Project crashing full example (part 2/2)

  Рет қаралды 104,136

Engineer4Free

Engineer4Free

Күн бұрын

Check out www.engineer4free.com for more free engineering tutorials and math lessons!
Project Management Tutorial: Project crashing full example (part 2/2).
Here is the link to Part 1 of the tutorial: • Project crashing full ...
There is a typo in the table of dependencies. Activity E should depend on C and D. Also, In run 4, I wrote 11,000 but said 1,100. I should have written 1,100.
Please support my work:
PATREON | / engineer4free
Every dollar is seriously appreciated and enables me to continue making more tutorials

Пікірлер: 134
@tariqfarooq543
@tariqfarooq543 8 күн бұрын
After 9 Years...... Your videos are so much understandable.
@immortaleddie
@immortaleddie 6 жыл бұрын
I had to sort for hours through hours of videos from people who barely speak any English and did not know how to explain crashing correctly. Thank you for posting this! this truly helped me. The inclusion of indirect cost is totally needed in crashing.
@Engineer4Free
@Engineer4Free 6 жыл бұрын
Hey thanks for letting me know. I have seen other examples that don't include indirect costs and think it's a shame to leave out. Feel free to check out the rest of my PM videos if you haven't already at engineer4free.com/project-management this is video # 29 of 46. Cheers!
@user-ci7uo1uz9n
@user-ci7uo1uz9n 3 жыл бұрын
omg thank you!!!! this just saved me on my project management exam thank you so much for your amazing explanation it definitely makes sense to me now! you've literally saved me, had to subscribe!
@Engineer4Free
@Engineer4Free 3 жыл бұрын
You're very welcome!!! The rest of my PM videos are here: engineer4free.com/project-management good luck =)
@arvindprasad5919
@arvindprasad5919 4 жыл бұрын
Thank you. Your explanation is the simplest among the many tutorials that I saw. You helped me complete an assignment. Cheers
@Engineer4Free
@Engineer4Free 4 жыл бұрын
Amazing, thanks for letting me know! Do check out all the PM videos that I made here: engineer4free.com/project-management if you haven't already, and share them with some classmates 😊
@maksympt1
@maksympt1 7 жыл бұрын
Thanks a lot for the vid! There is a small error: in run 4 you said eleven hundred but you wrote 11,000
@mrsbobbicisse
@mrsbobbicisse 3 жыл бұрын
Thank you for taking the time to create these videos.. this material is hard for me to digest because I am not process oriented, I am task oriented having left IT years ago BUT my current role requires this soooo.. thank goodness for this video..
@Engineer4Free
@Engineer4Free 3 жыл бұрын
You can do it! Sounds like you know already that there are more videos here: engineer4free.com/project-management but thanks for being subscribed and watching! =)
@MRS75
@MRS75 6 жыл бұрын
I wish you would post a lesson on crashing with consideration to damage costs. That would be so helpful.
@Onestarmn
@Onestarmn 2 жыл бұрын
that is pretty well understood, really well-organized, you are a well-done tutor, thank you a lot
@Engineer4Free
@Engineer4Free 2 жыл бұрын
You're welcome Khilola! Thanks for watching 🙌. Many more in the Project Management playlist on my channel 😁😁
@andrewjeon2714
@andrewjeon2714 6 ай бұрын
This is an incredable explanation for CRM. Thank you so much!
@Engineer4Free
@Engineer4Free 6 ай бұрын
Thanks!! =)
@traviswilliams9800
@traviswilliams9800 3 жыл бұрын
Incredible video! Thank you so much. I no longer have to cry myself to sleep trying to figure this out.
@Engineer4Free
@Engineer4Free 3 жыл бұрын
😂 glad I could help!!!
@moechano
@moechano 4 жыл бұрын
Literally the best video on the internet, thanks heaps fam.
@Engineer4Free
@Engineer4Free 4 жыл бұрын
🙌 Thanks so much Moe 🙌
@blezyaugusto9021
@blezyaugusto9021 6 жыл бұрын
Thank you so much! Very helpful in Operations Research
@Engineer4Free
@Engineer4Free 6 жыл бұрын
Awesome, thanks for letting me know!! :)
@fatimamizil4992
@fatimamizil4992 5 жыл бұрын
ive watched most of you PM vids, they are sooo helpful! thank you so much. this one, though, was a bit confusing. i think it wouldve been better if you took more time explaining each step. otherwise thank you so much!
@Engineer4Free
@Engineer4Free 5 жыл бұрын
Hey Tima, there was a video that I did that explains the process of project crashing, and then this two part example. If you haven't seen the explainer vid yet, it's here: www.engineer4free.com/4/project-crashing-explained If you had already seen it and still find crashing a bit difficult, that's normal. There's a lot going on in these problems and it just takes some practice to really become comfortable with knowing that you are making the right decision at each step =)
@fahimqasimi2481
@fahimqasimi2481 4 жыл бұрын
Thank you for the good work. Appreciate it.
@Engineer4Free
@Engineer4Free 4 жыл бұрын
You're welcome!!
@theawaiskhan599
@theawaiskhan599 4 жыл бұрын
Excellent !! Helped a lot!
@basakar5912
@basakar5912 4 жыл бұрын
Thank you so much! This video helps a lot!!
@Engineer4Free
@Engineer4Free 4 жыл бұрын
You're welcome, thanks for watching! Check out all the PM vids I did over at engineer4free.com/project-management when you have a minute ☺️
@dannysakavuyi1587
@dannysakavuyi1587 2 жыл бұрын
Wow, I finally get this now. Thanks
@ismantoringgo6707
@ismantoringgo6707 5 жыл бұрын
thanks a lot for your video. Amazing. very helpful
@Engineer4Free
@Engineer4Free 5 жыл бұрын
You're welcome Ismanto, thanks for the nice feedback and glad you find it helpful!!
@Feri9
@Feri9 5 жыл бұрын
LOL i commented in part one as the typo of TF and you already fixed it here ,good videos tho! better than my prof...
@Engineer4Free
@Engineer4Free 5 жыл бұрын
=) =)
@nicholeh1280
@nicholeh1280 6 жыл бұрын
So very helpful! This and part one. I would not have gotten this right from just reading the text book.
@Engineer4Free
@Engineer4Free 6 жыл бұрын
Thanks for letting me know, glad to hear it :)
@SepSol75
@SepSol75 5 жыл бұрын
Thanks a lot! these videos are awesome! keep it up :) btw there is another typo in this part as well, at 5:43 you say 1,100 but write 11,000. I thought I should point that out.
@Engineer4Free
@Engineer4Free 5 жыл бұрын
Hey yeah thanks for pointing it out! Not worth remaking the video over but hopefully others will see your comment and not be confused!!
@mariaerickanicolas
@mariaerickanicolas 4 жыл бұрын
Thank you so much!! Big help!
@Engineer4Free
@Engineer4Free 4 жыл бұрын
Glad to hear it!!!
@hamidahshuhud245
@hamidahshuhud245 3 жыл бұрын
Thankyou so much! I finally understand how to crush a project
@Engineer4Free
@Engineer4Free 3 жыл бұрын
Glad it helped!!! The full PM playlist is here btw: kzbin.info/aero/PLOAuB8dR35oeyKU0ojIxD8Muf6Mwc8ugW. 💪
@Blissful8640
@Blissful8640 Жыл бұрын
Love this thank you so much
@brandonlee8718
@brandonlee8718 5 жыл бұрын
thanks for your videos, very nice
@Engineer4Free
@Engineer4Free 5 жыл бұрын
Thanks for watching and commenting :)
@faichalayeva6017
@faichalayeva6017 2 жыл бұрын
Sincerely, thank you.
@jarcology8000
@jarcology8000 3 жыл бұрын
Omg you made it easier for us! More vids plss!💝💝
@Engineer4Free
@Engineer4Free 3 жыл бұрын
Awesome!! Full playlist is here: engineer4free.com/project-management
@felixkipyego8497
@felixkipyego8497 5 жыл бұрын
Hey, great videos! You have been of great help for more than two years for me now. Okay, in the 3rd run, you saved a day each from activity C & D, aren't those supposed to be 2 days and the total cost equivalent to $1200? Perhaps since you crashed on the same day got me confused.
@Engineer4Free
@Engineer4Free 5 жыл бұрын
Heyyyy that's awesome to hear! Glad I can help and that you've stuck around so long =) =). Now to answer your question. At the beginning of run 4, there are two critical path: A-B-C-E and A-B-D-E. each path before the 4th run is 15 days long. If you crash A-B-C-E, then A-B-C-E would have 14 days of activity and 1 day of float, while A-B-D-E would still be 15 days of activity, so the project duration would still be 15 days. So, to actually shave a full day off the project and get the whole project down to 14 days, we need to also crash A-B-D-E. Once we do this, A-B-C-E and A-B-D-E will both have 14 days long, and will both be critical again. So, we have crashed twice, but only reduced the entire project duration by one day (from 15 days to 14 days). Our whole project costs us $600 per day in overhead, and because we have only shaved off one day (15 days down to 14 days) we have only saved one day in in overhead costs. Really I should have crashed A-B-C-E and A-B-D-E in two separate steps to show that the project duration wouldn't be affected with only one of them crashed, but I just wanted to speed it up a bit so I did both together. Does that make sense?
@felixkipyego8497
@felixkipyego8497 5 жыл бұрын
@@Engineer4Free It makes sense now... thank you so much! And thank you for the timely response, I am working on my assignment, the timing was perfect. Keep doing what you do. How I wish you were my professor... straight A's lol.
@Engineer4Free
@Engineer4Free 5 жыл бұрын
Thanks @@felixkipyego8497!! 😀😀
@brianc3271
@brianc3271 3 жыл бұрын
Awesome videos! But why did you keep reducing the durations of the other activities even if you weren’t crashing that specific one?
@sylvamadu3721
@sylvamadu3721 Жыл бұрын
super super useful again, teaching me more then some of my uni leturers haha.
@Engineer4Free
@Engineer4Free Жыл бұрын
Haha glad I can help! The full playlist is over here: engineer4free.com/project-management 👌
@dilpreetsinghwadhwa237
@dilpreetsinghwadhwa237 5 жыл бұрын
Thanks alot for this video.
@Engineer4Free
@Engineer4Free 5 жыл бұрын
You're welcome Dilpreet, thanks for watching!
@rajeshparkar5683
@rajeshparkar5683 4 жыл бұрын
helpful!!! THANK YOU
@NightGlory.
@NightGlory. 5 жыл бұрын
you saved my life!!!!!!!!!!
@Engineer4Free
@Engineer4Free 5 жыл бұрын
Glad I can help!!! =)
@rahalhettiarachchi8967
@rahalhettiarachchi8967 4 жыл бұрын
Thank you very much!
@Engineer4Free
@Engineer4Free 4 жыл бұрын
You’re welcome Rahal!! Thanks for watching =)
@nabulsi93
@nabulsi93 9 жыл бұрын
very helpful
@mickeycook569
@mickeycook569 3 жыл бұрын
Man you are awesome!!!!!!!!
@Engineer4Free
@Engineer4Free 3 жыл бұрын
Thanks!!! =)
@drewjohnson5200
@drewjohnson5200 Жыл бұрын
Hey @engineer4free , Great content and super helpful. Just one question though. Why did you not just crash one of the variables at 3:55 ? I know you said it is becuase "they are in parallel" but im not sure what this means. Could you elaborate? thanks.
@nihalahmed3309
@nihalahmed3309 Жыл бұрын
Since both the activities are now critical, we need to crash both in-order to reduce the project duration, if we crash only one like u said there will be no impact on project duration (i.e., project duration does not reduce) For better understanding - Imagine a building resting on 2 columns whos height is 30m (I know building with 2 columns doesn't exists but lets imagine) so in-order to reduce the building height we need to remove 2 columns, if only 1 column is removed the building height does not change. Plz correct me if am wrong.
@alamsyahsuhanto
@alamsyahsuhanto 2 жыл бұрын
Hi, don't you think on the run 2, the cost should be 500 + 600? Because on run 2, you crash activity E and B. In you calculation you only count the crash cost of activity B.
@farhan777k
@farhan777k 6 жыл бұрын
You're the best !!
@Engineer4Free
@Engineer4Free 6 жыл бұрын
Thanks Farhan! :)
@MegaMeowzerz
@MegaMeowzerz 4 жыл бұрын
Thank you good sir!
@Engineer4Free
@Engineer4Free 4 жыл бұрын
Thanks Connor!!!!
@berkanspotify4867
@berkanspotify4867 5 жыл бұрын
LEGEND. AMAZING VIDEO. HOPE ILL DO FINE TMR. GOT A STATS FINAL
@Engineer4Free
@Engineer4Free 5 жыл бұрын
Haha thanks! Good luck I hope you crush it 💯💯
@alyannamarielle2056
@alyannamarielle2056 5 жыл бұрын
Hi! The cost for run 4 is just 1,100. Great tutorial btw, was very helpful!
@Engineer4Free
@Engineer4Free 5 жыл бұрын
Derp
@thesunilg
@thesunilg 4 жыл бұрын
@@Engineer4Free if both activity duration is reduced by one day and spent 400+700=1100, then money saved should be 600+600=1200
@hamedahmed5535
@hamedahmed5535 3 жыл бұрын
@@thesunilg No, because you will only save one day not 2 days.
@mmx123
@mmx123 6 жыл бұрын
What do we do when the crash cost for 2 options are exactly the same and both are on critical paths?
@poyax313
@poyax313 5 жыл бұрын
Very nice video. I would like to ask if I can crash activity D directly by 2 days or can just 1 day at a time? why? thanks.
@Engineer4Free
@Engineer4Free 5 жыл бұрын
Always crash one day at a time. You need to find the ES,EF,LS,LF of all impacted activities (which can be many) every time you crash one activity by one day. If you skip this and try to do two days at once, you'll start getting incorrect results.
@ekongekpenyong6320
@ekongekpenyong6320 7 жыл бұрын
Kindly explain why in Run 4 Activity C & Activity D were crashed simultaneously? Agreed they are both on the critical path, but the same situation happened in Runs 1 - 3 and you only crashed the activity having the least additional cost/day.
@alejguz1552
@alejguz1552 Жыл бұрын
awesome!
@merp_pp
@merp_pp 7 жыл бұрын
Hi! Can you clarify why we have to crash C&D together for Run 5? Is it because C is now also on a Critical Path or is there any other factors playing into this? Thanks !
@electriczzmusic
@electriczzmusic 7 жыл бұрын
If you only crash one of them you will not reduce the whole project duration because the other task that you don't crash will remain on the critical path with the same number of days. So yes, that's the only reason why he crashes both together.
@yueyutao1317
@yueyutao1317 4 жыл бұрын
Hi, thanks for the video. I wonder why couldn't you crash the D by 2 days in the first place since D could be crashed for the maximum of 2 days?
@Engineer4Free
@Engineer4Free 4 жыл бұрын
You should always just crash one activity at a time, it's good practise 👍
@tabiafurkan1933
@tabiafurkan1933 2 жыл бұрын
thanks a lot
@Engineer4Free
@Engineer4Free 2 жыл бұрын
You're welcome Tabia ☺️
@mohamedhusseinabouzaid4943
@mohamedhusseinabouzaid4943 2 жыл бұрын
please can you explain how you got the project cost in the last 2 steps (19400 &19800 ??), thank you.
@fatimahhafizahmamat4340
@fatimahhafizahmamat4340 3 жыл бұрын
Thank youu
@Engineer4Free
@Engineer4Free 3 жыл бұрын
You're welcome again!!
@RobAuthor
@RobAuthor 4 жыл бұрын
Appreciate the demonstration, but, if I am not wrong, there are a few mistakes. The TF in Run 2 should be 0 on B and 1 on C. Also, the duration D in Run 3 should be 5 as the Days Saved is 2.
@Engineer4Free
@Engineer4Free 4 жыл бұрын
Hey yeah, see the video description for clarification. I didn’t want to remake the entire video..✌️✌️
@notyourordinary1045
@notyourordinary1045 3 жыл бұрын
I thank you too. Do you have a video where you have two or more paths with two starting points within the activities on a network?
@Engineer4Free
@Engineer4Free 3 жыл бұрын
I cant remember if I have an example with that condition. All of the videos are here: engineer4free.com/project-management If you have two initial activities with no predecessors, just start them both with ES = 0 (or ES = 1 if that's the system you use) an then proceed with the forward and backward pass. When you get back to the beginning, at least one of those initial activities must have a LS = ES, but the rest don't necessarily need to.
@notyourordinary1045
@notyourordinary1045 3 жыл бұрын
@@Engineer4Free That makes sense, thanks
@santiagogarzon5228
@santiagogarzon5228 3 жыл бұрын
I love you bro
@Engineer4Free
@Engineer4Free 3 жыл бұрын
luv u 2
@alejandroh3347
@alejandroh3347 3 жыл бұрын
why do you keep crashing when 0 days of total float, does this not mean there is no float and therefore no time to possibly save
@mmx123
@mmx123 6 жыл бұрын
So in the exercise i have to do we are given months instead of days and the crash cost doesn't specify if it is the overall, per day or per month.... should i still calculate on per month basis??
@Engineer4Free
@Engineer4Free 6 жыл бұрын
Yeah I would think so. The "time-unit" in these problems can be days, weeks, months, or years, etc, but regardless the process is the same. All costs in network diagram problems will typically be given per "time-unit" or per activity, and crashing is per "time-unit" so I would think it's safe to assume that if your problems says something to the effect of "the crash cost of activity A = $1000" then it costs $1000 to crash it by a month.
@farhanfairooz8275
@farhanfairooz8275 5 жыл бұрын
it really great example thank a lost
@Engineer4Free
@Engineer4Free 5 жыл бұрын
You're welcome Farhan, thanks for writing :)
@nexovec
@nexovec 9 ай бұрын
It says the activity E is dependent on an activity F that isn't even there.
@GeorgiusEdo
@GeorgiusEdo 5 жыл бұрын
If I have 26 activities, does that mean I should run 26 iteration? Not to mention that I have 5 parallel paths on my pdm network
@Engineer4Free
@Engineer4Free 5 жыл бұрын
That sounds terrible. Probably not. You want to iterate until the project can't get any shorter. With 5 critical paths, there's probably a trick in your problem that will make it so that you only actually have a crash a few times.
@sirishaburra6807
@sirishaburra6807 6 жыл бұрын
Can we crash non-critical path activities to reduce project time in most economical way?
@Engineer4Free
@Engineer4Free 6 жыл бұрын
If you crash an activity that is not on the critical path, it will not reduce the project duration which will likely defeat the purpose of crashing. Sometimes you sort of need to do this though, like in the event that there are two parallel critical paths.
@ekongekpenyong6320
@ekongekpenyong6320 7 жыл бұрын
kindly disregard my last question: you had mentioned that as both activities are in parallel they must be crashed simultaneously.
@Engineer4Free
@Engineer4Free 6 жыл бұрын
No worries :)
@ecemtezgiden
@ecemtezgiden 5 ай бұрын
Hello, firstly ı want to say thank you but I didn't understand the last part :( why did'nt you crash C and D together for 1 day in Run 5 part?
@tariqfarooq543
@tariqfarooq543 8 күн бұрын
They probably won't be parallel. Parallel mean having same no of float. It's 4 months late, Hope you are project Manager Now, I have exam tomorrow.
@ecemtezgiden
@ecemtezgiden 8 күн бұрын
@@tariqfarooq543 Thank you for the answer. I'm not a PM now, but I became an industrial engineer 😂 This video was very useful for the exam. Good luck bro!
@mohammad2692
@mohammad2692 5 жыл бұрын
you should start crashing with activity D, because it has the lowest cost in the CP , why did you choose activity E instead ??
@Engineer4Free
@Engineer4Free 5 жыл бұрын
In this problem, the "Normal Cost of Activity" does not change if the activity is shortened. I prioritize based on "Additional Cost/day to Crash" for activities on the critical path. Following this, Activity E was the best choice, so it gets crashed first.
@leylasolmaz3978
@leylasolmaz3978 6 жыл бұрын
in run5, why did you put 1 for C's float. I think it should be 2.
@Engineer4Free
@Engineer4Free 6 жыл бұрын
Hey thanks for commenting! It's a little hard to see cause there's so much congestion and different colors and the red 12 is crossed out with a lighter purple that's hard to see, but for C the LF is 11 and the EF after that last crash is 10. 11-10=1. Or alternatively, LS-ES=7-6=1. Does that clear it up?
@leylasolmaz3978
@leylasolmaz3978 6 жыл бұрын
Engineer4Free yes sir, thanks!
@Engineer4Free
@Engineer4Free 6 жыл бұрын
Awesome, thanks for watching!
@kimwang4057
@kimwang4057 3 жыл бұрын
very good. 1100 should be in calcution in run 4 . not 11000.
@Engineer4Free
@Engineer4Free 3 жыл бұрын
Oh whoops! I put a note in the description. Thanks for pointing that out, hope it didn’t confuse anyone else.
@shayrienalina3969
@shayrienalina3969 6 жыл бұрын
how to calculate the project cost
@Engineer4Free
@Engineer4Free 6 жыл бұрын
I recommend watching videos 25-32 here: engineer4free.com/project-management
@taufeqtauf1817
@taufeqtauf1817 8 жыл бұрын
neat
@BurziFreestyle
@BurziFreestyle 2 жыл бұрын
top
@briankyalo7994
@briankyalo7994 4 жыл бұрын
this makes no fucking sense. Why do I have to pay $1900 to pretend to understand this in class when I can learn it here for free?
@Engineer4Free
@Engineer4Free 4 жыл бұрын
Yes
@arvind2041
@arvind2041 8 жыл бұрын
In run 4, you saved 2 days right. So savings column should be 1200(600+600), not 600
@Engineer4Free
@Engineer4Free 8 жыл бұрын
+Arvind Reddy Hey no, run 4 reduces the total project duration by 1 day only (from 15 days to 14 days). We do shorten Activity C by 1 day and also Activity D by 1 day, but it's actually the same day because in run 4 they are both on the critical path. Hope that helps! Also I noticed that I wrote 11,000 instead of 1,100 for the cost of run 4 even when I correctly say its 1,100, sorry if that caused any confusion too!
@arvind2041
@arvind2041 8 жыл бұрын
Thank You so much. It's very helpful.
@ninagad841
@ninagad841 7 жыл бұрын
In run 4 you saved two days and cost per day is 600 so you are saving 1200 not 600 which would lead us to a total project cost of 18.800
@maksympt1
@maksympt1 7 жыл бұрын
you are interpreting it a bit wrong, "days saved" are actually "days saved for the whole project" and not for each activity. in this case we are actually saving only 1 day for the project = 600.
@mathsolution9015
@mathsolution9015 6 жыл бұрын
Can anyone comment on it
@babalolaoladokun3096
@babalolaoladokun3096 2 жыл бұрын
he should speak slowly
Project Management: Crashing a Project
11:20
The Business Doctor
Рет қаралды 78 М.
Earned value analysis worked example
10:32
Engineer4Free
Рет қаралды 488 М.
Just try to use a cool gadget 😍
00:33
123 GO! SHORTS
Рет қаралды 84 МЛН
Универ. 13 лет спустя - ВСЕ СЕРИИ ПОДРЯД
9:07:11
Комедии 2023
Рет қаралды 5 МЛН
World’s Deadliest Obstacle Course!
28:25
MrBeast
Рет қаралды 92 МЛН
Difficult network diagram example with lag solved
12:37
Engineer4Free
Рет қаралды 347 М.
Project crashing full example (part 1/2)
9:35
Engineer4Free
Рет қаралды 302 М.
Project Crashing
12:29
Stephanie Powers
Рет қаралды 43 М.
Operations Management: Project Management - Crashing II
7:51
The Business Doctor
Рет қаралды 16 М.
Project crashing explained
5:59
Engineer4Free
Рет қаралды 196 М.
CPM and PERT
27:26
SHSUOnlineTV
Рет қаралды 543 М.