you! Cheers, Kunal!
@ehsaanmiah43763 жыл бұрын
What if there are issues that needs to be dealt with on one of the work streams immediatley (Chad) , do you apply the resource/feeder/project buffer to temporarily give chad one day to fix this or do they have to wait till the the 7 day buffer to get issues solved
@Onlinepmcourses3 жыл бұрын
You have options, as you say. So, there is no theoretical 'right' answer... just the best answer in your situation. However, note that, if Becky and Chang need to hard-schedule their start dates, the critical chain approach may not work, because if Amit's task is delayed, you may lose time in the availability of Becky or Chang.
@ehsaanmiah43763 жыл бұрын
@@Onlinepmcourses so what i said can be applied to immediately give buffer time to chad or to wait till the 7 days, but the concern is mainly who to give attention to based on the resources the pm as if you help chas immediately the aggregate buffer time will reduce further causing issues with the pm Can you explain what you mean by giving pm flexibility (in ur video) if u add the buffer times together. Im kind of confused as u didnt go in depth what u meant by flexibility Thx again ur a life saver
@Onlinepmcourses3 жыл бұрын
@@ehsaanmiah4376 By aggregating the contingency, the PM now has 7 days to use as they choose, to overcome delays and problems. It doesn't matter whose work is the problem, the PM can apply all 7 days to fixing the problem they encounter. If you don't need the extra time, you can either start the next task set early (if possible), undertake additional work, or relax.The PM is in control of the full buffer time because you have not allocated it to anyone else.
@janlanghans48382 жыл бұрын
Now I understand. Thanks for that.
@Onlinepmcourses2 жыл бұрын
You're welcome - great to hear.
@birminghamcitytraders835918 күн бұрын
unfortunately, I think this seems a little misleading. Goldratts simple critical chain method is cut and paste. So you cut the critical chain in half, and the half you cut is now the contingency. You've showed the variance in each task, which is good, but then summed up the variance and added that as contingency. So this is like someone giving you a pessimistic and likelihood estimate and then you using the difference as contingency, which I don't think is Goldratts method. Good Video though.
@Onlinepmcourses18 күн бұрын
I am highlighting the distinction between the critical path method which allocates contingency to each task (and therefore, to each performer) and the critical chain method, which does not, but creates a buffer for the chain, based on an estimate of the contingency needed. In practice, tis can be less than the sum of the individual contingencies if (and only if) the uncertainties are probabilistic.
@Adam-ui3ot4 жыл бұрын
Superb.
@Onlinepmcourses4 жыл бұрын
Thank you.
@aliviawalidonna4 жыл бұрын
That's awesome explanation sir..
@Onlinepmcourses4 жыл бұрын
Thank you very much.
@MrJeffmaze2 жыл бұрын
was interested but terrible audio.
@Onlinepmcourses2 жыл бұрын
Thank you... a bit. Audio is hard, and this was an early video, so I have learned a lot and I think my newer videos are far better. I have also invested in better equipment. I apologise for my past sins and hope you'll forgive me.