Project crashing explained

  Рет қаралды 195,006

Engineer4Free

Engineer4Free

Күн бұрын

Check out www.engineer4free.com for more free engineering tutorials and math lessons!
Project Management Tutorial: Project crashing explained.
Here is the link to the project crashing example: • Project crashing full ...
Minor typo: E is written as preceded by E&F while it should be C&D!
Please support my work:
PATREON | / engineer4free
Every dollar is seriously appreciated and enables me to continue making more tutorials

Пікірлер: 35
@taufeqtauf1817
@taufeqtauf1817 8 жыл бұрын
All the project management videos are great, thank you
@meghanchilds5312
@meghanchilds5312 5 жыл бұрын
Hey, I just wanted to say thank you for making these videos! These videos literally helped me pass my operational management course
@Engineer4Free
@Engineer4Free 5 жыл бұрын
That's awesome!!! Thanks for letting me know =)
@qhakazilenono4471
@qhakazilenono4471 3 жыл бұрын
Can you please help me am struggling
@Engineer4Free
@Engineer4Free 3 жыл бұрын
Full playlist is here: engineer4free.com/project-management I recommend starting at the beginning and working along! It will be worth your time
@Jasminlieber
@Jasminlieber 7 ай бұрын
Thank you! Those videos are really helpful for me, especially at the first semester of learning project management.
@lexparsimoniae2107
@lexparsimoniae2107 7 жыл бұрын
Very clear explanation! Thank you!
@carlodelossantoslebron7874
@carlodelossantoslebron7874 3 жыл бұрын
Hello. Very helpful video. My only question is if it is possible to do partial crashing? For example, I need to reduce the days of a project by 3, but the crash duration of the next cheapest option is 5. How can I calculate the cost for this activity after partial crashing?
@jyotinegi7413
@jyotinegi7413 2 жыл бұрын
when crashing a project do we have to concentrate on task with least expensive gradient or path with least slack?
@shahzebchoudry6175
@shahzebchoudry6175 2 жыл бұрын
Very very very very*100 clear and understandable information
@chewiearmy5524
@chewiearmy5524 Жыл бұрын
I thought I would never get this. Thank you for this video.
@mehdi.sajadi
@mehdi.sajadi 2 жыл бұрын
you're amazing man , thank you so muuuuuuuuuuuuuuuuuuch
@jeetpatel4169
@jeetpatel4169 2 жыл бұрын
How did you get project duration is it assumed. If it is assumed then on what basis
@andilenjani9310
@andilenjani9310 4 жыл бұрын
Amazing thankyou, the day before my Construction Management exam!
@Engineer4Free
@Engineer4Free 4 жыл бұрын
Good luck!! Check out engineer4free.com/project-management for the rest of the videos if you haven’t already!!
@andilenjani9310
@andilenjani9310 4 жыл бұрын
@@Engineer4Free I'm confident in saying I got the crashing Question correct thanks to you! I have also bookmarked your website for the rest of my Civil Engineering ,degree It looks fantastic! Thank you for the great work!
@Engineer4Free
@Engineer4Free 4 жыл бұрын
@@andilenjani9310 Amazing!!! So glad to hear it 😁. Thanks for the bookmark, and please share it with some friends in your classes too 🤜🤛
@reetikaaggarwal2587
@reetikaaggarwal2587 5 жыл бұрын
Hi can you please tell me how to crash an activity if its in critical path and it’s normal time is less than crash time?
@Engineer4Free
@Engineer4Free 5 жыл бұрын
Normal time less than crash time sounds like a typo, I'd ask your professor to make sure it's not.
@sanamehtab5392
@sanamehtab5392 5 жыл бұрын
Can u help me in a question?
@MitulShah114
@MitulShah114 5 жыл бұрын
What if the fixed cost is not mentioned in the question? Do we assume something?
@Engineer4Free
@Engineer4Free 5 жыл бұрын
If you're not given a fix cost, don't worry and be happy, assume there is none.
@sevdaeren5370
@sevdaeren5370 4 жыл бұрын
For activity A, if the crash duration would be 1, still you won't crash it. Can you please explain why? Why it is a good idea and why it is a bad idea?
@Engineer4Free
@Engineer4Free 4 жыл бұрын
Hey i did a 2 part video solving this exact problem and explaining everything, it's here: kzbin.info/www/bejne/kIC6Y4SLlNiVgJY and kzbin.info/www/bejne/ZqClhquopd-Knq8
@minafathi1164
@minafathi1164 3 жыл бұрын
thank you so much! helped me alot.
@Engineer4Free
@Engineer4Free 3 жыл бұрын
Glad it helped! You can check out the rest of the playlist here: kzbin.info/aero/PLOAuB8dR35oeyKU0ojIxD8Muf6Mwc8ugW =)
@minafathi1164
@minafathi1164 3 жыл бұрын
@@Engineer4Free Almost finish all videos. Thank you again👍
@xzotzvvs6492
@xzotzvvs6492 8 жыл бұрын
Nice one
@dawnnelson1814
@dawnnelson1814 2 жыл бұрын
I cant see the bottom chart layout... too blurry
@saraair7939
@saraair7939 7 жыл бұрын
Thank you so much 🌹
@Engineer4Free
@Engineer4Free 7 жыл бұрын
Thanks for the rose! Glad you liked the video :)
@Memento-_-Mori-_-982
@Memento-_-Mori-_-982 6 жыл бұрын
E is written as preceded by E&F while it should be D&F!
@Engineer4Free
@Engineer4Free 6 жыл бұрын
Good eye, thanks for pointing it out, I've added your note to the description!
@Pepperrinooo
@Pepperrinooo 4 ай бұрын
Shouldnt it be C,D since F would have the predecessor E not vice versa ???
@nalaunanyannickodjayp.2088
@nalaunanyannickodjayp.2088 2 жыл бұрын
SAKET SA ULO HUHU
Project crashing full example (part 1/2)
9:35
Engineer4Free
Рет қаралды 298 М.
Difficult network diagram example with lag solved
12:37
Engineer4Free
Рет қаралды 345 М.
ХОТЯ БЫ КИНОДА 2 - официальный фильм
1:35:34
ХОТЯ БЫ В КИНО
Рет қаралды 2,2 МЛН
Кәріс тіріма өзі ?  | Synyptas 3 | 8 серия
24:47
kak budto
Рет қаралды 1,7 МЛН
OMG 😨 Era o tênis dela 🤬
00:19
Polar em português
Рет қаралды 9 МЛН
What is Crashing the Timeline? Project Management in Under 5
5:39
Online PM Courses - Mike Clayton
Рет қаралды 8 М.
Operations Management: Project Management - Crashing III
12:49
The Business Doctor
Рет қаралды 7 М.
Project Network Diagrams - Project Management
26:38
Q Visible
Рет қаралды 398 М.