In this video Tom Stephenson explains how and why changes need to be inserted into a project schedule using MS Project. The video details the impact that change makes on the project schedule.
Пікірлер: 37
@mohasoamakara5085 Жыл бұрын
Hi Tom, I truly appreciate the content of the entire series. I would like to have more on multiple projects, say five to ten for a year.
@TomStephensontraining Жыл бұрын
Take a look at my msproject made easy playlist and i have a video on multiple projects. Thanks for watching
@janee_199 ай бұрын
Hi Tom! I just wanna thank you for these free tutorials. They're all so great and I'm learning a lot.
@TomStephensontraining9 ай бұрын
Happy to help, thanks for watching!
@hamidsk25733 жыл бұрын
really appreciated for all these series, it was really educative for me
@TomStephensontraining3 жыл бұрын
Im happy they help you, more to come!
@1083mohan17 күн бұрын
Great tutorial sir. Easy for beginners
@TomStephensontraining16 күн бұрын
Thanks Mohan!
@psclhys4 ай бұрын
Hi Tom. You are a very effective educator. Very clear speech, well organized, well prepared, etc. I wish I had been in a class of yours back in 1981 when I took a CPM course !! I have a question. Often, with our client, we will agree to extend the "days" of the schedule but not the "cost" of the schedule. This is important for jobs with Liquidated Damages. That means I need to trick MS Project some way so that it doesn't include the daily overhead costs during the time extension. I will be watchful in tutorials after Tutorial 7 to see if you offer a recommended way to do that.
@TomStephensontraining4 ай бұрын
Yes I’m thinking of doing a series of videos just answering and solving questions and problems like you mentioned
@akeemolofing3701 Жыл бұрын
Great video and well explained
@TomStephensontraining Жыл бұрын
Thanks Akee
@MiguelChavez-u1cАй бұрын
Hello Tom, thanks for making these videos. I've learned so much in a couple of days. I have a question; how do I save my date changes when I am extending my schedule. I have a complete schedule for a project and we scheduled it based on our projections, but our customer wants to see the schedule all the way out to their projected date, and we have about a 74-day variance.
@TomStephensontrainingАй бұрын
Hi Miguel Review my videos on baseline updates
@MiguelChavez-u1cАй бұрын
@@TomStephensontraining Thank you Sir!
@jasoncherene68014 жыл бұрын
Thank you! I have been searching for videos on inserting CO's and Delays. If you have any suggestions for other videos to watch regarding CO's and delays, please let me know. Again Thank you.
@TomStephensontraining4 жыл бұрын
If you click subscribe and check the msproject play list you will see more videos, there is one on file naming protocols including changes that is helpful. I will be doing many more in the coming months.
@Emperor279 Жыл бұрын
Hi Tom, really love your videos. I have a question on Change Order. Once we insert the change activities,how do we need to re-baseline as it has impacted cost and schedule. Do i need to make two copies of the baseline ? Any tips ?
@TomStephensontraining Жыл бұрын
Check my MS Project the course video on changes in my playlist. I'm pretty sure I show how to baseline selected tasks e.g. the change order, by doing that you add a baseline only to the change so you can track it as well
@sobc27373 жыл бұрын
Hi Tom, I have a master project plan consisting of 4 different projects(not linked via subproject). I have several tasks going on at the same time. How do I manage resource allocation and scheduling for tasks going on at the same time?
@TomStephensontraining3 жыл бұрын
Hi sorry for the slow reply, It maybe be difficult to do now but you could create a resource oool where your projects share the same resources. Over allocations will appear if there are any.
@irviantantohaditomo87214 жыл бұрын
Dear Tom, when we will use the update project icon? Thank you.
@TomStephensontraining4 жыл бұрын
You can use it instead of some of the ways I indicated in the video. MSproject lets you do the same thing often many different ways. Hope that helps.
@irviantantohaditomo87214 жыл бұрын
@@TomStephensontraining Thank you Sir. In another youtube channel I found some people used the project update for rescheduling the activity. What do you prefer between move the task after tbe status date or used the rescheduling task. Would you please, make the video for this matters. Thank you Sir.
@rishikantmittal68072 жыл бұрын
great way show to incorporate CO
@TomStephensontraining2 жыл бұрын
Yes and it’s important to track them as they have a huge impact on your project. Thanks for watching Rishi!
@Fishwater10002 жыл бұрын
The suggestion made around 23 minute mark is money guys
@TomStephensontraining2 жыл бұрын
Thanks so much, have a great weekend!
@HunterGyp Жыл бұрын
Why wouldn't you just put the start date of this change the day you found out or actually started it instead of linking it as SS+?days?
@TomStephensontraining Жыл бұрын
You certainly can the only issue is that you are using a constraint and that often makes the critical path on the original project before the change disappear by turning blue. In other videos I do it like you said if it is soon to be marked complete it does not matter much.
@HunterGyp Жыл бұрын
@@TomStephensontraining Is the critical path prior to this change important enough to link the starts together. I see that this change is what would drive the schedule and not so much ther previous path, at least where it was inserted at. Maybe if this change was identified a little earlier the previous path would still be applicable enough to need the start link. Just a thought as i went thru all your videos. By the way thanks for those as yours series was by far the best in presenting usable knowledge.
@sangeetkarki9055 Жыл бұрын
Can you provide me your email address .I have many queries regarding project management and also we are working on a software for project management focusing on mid range contractor who cannot afford high end software so your value addition will create remarkable change
@TomStephensontraining Жыл бұрын
Here you go Sangee, I’ll see if i can help but I’m pretty busy tomstephensontraining@gmail.com
@mohi73813 жыл бұрын
really appreciated for all these series, it was really educative for me