Hey Patt, Nice work. Can you upload the process of Resource loading a schedule?
@PJMScheduling3 жыл бұрын
Yes! Great suggestion. Here's the link: kzbin.info/www/bejne/mWTWZ3SLi9Flq5I
@sauravmohanty923 жыл бұрын
Love your work. Just a suggestion, why don't you work on a series of videos where you go from initiation to close-out with every step from setting up the calendar, to adding activities, to resource loading to cost loading to making reports. I think this will be a hit.
@PJMScheduling3 жыл бұрын
Great suggestion! I've completed that series and it starts with this video: kzbin.info/www/bejne/a6TSnXlvlruhm8k
@lordydavilacustodio3552 жыл бұрын
Why is it when I Update my schedule my total budgeted cost will disappear
@PJMScheduling2 жыл бұрын
That's likely because you have "calculate costs from units" checked on your resource assignments and you entered your amounts into the budgeted cost column. You either have to enter the amounts into the budgeted units column, or uncheck the calculate costs from units setting.