Wonderful explain and easy to catch..keep rock...all the best
@QuantitySurveyingStudio2 жыл бұрын
Thanks a lot
@kevinasega2823 жыл бұрын
Very informative. Great presentation.
@QuantitySurveyingStudio3 жыл бұрын
Thanks a lot !!!
@vepakrishna75132 жыл бұрын
Very informative, thanks a lot. Below are some of my doubts, I will be thankful, if you can reply. 1) what about the cost of builders work / civil work / indirect work for executing the works listed under PC & PS items? 2) Is Project duration depends on PC & PS Items? 3) If there is a change in the amount or list of items of PC & PS Amount, how it will be treated? 4) What assistance is to be allowed by the Contractor for PS & PS amount items subcontractors Thanks
@QuantitySurveyingStudio2 жыл бұрын
1. It should be included while pricing it 2. It should also be considered. 3. Depending on actual usage, the final amount can reduce or increase. 4. Attendance and coordination percentage can be claimed by main contractor.
@Adnan.44742 жыл бұрын
Very informative, Good job bro 👍👍
@QuantitySurveyingStudio2 жыл бұрын
Thanks a lot.
@manhaseema95902 жыл бұрын
Very use full thank a lot
@QuantitySurveyingStudio2 жыл бұрын
You are welcome !!
@vijaynmr4 жыл бұрын
Very useful and informative video.....
@QuantitySurveyingStudio4 жыл бұрын
Thanks a lot for the positive feedback!!
@salmanameen59592 жыл бұрын
Super informative
@QuantitySurveyingStudio2 жыл бұрын
Thanks a lot !!!
@PradeepKumar-sw8hl2 жыл бұрын
very useful. pls upload related to cesmm explanation videos is possible.
@QuantitySurveyingStudio2 жыл бұрын
Have already uploaded
@vishwazoysa91003 жыл бұрын
Good work , keep it up !
@QuantitySurveyingStudio3 жыл бұрын
Thanks a lot !!!
@priyajain20132 жыл бұрын
Superb
@QuantitySurveyingStudio2 жыл бұрын
Thanks a lot !!
@amosarockiasamy3 жыл бұрын
Very Helpful..
@QuantitySurveyingStudio3 жыл бұрын
Glad to hear that
@john212198113 жыл бұрын
Your videos are very useful and fully appreciated. i have a small clarification regarding the PC rate and provisional sum items, from my expereince not all PC rate and PS items need to be nominated unless the contract specifically states so, correct me if i am wrong
@QuantitySurveyingStudio3 жыл бұрын
Usually these will be done by Nominated sub contractor. Hence the provision for same. If contract specifies the contractor itself to carry out the work, then it will be their responsibility. But ultimately these are priced at later stages.
@mdtouseef69403 жыл бұрын
Does the PC rate remains fixed? Why the contractor will require invoice from supplier to determine the price when it's already mentioned in BOQ? And does it always means that PC rate is the price of only supply of material..and thus it by default means that main contractor scope will be excluding supply of that material?
@qsbestimate34723 жыл бұрын
Quality video
@QuantitySurveyingStudio3 жыл бұрын
Thanks a lot for the positive feedback!!
@mdtouseef69403 жыл бұрын
The nominated sub contractor will be contractually dealing directly with the client or their contract will be with main contractor?
@QuantitySurveyingStudio3 жыл бұрын
Contract will be between main contractor and NSC but the NSC will be decided by client.
@sabhisaini45182 жыл бұрын
Hello sir how can we calculate preliminaries breakdown sheet rates
@QuantitySurveyingStudio2 жыл бұрын
That depends on the quotations and bills of different utilities.
@sabhisaini45182 жыл бұрын
@@QuantitySurveyingStudio sir please make a video on preliminary breakdown sheet 🙏🙏🙏🙏